Lake Mariner Building 3 expansion to 153 MW

Company: TeraWulf

Subject kind
facility capacity
Statement date
2023-08-13
Promised by
2023-12-31
Promised amount
153.0 MW
Current status
verified

What the later record shows

Delivered on time · happened December 31, 2023

The 10-K says Lake Mariner was operating about 160 MW as of December 31, 2023, which exceeds the 153 MW target. A later 10-Q confirms three buildings energized, totalling 160 MW.

“The Lake Mariner Facility is operating approximately 160 MW of bitcoin mining capacity at the site as of December 31, 2023”
2024-03-19 · TeraWulf 10-K filed 2024-03-20 View cached copy (2026-09-13)Live source ↗
“the Company has energized three buildings and additional infrastructure comprising 160 MW of capacity”
2024-05-12 · TeraWulf 10-Q filed 2024-05-13 View cached copy (2026-09-13)Live source ↗

Checked November 21, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf is expanding its wholly owned Lake Mariner facility in New York with Building 3. It expects this to raise operational capacity from 110 MW to 153 MW by year-end 2023.

Source (primary)

terawulf 8-K exhibit (wulf-20230814xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-21)Live source ↗

Quote: “TeraWulf is currently expanding mining operations at its wholly owned Lake Mariner facility in New York with the addition of Building 3, which is expected to increase the facility's operational capacity from 110 MW currently to 153 MW by year-end 2023.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (wulf-20230814xex99d1.htm)

Quote: “TeraWulf is currently expanding mining operations at its wholly owned Lake Mariner facility in New York with the addition of Building 3, which is expected to increase the facility's operational capacity from 110 MW currently to 153 MW by year-end 2023.”

View cached copy (2026-11-21)Live source ↗

confirms TeraWulf 10-Q filed 2024-05-13

Quote: “the Company has energized three buildings and additional infrastructure comprising 160 MW of capacity”

View cached copy (2026-09-13)Live source ↗

confirms TeraWulf 10-K filed 2024-03-20

Quote: “The Lake Mariner Facility is operating approximately 160 MW of bitcoin mining capacity at the site as of December 31, 2023”

View cached copy (2026-09-13)Live source ↗

Record of changes

November 21, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 21, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.