Polaris Forge 1
Project of Applied Digital
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 175 MW | 2026-09-01 | Polaris Forge 1 total live capacity 175 MW |
| Contracted a customer is on the hook | 400 MW IT load | 2026-09-01 | CoreWeave Polaris Forge 1 lease |
| Under construction | 250 MW | 2025-07-29 | Polaris Forge 1 under construction capacity |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 1,000 MW IT load | 2026-09-01 | Polaris Forge 1 designed to scale to 1 gigawatt total capacity |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2024-08-28
Undisclosed counterparty (one or more) - tenant · 400 MW source
2026-09-01
Marathon Digital Holdings - offtaker source
Claims about this project
2024-05-16 - delayed
HPC Ellendale Operational Start. Promised by 2025-01-01.
2024-05-16 - stated
HPC Ellendale Facility Construction 100.0 MW.
2024-05-30 - delayed
2024-06-06 - stated
2024-06-16 - stated
2024-08-28 - delayed
Extended LOI exclusivity period for Ellendale campus. Promised by 2024-07-26.
2024-08-28 - stated
2024-08-28 - stated
400 MW LOI with US-based hyperscaler 400.0 MW.
2024-08-29 - stated
2024-08-29 - stated
2024-08-29 - stated
2024-08-29 - stated
2024-08-29 - stated
2024-08-29 - stated
2024-08-29 - stated
2024-08-29 - stated
Ellendale HPC data center groundbreaking 100.0 MW.
2024-08-29 - stated
2024-08-29 - stated
2024-08-29 - stated
2024-08-29 - stated
Hyperscaler capacity lease commitment 400.0 MW.
2024-08-29 - stated
2024-09-10 - stated
2024-09-10 - stated
2024-09-10 - delayed
Hyperscaler exclusivity extension for HPC Ellendale Facility. Promised by 2024-07-26.
2024-09-10 - stated
2024-09-10 - stated
400 MW capacity lease with hyperscaler 400.0 MW.
2024-09-10 - stated
2024-10-03 - stated
HPC Ellendale Facility capacity 100.0 MW.
2024-10-03 - delayed
HPC Ellendale Facility operational timeline. Promised by 2025-12-31.
2024-10-17 - delayed
2024-11-14 - stated
100 MW Ellendale building construction 100.0 MW.
2024-11-21 - stated
2024-11-21 - stated
2024-12-01 - delayed
ELN-02 Project completion deadline. Promised by 2025-12-06.
2025-01-07 - stated
Entry into lease with hyperscaler for 100MW Building A. Promised by 2027-12-31.
2025-01-07 - stated
2025-01-07 - stated
Real estate project financing for Building A construction. Promised by 2027-12-31.
2025-01-07 - stated
Entry into lease with hyperscaler for 100MW Building B. Promised by 2027-12-31.
2025-01-07 - stated
2025-07-29 - stated
Polaris Forge 1 total planned capacity 400.0 MW.
2025-07-29 - stated
2025-07-29 - stated
2025-07-29 - stated
2025-07-29 - stated
2025-07-29 - stated
Polaris Forge 1 total planned capacity 400.0 MW.
2025-07-29 - stated
Polaris Forge 1 third building capacity 150.0 MW.
2025-07-29 - stated
Polaris Forge 1 second building capacity 150.0 MW.
2025-07-29 - stated
2025-07-29 - stated
Polaris Forge 1 lease agreements 250.0 MW.
2025-07-29 - stated
2025-07-29 - stated
Polaris Forge 1 first building capacity 100.0 MW.
2025-07-29 - stated
Polaris Forge 1 campus total capacity 400.0 MW.
2025-07-29 - delayed
Polaris Forge 1 operational start. Promised by 2025-12-31.
2025-07-29 - stated
Polaris Forge 1 leased capacity 250.0 MW.
2025-07-29 - delayed
Polaris Forge 1 first building operational date. Promised by 2025-12-31.
2025-07-29 - stated
2025-07-29 - stated
2025-08-14 - stated
2025-08-28 - stated
2025-08-28 - stated
Building 4 Lease contract value 4000000000.0 USD.
2025-08-28 - stated
Polaris Forge 1 total capacity 400.0 MW.
2025-08-28 - stated
2025-08-28 - stated
Building 4 capacity 150.0 MW.
2025-09-02 - stated
2025-09-11 - stated
CoreWeave 15-year lease agreement for Polaris Forge 1 11000000000.0 USD.
2025-09-11 - stated
Polaris Forge 1 design capacity 1.0 GW.
2025-09-11 - delayed
Polaris Forge 1 phased rollout. Promised by 2025-12-31.
2025-09-21 - delayed
2025-09-21 - stated
2025-09-21 - stated
CoreWeave Polaris Forge 1 lease agreement 11000000000.0 USD.
2025-10-08 - stated
Conditional Macquarie investment obligation in Polaris Forge 1 250.0 million USD. Promised by 2028-04-06.
2025-10-08 - stated
Polaris Forge 1 data center capacity 100.0 MW.
2025-10-08 - stated
Total potential Macquarie investment in Polaris Forge 1 450.0 million USD.
2025-10-08 - stated
Macquarie conditional investment right for Polaris Forge 1 additional phases 337.5 million USD.
2025-10-08 - delayed
Macquarie Asset Management investment partnership closed. Promised by 2025-10-06.
2025-10-08 - stated
Applied Digital equity contributions to Polaris Forge 1 990.0 million USD.
2025-10-08 - stated
Warrants issued to Macquarie affiliates 2400000.0 shares.
2025-10-08 - stated
2025-10-08 - delayed
2025-10-09 - stated
2025-10-09 - delayed
2025-10-09 - delayed
2025-10-09 - stated
CoreWeave lease - $11 billion total contracted revenue 11000.0 USD millions.
2025-10-09 - stated
Macquarie preferred equity - $112.5 million drawn from $5 billion facility 112.5 USD millions.
2025-10-09 - delayed
2025-10-09 - delayed
2025-10-09 - stated
2025-10-09 - stated
2025-11-19 - stated
Data center ELN-03 at Ellendale campus 150.0 MW.
2025-11-19 - stated
Data center ELN-02 at Ellendale campus 100.0 MW.
2025-12-04 - stated
2025-12-04 - stated
Polaris Forge 1 ELN-02 Operations 100.0 MW.
2025-12-04 - stated
2025-12-04 - stated
CoreWeave Warrant Issuance 8393611.0 shares.
2025-12-04 - stated
Macquarie Warrant Issuance 2.4 shares.
2025-12-04 - stated
2025-12-04 - stated
2026-01-07 - stated
Ellendale data center fully leased 400.0 MW.
2026-02-08 - stated
Polaris Forge 1 data center capacity 400.0 MW.
2026-03-12 - stated
2026-03-31 - stated
2026-03-31 - delayed
2026-03-31 - stated
2026-03-31 - stated
2026-03-31 - stated
2026-03-31 - stated
ELN-02 data center capacity 100.0 MW.
2026-03-31 - stated
2026-03-31 - stated
2026-03-31 - stated
ELN-03 data center capacity 150.0 MW.
2026-06-08 - stated
2026-06-08 - stated
2026-06-08 - stated
2026-06-16 - stated
2026-07-28 - stated
2026-07-28 - stated
2026-07-28 - stated
2026-07-28 - stated
2026-07-28 - delayed
2026-07-28 - stated
CoreWeave leases at Polaris Forge 1 400.0 MW.
2026-07-28 - stated
2026-07-28 - stated
Polaris Forge 1 second data center 150.0 MW.
2026-07-28 - stated
2026-07-28 - stated
2026-07-28 - stated
CoreWeave leases at Polaris Forge 1 400.0 MW.
2026-07-28 - delayed
2026-08-13 - stated
CoreWeave 400 MW Polaris Forge 1 contract 11000000000.0 USD.
2026-08-18 - stated
2026-08-22 - stated
$300 million bridge facility for Polaris Forge 1 300.0 million USD.
2026-08-22 - delayed
2026-08-22 - stated
2026-08-22 - stated
2026-08-22 - stated
2026-08-22 - stated
$1.59 billion senior secured notes for Polaris Forge 1 building 4 1.59 billion USD.
2026-08-22 - stated
2026-08-22 - stated
2026-08-22 - stated
2026-08-24 - stated
Polaris Forge 1 operational capacity 175.0 MW.
2026-08-24 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - delayed
2026-09-01 - stated
2026-09-01 - delayed
Third facility groundbreaking Q3 2022. Promised by 2022-09-30.
2026-09-01 - stated
CoreWeave Lease Enhancement and Credit Support 50.0 million USD.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - delayed
2026-09-01 - delayed
2026-09-01 - stated
$1.59B 7.000% Senior Secured Notes offering 1.59 billion USD.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
$50 million letter of credit from CoreWeave 50000000.0 USD.
2026-09-01 - stated
CoreWeave lease agreement - Polaris Forge 1 11000000000.0 USD.
2026-09-01 - stated
2026-09-01 - stated
Polaris Forge 1 ultimate capacity target 1000.0 MW.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
Ellendale, ND facility planned capacity 180.0 MW.
2026-09-01 - stated
2026-09-01 - stated
$300M senior secured bridge facility 300.0 million USD.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
Macquarie up to $900 million investment in Ellendale HPC campus 900000000.0 USD.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - delayed
2026-09-01 - delayed
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
Polaris Forge 1 Phase 2 expansion 150.0 MW.
2026-09-01 - stated
2026-09-01 - stated
Polaris Forge 1 CoreWeave leases 400.0 MW.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - delayed
APLD ELN-02 Holdings $150 million senior secured debt from Macquarie Equipment Capital 150000000.0 USD. Promised by 2024-11-27.
2026-09-01 - delayed
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
Polaris Forge 1 CoreWeave leases 400.0 MW.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
CoreWeave lease credit enhancements with $50 million letter of credit 50.0 million USD.
2026-09-01 - stated
2026-09-01 - delayed
2026-09-01 - delayed
2026-09-01 - stated
CoreWeave 150MW lease option for additional capacity 4000.0 million USD.
2026-09-01 - stated
CoreWeave 250MW lease agreements at Polaris Forge 1 7000.0 million USD.
2026-09-01 - delayed
2026-09-01 - delayed
Ellendale HPC facility ready for service. Promised by 2025-12-31.