WULF Den HPC Deployment Q2 2025

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
facility timeline
Statement date
2025-05-08
Promised by
2025-06-30
Promised amount
2.5 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

WULF Den was operating and began recording revenue in July 2025, so the deployment happened. The passages do not show whether it was online by the June 30, 2025 target.

“x WULF Den began recording revenue in July x CB - 1 will begin recording revenue mid - August x CB - 2 on track for Q4 delivery”
2025-08-13 · terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) View cached copy (2026-10-06)Live source ↗
“The Company commenced HPC leasing operations at the Lake Mariner Data Campus in July 2025”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Targeting 2.5 MW critical IT capacity to come online in Q2 2025

Source (primary)

Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Q2 2025: 2.5 MW WULF Den”

How we checked this

Checked on October 10, 2026. The cited source supports part of this claim, but not all of it.

The document targets WULF Den for Q2 2025 at 2.5 MW, but labels that figure as gross capacity. It lists the critical IT capacity as 2.0 MW.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_0c87b48cb4d1c6967968c7d0c3e5933d/terawulf/db/2396/23301/pdf/WULF_Q1_2025_Investor_Pres_vF.pdf) in full (23,307 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Presentation

Quote: “Q2 2025: 2.5 MW WULF Den”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms View 10-K PDF

Quote: “The Company commenced HPC leasing operations at the Lake Mariner Data Campus in July 2025”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms terawulf 8-K exhibit (tm2523008d1_ex99-3.htm)

Quote: “x WULF Den began recording revenue in July x CB - 1 will begin recording revenue mid - August x CB - 2 on track for Q4 delivery”

View cached copy (2026-10-06)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 2, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2025-05-08.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.