Lake Mariner power block data center expansion completed

Company: TeraWulf

Subject kind
facility timeline
Statement date
2023-07-05
Promised amount
4700.0 units
Current status
stated

The claim, verbatim

The expansion of the former power block data center area at Lake Mariner was completed near the end of June 2023 and now holds more than 4,700 miners (0.5 EH/s).

Source (primary)

terawulf 8-K exhibit (wulf-20230706xex99.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-22)Live source ↗

Quote: “The expansion of the former power block data center area at the Lake Mariner facility was completed near the end of June, which now holds more than 4,700 miners (or 0.5 EH/s)”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (wulf-20230706xex99.htm)

Quote: “The expansion of the former power block data center area at the Lake Mariner facility was completed near the end of June, which now holds more than 4,700 miners (or 0.5 EH/s)”