CB-2 (50 MW) completion in Q2 2025
Company: TeraWulf
What the later record shows
Partly delivered · new target March 31, 2026
CB-2 was not complete in Q2 2025. By February 2026, half of it (CB-2A, 21 MW) was delivered, and CB-2B (21 MW) was expected in Q1 2026.
“CB-2B: 21 MW expected to be delivered in Q1 ➢ UPS installations for CB-1 and CB-2 are expected to be completed in May”
2026-02-25 · terawulf 8-K exhibit (terawulfq42025investorpr.htm) View cached copy (2026-09-13)Live source ↗
“Construction Updates ➢ Wulf Den & CB-1 delivered (18 MW) ➢ CB-2A delivered (21 MW)”
2026-02-26 · Q4 Earnings Update Presentation View cached copy (2026-10-13)Live source ↗Archive.org ↗
Checked October 26, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The next building, CB-2, has a planned gross capacity of 50 MW and is targeted for completion in Q2 2025.
Source (primary)
terawulf 8-K exhibit (eh240539927_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-26)Live source ↗
Quote: “The next building, CB-2, has a planned gross capacity of 50 MW and is targeted for completion in Q2 2025.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (eh240539927_ex9901.htm)
Quote: “The next building, CB-2, has a planned gross capacity of 50 MW and is targeted for completion in Q2 2025.”