CB-2 delivery Q4 2025

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

This claim was marked delayed on October 9, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2025-08-13
Promised by
2025-12-31
Current status
delayed

What the later record shows

The date slipped · new target December 31, 2026

CB-2 was not delivered in Q4 2025: only 18 critical IT MW were energized at year-end. The company cited sequencing and timing impacts and said the remaining leases would commence in 2026.

“Certain building milestones were sequenced accordingly, and associated timing impacts have been incorporated into the Company’s financial plan.”
2026-02-25 · terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm) View cached copy (2026-09-13)Live source ↗
“As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB-2 at Lake Mariner is on track for delivery in Q4 2025.

Source (primary)

terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-06)Live source ↗

Quote: “CB - 2 on track for Q4 delivery”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The presentation's 2025 highlights state that CB-2 is on track for Q4 delivery, as part of delivering Core42 capacity at Lake Mariner.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000110465925078086/tm2523008d1_ex99-3.htm) in full (18,636 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (tm2523008d1_ex99-3.htm)

Quote: “CB - 2 on track for Q4 delivery”

View cached copy (2026-10-06)Live source ↗

delays View 10-K PDF

Quote: “As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

delays terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm)

Quote: “Certain building milestones were sequenced accordingly, and associated timing impacts have been incorporated into the Company’s financial plan.”

View cached copy (2026-09-13)Live source ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 7, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.