Building 4 miner slots and 10 EH/s target

Company: TeraWulf

This claim was marked delayed on November 12, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2024-02-01
Promised by
2024-06-30
Promised amount
12000.0 units
Current status
delayed

What the later record shows

The date slipped

The 10-Q reports operational hashrate of 8.0 EH/s as of June 30, 2024, short of the ~10 EH/s mid-2024 target. No passage confirms the 12,000 additional Building 4 slots came online.

“Construction of Building 4 (35 MW) at the Lake Mariner facility remains on track for completion in June 2024”
2024-06-03 · terawulf 8-K exhibit (wulfmay24opsreportdraft0.htm) View cached copy (2026-11-04)Live source ↗
“TeraWulf operational hashrate (EH/s) (4) 12.2 8.0 TeraWulf percentage of global hashrate”
2025-08-07 · TeraWulf 10-Q filed 2025-08-08 View cached copy (2026-08-31)Live source ↗

Checked November 12, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Building 4 will provide over 12,000 additional miner slots, bringing TeraWulf's total operational capacity to approximately 10 EH/s by mid-2024.

Source (primary)

terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-12)Live source ↗

Quote: “which will provide over 12,000 additional miner slots, which would further increase TeraWulf's total operational capacity to approximately 10 EH/s”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm)

Quote: “which will provide over 12,000 additional miner slots, which would further increase TeraWulf's total operational capacity to approximately 10 EH/s”

View cached copy (2026-11-12)Live source ↗

delays TeraWulf 10-Q filed 2025-08-08

Quote: “TeraWulf operational hashrate (EH/s) (4) 12.2 8.0 TeraWulf percentage of global hashrate”

View cached copy (2026-08-31)Live source ↗

delays terawulf 8-K exhibit (wulfmay24opsreportdraft0.htm)

Quote: “Construction of Building 4 (35 MW) at the Lake Mariner facility remains on track for completion in June 2024”

View cached copy (2026-11-04)Live source ↗

Record of changes

November 12, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 12, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.