CB-3 delivery

Company: TeraWulf

Subject kind
facility timeline
Statement date
2026-02-26
Promised by
2026-05-31
Promised amount
42.0 MW
Current status
verified

What the later record shows

Delivered late · happened July 31, 2026

Energized HPC capacity was 81 MW at June 30, 2026, which is only 21 MW above the 60 MW delivered before CB-3. It reached 102 MW as of July 2026, when CB-3 (42 MW) was listed as delivered and operational, so full delivery came after the May target.

“As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
“102 MW Energized and Generating Lease Revenue as of July 2026”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-11-05)Live source ↗Archive.org ↗
“DELIVERED 102 MW ➢ WULF Den (2 MW) ➢ CB - 1 (16 MW) ➢ CB - 2A (21 MW) ➢ CB - 2B (21 MW) ➢ CB - 3 (42 MW)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-11-05)Live source ↗Archive.org ↗

Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

CB-3, 42 MW of critical IT capacity, is scheduled for delivery in May 2026, with the estimated lease start moved from 3/15/26 to May.

Source (primary)

Q4 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗

Quote: “CB-3 (42 MW, May)”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Q4 Earnings Update Presentation

Quote: “CB-3 (42 MW, May)”

View cached copy (2026-11-06)Live source ↗Archive.org ↗

confirms TeraWulf 10-Q filed 2026-08-05

Quote: “As of June 30, 2026, TeraWulf had energized 81 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus.”

View cached copy (2026-08-31)Live source ↗

confirms Q2 2026 Earnings Update Presentation

Quote: “102 MW Energized and Generating Lease Revenue as of July 2026”

View cached copy (2026-11-05)Live source ↗Archive.org ↗

Record of changes

November 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 6, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.