CB-2 data center online

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2025-11-10
Promised by
2025-12-31
Current status
verified

What the later record shows

Delivered late · happened March 31, 2026

CB-2 was not online at 2025 year-end (only 18 MW of HPC). Both CB-2A and CB-2B were delivered by March 31, 2026. The company cited tenant fit-out sequencing as the reason for the delay.

“Certain building milestones were sequenced accordingly, and associated timing impacts have been incorporated into the Company’s financial plan.”
2026-02-25 · terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm) View cached copy (2026-09-13)Live source ↗
“as of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“WULF Den (2 MW) ➢ CB-1 (16 MW) ➢ CB-2A (21 MW) ➢ CB-2B (21 MW) DELIVERED TO DATE(1)”
2026-05-07 · terawulf 8-K exhibit (terawulfq12026investorpr.htm) View cached copy (2026-09-08)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB-2 anticipated to come online around year-end 2025, subject to tenant fit-out requests

Source (primary)

Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗

Quote: “CB-2 anticipated to come online around year-end 2025 subject to tenant fit-out requests”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The presentation states that CB-2 is anticipated to come online around year-end 2025, subject to tenant fit-out requests.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_0c87b48cb4d1c6967968c7d0c3e5933d/terawulf/db/2396/23306/pdf/WULF_Q3_2025_Investor_Update_%28Nov_2025%29vF.pdf) in full (31,442 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Presentation

Quote: “CB-2 anticipated to come online around year-end 2025 subject to tenant fit-out requests”

View cached copy (2026-09-01)Live source ↗

confirms View 10-K PDF

Quote: “as of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms terawulf 8-K exhibit (terawulfq12026investorpr.htm)

Quote: “WULF Den (2 MW) ➢ CB-1 (16 MW) ➢ CB-2A (21 MW) ➢ CB-2B (21 MW) DELIVERED TO DATE(1)”

View cached copy (2026-09-08)Live source ↗

confirms terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm)

Quote: “Certain building milestones were sequenced accordingly, and associated timing impacts have been incorporated into the Company’s financial plan.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 2, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2025-11-10.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.