WULF Den 2 MW AI/HPC GPU pilot by Q3 2024
Company: TeraWulf
What the later record shows
The date slipped
In August 2024 the WULF Den was still under construction. The Q3 2024 10-Q says the company operated only bitcoin mining facilities through September 30 and still describes the 2.5 MW HPC block as a targeted commitment, which suggests it was not complete by Q3. No new date is given.
“progress continues on the previously announced construction of a 2 MW AI/HPC digital infrastructure proof-of- concept building”
2024-08-04 · terawulf 8-K exhibit (wulfjuly2024opsreport08-.htm) View cached copy (2026-10-31)Live source ↗
“the Company only operated bitcoin mining facilities; however, the Company has targeted an initial commitment for an allocation of a 2.5 MW power block”
2024-11-11 · TeraWulf 10-Q filed 2024-11-12 View cached copy (2026-08-31)Live source ↗
Checked November 1, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf is finalizing the 2 MW 'WULF Den' AI/HPC pilot at Lake Mariner to house latest-generation GPUs, targeted for completion by the third quarter of 2024.
Source (primary)
terawulf 8-K exhibit (wulfopsreportjun24.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-01)Live source ↗
Quote: “finalizing the 2 MW pilot project, known as the 'WULF Den,' which will house and operate the latest generation GPUs and is targeted for completion by the third quarter”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfopsreportjun24.htm)
Quote: “finalizing the 2 MW pilot project, known as the 'WULF Den,' which will house and operate the latest generation GPUs and is targeted for completion by the third quarter”
delays TeraWulf 10-Q filed 2024-11-12
Quote: “the Company only operated bitcoin mining facilities; however, the Company has targeted an initial commitment for an allocation of a 2.5 MW power block”
delays terawulf 8-K exhibit (wulfjuly2024opsreport08-.htm)
Quote: “progress continues on the previously announced construction of a 2 MW AI/HPC digital infrastructure proof-of- concept building”