Lake Mariner Building 3 capacity

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility capacity
Statement date
2023-09-04
Promised by
2023-12-31
Promised amount
43.0 MW
Current status
verified

What the later record shows

Delivered late · happened January 31, 2024

The February 2024 operations update says Building 3, at 45 MW, was energized at Lake Mariner in January 2024, after the year-end 2023 target. It also says more S19j XP miners were expected to be deployed there in early February.

“With the energization of Building 3 (45 MW) at the Lake Mariner facility in January, operational infrastructure capacity at the Lake Mariner facility increased to approximately 160 MW”
2024-02-01 · terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm) View cached copy (2026-11-12)Live source ↗
“The Company expects to deploy an additional 5,000 S19j XPs at Lake Mariner in early February”
2024-02-01 · terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm) View cached copy (2026-11-12)Live source ↗

Checked November 20, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Building 3 at Lake Mariner will house 43 MW of capacity and next-generation Antminer S19j XP bitcoin miners.

Source (primary)

terawulf 8-K exhibit (wulf-20230905xex99.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-20)Live source ↗

Quote: “construction of Building 3, which will house 43 MW of capacity and the next generation Antminer S19j XP bitcoin mining machines”

How we checked this

Checked on November 21, 2026. The cited source supports every part of this claim.

The release says Building 3 at Lake Mariner will house 43 MW of capacity and next-generation Antminer S19j XP miners.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330123000042/wulf-20230905xex99.htm) in full (8,113 characters, retrieved November 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (wulf-20230905xex99.htm)

Quote: “construction of Building 3, which will house 43 MW of capacity and the next generation Antminer S19j XP bitcoin mining machines”

View cached copy (2026-11-20)Live source ↗

confirms terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm)

Quote: “With the energization of Building 3 (45 MW) at the Lake Mariner facility in January, operational infrastructure capacity at the Lake Mariner facility increased to approximately 160 MW”

View cached copy (2026-11-12)Live source ↗

Record of changes

November 20, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 20, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.