Polaris Forge 1

Project of Applied Digital

Kind
campus
Location
9685 87th Ave SE, Ellendale, ND
County
Dickey County
State/region
ND
Country
US
Status
announced

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today175 MW2026-09-01Polaris Forge 1 total live capacity 175 MW
Contracted a customer is on the hook400 MW IT load2026-09-01CoreWeave Polaris Forge 1 lease
Under construction250 MW2025-07-29Polaris Forge 1 under construction capacity
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure1,000 MW IT load2026-09-01Polaris Forge 1 designed to scale to 1 gigawatt total capacity

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2024-08-28
Undisclosed counterparty (one or more) - tenant · 400 MW source
2025-05-28
CoreWeave - anchor tenant · 400 MW · 15-year term source
2026-03-31
CoreWeave - guarantor source
2026-09-01

Claims about this project

2024-05-16 - delayed
HPC Ellendale Operational Start. Promised by 2025-01-01.
2024-05-16 - stated
2024-05-30 - delayed
HPC Ellendale Facility under construction 100.0 MW. Promised by 2025-01-01.
2024-08-28 - delayed
2024-08-28 - stated
2024-08-29 - stated
2024-08-29 - stated
2024-08-29 - stated
2024-08-29 - stated
2024-08-29 - stated
2024-09-10 - delayed
2024-09-10 - stated
2024-10-03 - stated
2024-10-03 - delayed
2024-10-17 - delayed
Ellendale HPC facility expected operational date 100.0 MW. Promised by 2025-12-31.
2024-11-14 - stated
2024-12-01 - delayed
ELN-02 Project completion deadline. Promised by 2025-12-06.
2025-01-07 - stated
2025-01-07 - stated
2025-01-07 - stated
2025-07-29 - stated
2025-07-29 - stated
2025-07-29 - stated
2025-07-29 - stated
2025-07-29 - stated
2025-07-29 - stated
2025-07-29 - stated
2025-07-29 - stated
2025-07-29 - stated
2025-07-29 - delayed
Polaris Forge 1 operational start. Promised by 2025-12-31.
2025-07-29 - stated
2025-07-29 - delayed
2025-08-28 - stated
2025-08-28 - stated
2025-08-28 - stated
2025-08-28 - stated
2025-09-11 - stated
2025-09-11 - stated
2025-09-11 - delayed
Polaris Forge 1 phased rollout. Promised by 2025-12-31.
2025-09-21 - delayed
Polaris Forge 1 first phase 100 MW operational 100.0 MW. Promised by 2025-12-31.
2025-09-21 - stated
Polaris Forge 1 additional 150 MW expansion 150.0 MW. Promised by 2027-12-31.
2025-09-21 - stated
2025-10-08 - stated
Conditional Macquarie investment obligation in Polaris Forge 1 250.0 million USD. Promised by 2028-04-06.
2025-10-08 - stated
2025-10-08 - stated
2025-10-08 - delayed
2025-10-08 - stated
2025-10-08 - stated
2025-10-08 - delayed
Initial Macquarie investment closed 112.5 million USD. Promised by 2025-10-06.
2025-10-09 - delayed
Polaris Forge 1 - 100 MW building completion 100.0 MW. Promised by 2025-12-31.
2025-10-09 - delayed
2025-10-09 - stated
2025-10-09 - delayed
HPC Hosting - 100 MW facility operational Q4 2025 100.0 MW. Promised by 2025-12-31.
2025-10-09 - delayed
HPC Hosting - 150 MW facility scheduled mid-2026 150.0 MW. Promised by 2026-06-30.
2025-10-09 - stated
HPC Hosting - 150 MW facility planned 2027 150.0 MW. Promised by 2027-12-31.
2025-10-09 - stated
2025-11-19 - stated
2025-11-19 - stated
2025-12-04 - stated
2025-12-04 - stated
2025-12-04 - stated
CoreWeave Warrant Issuance 8393611.0 shares.
2025-12-04 - stated
2026-01-07 - stated
2026-02-08 - stated
2026-03-12 - stated
2026-03-31 - stated
2026-03-31 - delayed
ELN-02 Letter of Credit commitment 50000000.0 USD. Promised by 2026-04-29.
2026-03-31 - stated
2026-03-31 - stated
2026-03-31 - stated
2026-03-31 - stated
2026-07-28 - stated
2026-07-28 - delayed
Polaris Forge 1 - First HPC data center operational 100.0 MW. Promised by 2025-10-31.
2026-07-28 - stated
2026-07-28 - stated
Polaris Forge 1 third data center delivery timeline 150.0 MW. Promised by 2027-12-31.
2026-07-28 - stated
2026-07-28 - stated
Polaris Forge 1 third facility ready-for-service 150.0 MW. Promised by 2027-12-31.
2026-07-28 - stated
2026-07-28 - delayed
Polaris Forge 1 first facility operational 100.0 MW. Promised by 2025-10-01.
2026-08-13 - stated
2026-08-22 - stated
2026-08-22 - delayed
Polaris Forge 1 Building 2 capacity addition 75.0 MW. Promised by 2026-06-30.
2026-08-24 - stated
2026-09-01 - delayed
Ellendale first 100 MW HPC facility 100.0 MW. Promised by 2025-12-31.
2026-09-01 - delayed
Third facility groundbreaking Q3 2022. Promised by 2022-09-30.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - delayed
2026-09-01 - delayed
2026-09-01 - stated
2026-09-01 - stated
Polaris Forge 1 third data center 150.0 MW. Promised by 2027-12-31.
2026-09-01 - stated
$1.59 billion Senior Secured Notes offering 1590000000.0 USD. Promised by 2031-12-31.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
$1.59B Senior Secured Notes due 2031 1.59 billion USD. Promised by 2031-01-01.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - delayed
Polaris Forge 1 Building 1 Operational 100.0 MW. Promised by 2025-10-31.
2026-09-01 - delayed
Polaris Forge 1 first phase operational date 100.0 MW. Promised by 2025-12-31.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
Polaris Forge 1 third 150 MW facility expected 2027 150.0 MW. Promised by 2027-12-31.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
CoreWeave Polaris Forge 1 lease 400.0 MW. Promised by 2027-06-30.
2026-09-01 - delayed
2026-09-01 - delayed
Polaris Forge 1 Building 2 Phase 1 Delivered 75.0 MW. Promised by 2026-06-30.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
Polaris Forge 1 Phase 3 ready-for-service date 150.0 MW. Promised by 2027-12-31.
2026-09-01 - stated
Polaris Forge 1 third 150 MW facility 150.0 MW. Promised by 2027-12-31.
2026-09-01 - stated
Polaris Forge 1 second 150 MW facility 150.0 MW. Promised by 2026-12-31.
2026-09-01 - delayed
2026-09-01 - delayed
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - delayed
Ellendale building 369,000+ square feet 369000.0 square feet. Promised by 2025-12-31.
2026-09-01 - delayed