jain.com

CB-1 critical IT load 16 MW

Company: TeraWulf

Subject kind
facility capacity
Statement date
2024-10-02
Promised amount
16.0 MW
Current status
stated

The claim, verbatim

CB-1 is a 20 MW colocation building designed to handle 16 MW of critical IT load, with liquid cooling and Tier 3 redundancy.

Source (primary)

terawulf 8-K exhibit (eh240539927_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-26)Live source ↗

Quote: “the Company is constructing a 20 MW colocation building, CB-1, at Lake Mariner, engineered to handle a critical IT load of 16 MW with advanced liquid cooling and Tier 3 redundancy features”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (eh240539927_ex9901.htm)

Quote: “the Company is constructing a 20 MW colocation building, CB-1, at Lake Mariner, engineered to handle a critical IT load of 16 MW with advanced liquid cooling and Tier 3 redundancy features”

View cached copy (2026-10-26)Live source ↗