Polaris Forge 1 Building 2 Phase 1 Ready for Service
Company: Applied Digital - Project: Polaris Forge 1
The claim, verbatim
Phase 1 of Building 2 (75 MW) at Polaris Forge 1 was delivered Ready for Service on July 1, 2026, bringing total live capacity at the campus to 175 MW.
Source (primary)
applied-digital 8-K exhibit (apldq127earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-08)Live source ↗
Quote: “Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 Ready for Service on July 1, 2026, bringing total live capacity at the campus to 175 MW”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The release states this delivery, its date, its size and the resulting 175 MW campus capacity.
Confirmed in the source:
- Phase 1 of Building 2 at Polaris Forge 1 is 75 MW
- Phase 1 of Building 2 was delivered Ready for Service on July 1, 2026
- The delivery brought total live capacity at Polaris Forge 1 to 175 MW
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487926000057/apldq127earningsrelease.htm) in full (40,083 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms applied-digital 8-K exhibit (apldq127earningsrelease.htm)
Quote: “Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 Ready for Service on July 1, 2026, bringing total live capacity at the campus to 175 MW”