Lake Mariner Building 3 capacity
Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory
What the later record shows
Delivered late · happened January 31, 2024
The February 2024 operations update says Building 3, at 45 MW, was energized at Lake Mariner in January 2024, after the year-end 2023 target. It also says more S19j XP miners were expected to be deployed there in early February.
“With the energization of Building 3 (45 MW) at the Lake Mariner facility in January, operational infrastructure capacity at the Lake Mariner facility increased to approximately 160 MW”
2024-02-01 · terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm) View cached copy (2026-11-12)Live source ↗
“The Company expects to deploy an additional 5,000 S19j XPs at Lake Mariner in early February”
2024-02-01 · terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm) View cached copy (2026-11-12)Live source ↗
Checked November 20, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Building 3 at Lake Mariner will house 43 MW of capacity and next-generation Antminer S19j XP bitcoin miners.
Source (primary)
terawulf 8-K exhibit (wulf-20230905xex99.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-20)Live source ↗
Quote: “construction of Building 3, which will house 43 MW of capacity and the next generation Antminer S19j XP bitcoin mining machines”
How we checked this
Checked on November 21, 2026. The cited source supports every part of this claim.
The release says Building 3 at Lake Mariner will house 43 MW of capacity and next-generation Antminer S19j XP miners.
Confirmed in the source:
- Building 3 is at the Lake Mariner facility
- Building 3 will house 43 MW of capacity
- Building 3 will house next-generation Antminer S19j XP bitcoin mining machines
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330123000042/wulf-20230905xex99.htm) in full (8,113 characters, retrieved November 20, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (wulf-20230905xex99.htm)
Quote: “construction of Building 3, which will house 43 MW of capacity and the next generation Antminer S19j XP bitcoin mining machines”
confirms terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm)
Quote: “With the energization of Building 3 (45 MW) at the Lake Mariner facility in January, operational infrastructure capacity at the Lake Mariner facility increased to approximately 160 MW”