WULF Den 2 MW AI/HPC GPU pilot by Q3 2024

Company: TeraWulf

This claim was marked delayed on November 1, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2024-07-02
Promised by
2024-09-30
Promised amount
2.0 MW
Current status
delayed

What the later record shows

The date slipped

In August 2024 the WULF Den was still under construction. The Q3 2024 10-Q says the company operated only bitcoin mining facilities through September 30 and still describes the 2.5 MW HPC block as a targeted commitment, which suggests it was not complete by Q3. No new date is given.

“progress continues on the previously announced construction of a 2 MW AI/HPC digital infrastructure proof-of- concept building”
2024-08-04 · terawulf 8-K exhibit (wulfjuly2024opsreport08-.htm) View cached copy (2026-10-31)Live source ↗
“the Company only operated bitcoin mining facilities; however, the Company has targeted an initial commitment for an allocation of a 2.5 MW power block”
2024-11-11 · TeraWulf 10-Q filed 2024-11-12 View cached copy (2026-08-31)Live source ↗

Checked November 1, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf is finalizing the 2 MW 'WULF Den' AI/HPC pilot at Lake Mariner to house latest-generation GPUs, targeted for completion by the third quarter of 2024.

Source (primary)

terawulf 8-K exhibit (wulfopsreportjun24.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-01)Live source ↗

Quote: “finalizing the 2 MW pilot project, known as the 'WULF Den,' which will house and operate the latest generation GPUs and is targeted for completion by the third quarter”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (wulfopsreportjun24.htm)

Quote: “finalizing the 2 MW pilot project, known as the 'WULF Den,' which will house and operate the latest generation GPUs and is targeted for completion by the third quarter”

View cached copy (2026-11-01)Live source ↗

delays TeraWulf 10-Q filed 2024-11-12

Quote: “the Company only operated bitcoin mining facilities; however, the Company has targeted an initial commitment for an allocation of a 2.5 MW power block”

View cached copy (2026-08-31)Live source ↗

delays terawulf 8-K exhibit (wulfjuly2024opsreport08-.htm)

Quote: “progress continues on the previously announced construction of a 2 MW AI/HPC digital infrastructure proof-of- concept building”

View cached copy (2026-10-31)Live source ↗

Record of changes

November 1, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 1, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 1, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.