20 MW colocation pilot at Lake Mariner by Q4 2024
Company: TeraWulf
What the later record shows
The date slipped
As of November 2024 the 20 MW colocation project was still under construction. In December 2024 the company moved its HPC delivery target to the end of Q2 2025, and no passage confirms that CB-1 itself was completed in Q4 2024.
“is also constructing a 20 MW colocation project at the Lake Mariner Facility capable of supporting 16 MW of critical IT load”
2024-11-11 · TeraWulf 10-Q filed 2024-11-12 View cached copy (2026-08-31)Live source ↗
“Remain on schedule to deliver 72.5 MW of HPC hosting capacity by the end of Q2 2025”
2024-12-02 · terawulf 8-K exhibit (wulfopsreport-202411nov2.htm) View cached copy (2026-10-24)Live source ↗
Checked November 1, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf is developing a 20 MW colocation pilot facility at Lake Mariner supporting 16 MW of critical IT load with liquid cooling and Tier 3-style redundancy, targeted for completion in Q4 2024 / by year-end.
Source (primary)
terawulf 8-K exhibit (wulfopsreportjun24.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-01)Live source ↗
Quote: “TeraWulf is also designing a 20 MW colocation pilot project at the Lake Mariner site capable of supporting 16 MW of critical IT load with liquid cooling and redundancy requirements typical of a Tier 3 data center, with a target completion date in Q4 2024.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfopsreportjun24.htm)
Quote: “TeraWulf is also designing a 20 MW colocation pilot project at the Lake Mariner site capable of supporting 16 MW of critical IT load with liquid cooling and redundancy requirements typical of a Tier 3 data center, with a target completion date in Q4 2024.”
delays TeraWulf 10-Q filed 2024-11-12
Quote: “is also constructing a 20 MW colocation project at the Lake Mariner Facility capable of supporting 16 MW of critical IT load”
delays terawulf 8-K exhibit (wulfopsreport-202411nov2.htm)
Quote: “Remain on schedule to deliver 72.5 MW of HPC hosting capacity by the end of Q2 2025”