Core42 72.5 MW lease in 2025

Company: TeraWulf - Project: Lake Mariner Anthropic AI Factory

Subject kind
customer
Statement date
2025-08-14
Promised by
2025-12-31
Promised amount
72.5 MW
Current status
outcome unconfirmed

What the later record shows

Partly delivered

Of the 72.5 MW gross committed to Core42, 22.5 MW of HPC capacity was energized and an additional 50 MW was still to be delivered. The remaining leases were expected to commence in 2026.

“the Lake Mariner Campus has 245 MW of energized capacity supporting bitcoin mining infrastructure and has energized 22.5 MW of HPC leasing capacity”
2025-11-09 · TeraWulf 10-Q filed 2025-11-10 View cached copy (2026-08-31)Live source ↗
“TeraWulf remains on track to deliver an additional 50 MW of HPC leasing capacity under its datacenter lease agreements with Core42 Holding US LLC”
2025-11-09 · TeraWulf 10-Q filed 2025-11-10 View cached copy (2026-08-31)Live source ↗
“Certain of the Core42 HPC Leases commenced in 2025 and the remainder of the HPC Leases are expected to commence in 2026.”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 13, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Core42 leases 72.5 MW of gross HPC hosting capacity at Lake Mariner, delivered in 2025.

Source (primary)

Q2 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-10-13)Live source ↗

Quote: “Core42: 72.5 MW in 2025”

How we checked this

Checked on October 15, 2026. The cited source supports part of this claim, but not all of it.

The document confirms Core42's 72.5 MW gross lease at Lake Mariner and schedules it for 2025, but it only says the capacity was planned for 2025, not that it was delivered.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of IR page (investors.terawulf.com) (https://d1io3yog0oux5.cloudfront.net/_513c80c486e62e4bdb70115ded3782f5/terawulf/db/2396/23302/pdf/WULF_Q2_2025_Investor_Update_%28Aug_2025%29vF.pdf) in full (17,599 characters, retrieved October 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Q2 Earnings Update Presentation

Quote: “Core42: 72.5 MW in 2025”

View cached copy (2026-10-13)Live source ↗

Record of changes

October 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 13, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.