Lake Mariner CB3 building energization

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2026-02-25
Promised by
2026-05-15
Promised amount
42.0 MW
Current status
verified

What the later record shows

Delivered late · happened July 31, 2026

Only 81 critical IT MW were energized at June 30, 2026. That is 60 MW Core42 plus about 21 MW, so only part of CB-3 was energized after mid-May. The Q2 deck says CB-3 (42 MW) was operational, with 102 MW energized as of July 2026. The lease amendment also shifted CB-3 from Q2'26 to Q2-Q3'26.

“As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
“102 MW Energized and Generating Lease Revenue as of July 2026 438 MW of Contracted Capacity Targeted for Energization by 1H27 CB - 3 Operational (Lake Mariner Data)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“rentalized CB - 3 Q2’26 Q2 - Q3’26 Monthly TFO Rent Increase +~$60MM Revenue (Over 10 - Year Lease)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB3 building phase (42 MW) energization expected mid-May 2026

Source (primary)

terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-13)Live source ↗

Quote: “CB3 (42 MW) – Energization expected mid-May 2026”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The construction status table lists CB3 at 42 MW with energization expected mid-May 2026.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330126000026/a_wulfearningsrelease2026-.htm) in full (26,590 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm)

Quote: “CB3 (42 MW) – Energization expected mid-May 2026”

View cached copy (2026-09-13)Live source ↗

confirms TeraWulf 10-Q filed 2026-08-05

Quote: “As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”

View cached copy (2026-08-31)Live source ↗

confirms Q2 2026 Earnings Update Presentation

Quote: “102 MW Energized and Generating Lease Revenue as of July 2026 438 MW of Contracted Capacity Targeted for Energization by 1H27 CB - 3 Operational (Lake Mariner Data)”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 14, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.