Lake Mariner Building 4 completion

Company: TeraWulf

Subject kind
facility timeline
Statement date
2024-06-03
Promised by
2024-06-30
Promised amount
35.0 MW
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

The August 2024 10-Q says Lake Mariner was operating about 195 MW, but no passage names Building 4 or says when it was completed.

“the Lake Mariner Facility is operating approximately 195 MW of bitcoin mining capacity”
2024-08-12 · TeraWulf 10-Q filed 2024-08-13 View cached copy (2026-08-31)Live source ↗

Checked November 4, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Construction of Building 4 (35 MW) at Lake Mariner is on track for completion in June 2024.

Source (primary)

terawulf 8-K exhibit (wulfmay24opsreportdraft0.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-04)Live source ↗

Quote: “Construction of Building 4 (35 MW) at the Lake Mariner facility remains on track for completion in June 2024”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (wulfmay24opsreportdraft0.htm)

Quote: “Construction of Building 4 (35 MW) at the Lake Mariner facility remains on track for completion in June 2024”

View cached copy (2026-11-04)Live source ↗

Record of changes

November 4, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 4, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.