CB-2 50 MW AI/HPC facility completion early Q2 2025

Company: TeraWulf

Subject kind
facility timeline
Statement date
2024-10-03
Promised by
2025-04-30
Promised amount
50.0 MW
Current status
outcome unconfirmed

What the later record shows

Partly delivered · new target March 31, 2026

CB-2 slipped from early Q2 2025, first to Q4 2025 and then past its prior 11/30/25 lease start. By February 2026, CB-2A (21 MW) was delivered and CB-2B (21 MW) was still expected in Q1 2026.

“Q2 2025: 2.5 MW WULF Den ➢ Q3 2025: 20 MW CB-1 ➢ Q4 2025: 50 MW CB-2”
2025-05-08 · Investor Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“CB-2B: 21 MW expected to be delivered in Q1 ➢ UPS installations for CB-1 and CB-2 are expected to be completed in May”
2026-02-25 · terawulf 8-K exhibit (terawulfq42025investorpr.htm) View cached copy (2026-09-13)Live source ↗
“Construction Updates ➢ Wulf Den & CB-1 delivered (18 MW) ➢ CB-2A delivered (21 MW)”
2026-02-26 · Q4 Earnings Update Presentation View cached copy (2026-10-13)Live source ↗Archive.org ↗
“Estimated Lease Start Date Prior Current Late Delivery Credits CB-2 11/30/25 Q1 None”
2026-02-26 · Q4 Earnings Update Presentation View cached copy (2026-10-13)Live source ↗Archive.org ↗

Checked October 26, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf has secured long-lead items for CB-2, a 50 MW AI/HPC facility, targeting completion in early Q2 2025.

Source (primary)

terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-26)Live source ↗

Quote: “We’ve also secured long-lead items for CB-2, a 50 MW AI/HPC facility, to ensure timely completion in early Q2 2025.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (wulfopsreportsep2410-03x.htm)

Quote: “We’ve also secured long-lead items for CB-2, a 50 MW AI/HPC facility, to ensure timely completion in early Q2 2025.”

View cached copy (2026-10-26)Live source ↗

Record of changes

October 26, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 26, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.