72.5 MW HPC capacity delivery in 2025
Company: TeraWulf
What the later record shows
Partly delivered
WULF Den and CB-1 of the 72.5 MW Core42 capacity began recording revenue in July/August 2025, and certain Core42 leases commenced in 2025. CB-2 was only described as on track for Q4, and no passage confirms its completion.
“x WULF Den began recording revenue in July x CB - 1 will begin recording revenue mid - August x CB - 2 on track for Q4 delivery”
2025-08-13 · terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) View cached copy (2026-10-06)Live source ↗
“Certain of the Core42 HPC Leases commenced in 2025 and the remainder of the HPC Leases are expected to commence in 2026.”
2025-11-09 · TeraWulf 10-Q filed 2025-11-10 View cached copy (2026-08-31)Live source ↗
Checked October 18, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf is focused on executing 72.5 MW of HPC hosting capacity set for delivery in 2025.
Source (primary)
terawulf 8-K exhibit (a_wulfformearningsrelease2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-18)Live source ↗
Quote: “our focus is on executing the 72.5 MW of HPC hosting capacity set for delivery in 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (a_wulfformearningsrelease2.htm)
Quote: “our focus is on executing the 72.5 MW of HPC hosting capacity set for delivery in 2025”