Core42 72.5 MW lease in 2025
Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory
What the later record shows
Partly delivered
Of the 72.5 MW gross committed to Core42, 22.5 MW of HPC capacity was energized and an additional 50 MW was still to be delivered. The remaining leases were expected to commence in 2026.
“the Lake Mariner Campus has 245 MW of energized capacity supporting bitcoin mining infrastructure and has energized 22.5 MW of HPC leasing capacity”
2025-11-09 · TeraWulf 10-Q filed 2025-11-10 View cached copy (2026-08-31)Live source ↗
“TeraWulf remains on track to deliver an additional 50 MW of HPC leasing capacity under its datacenter lease agreements with Core42 Holding US LLC”
2025-11-09 · TeraWulf 10-Q filed 2025-11-10 View cached copy (2026-08-31)Live source ↗
“Certain of the Core42 HPC Leases commenced in 2025 and the remainder of the HPC Leases are expected to commence in 2026.”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked October 13, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Core42 leases 72.5 MW of gross HPC hosting capacity at Lake Mariner, delivered in 2025.
Source (primary)
Q2 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-13)Live source ↗
Quote: “Core42: 72.5 MW in 2025”
How we checked this
Checked on October 15, 2026. The cited source supports part of this claim, but not all of it.
The document confirms Core42's 72.5 MW gross lease at Lake Mariner and schedules it for 2025, but it only says the capacity was planned for 2025, not that it was delivered.
Confirmed in the source:
- Core42 leases 72.5 MW at Lake Mariner
- The 72.5 MW is gross contracted HPC hosting capacity
- The capacity overview lists Core42's 72.5 MW for 2025
We could not confirm this from the cited source:
- That the full 72.5 MW was actually delivered in 2025 (the August 2025 document shows only planned 2025 deployment, with CB-2 still pending Q4 delivery)
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_513c80c486e62e4bdb70115ded3782f5/terawulf/db/2396/23302/pdf/WULF_Q2_2025_Investor_Update_%28Aug_2025%29vF.pdf) in full (17,599 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.