CB-2 50 MW HPC facility delivery
Company: TeraWulf
What the later record shows
The date slipped · new target December 31, 2025
An August 13, 2025 release says CB-2 is 'on track for Q4 delivery', which is after the end-of-Q2 2025 target. No passage confirms it was later completed.
“x CB - 1 will begin recording revenue mid - August x CB - 2 on track for Q4 delivery x 10 - year, $3.7Bn hyperscale lease with Fluidstack”
2025-08-13 · terawulf 8-K exhibit (tm2523008d1_ex99-3.htm) View cached copy (2026-10-06)Live source ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Preparations for CB-2, a 50 MW HPC hosting facility, are progressing. Key components have been secured, and delivery is expected by the end of Q2 2025.
Source (primary)
terawulf 8-K exhibit (wulfopsreport-202410oct2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “Preparations for CB-2, a 50 MW HPC hosting facility, are also progressing as key components have already been secured, ensuring timely delivery by the end of Q2 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfopsreport-202410oct2.htm)
Quote: “Preparations for CB-2, a 50 MW HPC hosting facility, are also progressing as key components have already been secured, ensuring timely delivery by the end of Q2 2025”
delays terawulf 8-K exhibit (tm2523008d1_ex99-3.htm)
Quote: “x CB - 1 will begin recording revenue mid - August x CB - 2 on track for Q4 delivery x 10 - year, $3.7Bn hyperscale lease with Fluidstack”