Promised amount
1.5 million USD per MW
Current status
stated

The claim, verbatim

12-month prepay for CB-1 and CB-2 assumed at $1.5 million per MW

Source (primary)

Nautilus Sale Announcement (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Estimated HPC Revenue Prepay assumes 12-month prepay for 20 MW CB-1 and 50 MW CB-2 at $1.5M per MW”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Nautilus Sale Announcement

Quote: “Estimated HPC Revenue Prepay assumes 12-month prepay for 20 MW CB-1 and 50 MW CB-2 at $1.5M per MW”