Additional S19j XP deployment to 7.9 EH/s
Company: TeraWulf
What the later record shows
Delivered; the record does not say when
The February 2024 operations report says self-mining hashrate reached the targeted 7.9 EH/s by month-end February. It does not say whether this happened by early February.
“Operational infrastructure capacity at the Lake Mariner facility was 160 MW and TeraWulf’s total self‐ mining hashrate reached 7.9EH/s as of month‐end February”
2024-03-03 · terawulf 8-K exhibit (wulffeb24opsreportdraft0.htm) View cached copy (2026-11-09)Live source ↗
Checked November 12, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf expects to deploy an additional 5,000 S19j XP miners at Lake Mariner in early February 2024, increasing self-mining hashrate about 10% from 7.2 EH/s to 7.9 EH/s.
Source (primary)
terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-12)Live source ↗
Quote: “The Company expects to deploy an additional 5,000 S19j XPs at Lake Mariner in early February, which will increase TeraWulf's self‐ mining hashrate by an additional 10% (from 7.2 EH/s to 7.9 EH/s).”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfjan24opsreport02-1x2.htm)
Quote: “The Company expects to deploy an additional 5,000 S19j XPs at Lake Mariner in early February, which will increase TeraWulf's self‐ mining hashrate by an additional 10% (from 7.2 EH/s to 7.9 EH/s).”
confirms terawulf 8-K exhibit (wulffeb24opsreportdraft0.htm)
Quote: “Operational infrastructure capacity at the Lake Mariner facility was 160 MW and TeraWulf’s total self‐ mining hashrate reached 7.9EH/s as of month‐end February”