CB-2 online date
Company: TeraWulf
What the later record shows
The date slipped · new target March 31, 2026
CB-2 was not fully online around year-end: the campus had only 18 critical IT MW of HPC capacity at December 31, 2025. In February 2026, CB-2A was delivered and CB-2B was still expected in Q1.
“CB-2A delivered (21 MW) ➢ CB-2B: 21 MW expected to be delivered in Q1”
2026-02-26 · Q4 Earnings Update Presentation View cached copy (2026-10-13)Live source ↗Archive.org ↗
“As of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity.”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
CB-2 is anticipated to come online around year-end 2025, subject to tenant fit-out requests.
Source (primary)
Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “CB-2 anticipated to come online around year-end 2025 subject to tenant fit-out requests”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Investor Presentation
Quote: “CB-2 anticipated to come online around year-end 2025 subject to tenant fit-out requests”
delays View 10-K PDF
Quote: “As of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity.”
delays Q4 Earnings Update Presentation
Quote: “CB-2A delivered (21 MW) ➢ CB-2B: 21 MW expected to be delivered in Q1”