Applied Digital Corporation designs, develops, and operates digital infrastructure solutions to high-performance computing (HPC) and artificial intelligence industries in North America. It operates through: Data Center Hosting Business, and HPC Hosting Business. The company offers infrastructure services to crypto mining customers; and GPU computing solutions for critical workloads related to AI, machine learning, and other HPC tasks. It also engages in the designing, constructing, and managing of data centers to support HPC applications. The company was formerly known as Applied Blockchain, Inc. and changed its name to Applied Digital Corporation in November 2022. Applied Digital Corporation has an lease agreement with CoreWeave for an additional 150MW at its Polaris Forge 1 Campus in Ellendale, North Dakota. Applied Digital Corporation is based in Dallas, Texas.
Analyst consensus, peer set, and quarterly-EPS surprise history. Sourced from Finnhub; refreshed nightly.
Summed across 8 tracked project(s), from the capacity figures on each. Anticipated takes the firmest stage on record per project, so a site that is announced at 2 GW and contracted at 400 MW counts once, at 2 GW.
| Subject | Statement date | Promised by | Amount | Status |
| Trailing twelve-month revenuefinancing | 2026-09-03 | - | 0.6 USD | stated |
| Polaris Forge 1 initial online capacityfacility capacity | 2026-09-03 | - | 100.0 MW | stated |
| Polaris Forge 1 additional delivered capacityfacility capacity | 2026-09-03 | - | 75.0 MW | stated |
| Contracted critical IT load across campusescustomer | 2026-09-03 | - | 1.41 GW | stated |
| Total contracted long-term lease valuecustomer | 2026-09-03 | - | 36.0 USD | stated |
| Base Electron natural gas generation partnershippartnership | 2026-09-03 | - | 1.2 GW | stated |
| Base Electron power capacity arrival in 2029facility timeline | 2026-09-03 | 2029-01-01 | - | stated |
| Base Electron power capacity arrival in 2030facility timeline | 2026-09-03 | 2030-01-01 | - | stated |
| Polaris Forge 1 first building construction timefacility timeline | 2026-09-03 | - | 24.0 months | stated |
| Polaris Forge 1 second building construction timefacility timeline | 2026-09-03 | - | - | stated |
| Construction project statusguidance | 2026-09-03 | - | - | stated |
| Annual supply chain build capacityguidance | 2026-09-03 | - | 700.0 MW | stated |
| Contracted build delivery commitmentguidance | 2026-09-03 | - | 1.5 GW | stated |
| Three recent customer leases capacitycustomer | 2026-09-03 | - | 810.0 MW | stated |
| Lease rate positioningguidance | 2026-09-03 | - | - | stated |
| Contract value from three recent leasescustomer | 2026-09-03 | - | 20.0 USD | stated |
| Expansion lease 1 in negotiationcustomer | 2026-09-03 | - | 100.0 MW | stated |
| Expansion lease 2 in negotiationcustomer | 2026-09-03 | - | 150.0 MW | stated |
| Contracted capacityfacility capacity | 2026-09-03 | - | 1.41 GW | stated |
| Base-term contracted revenuecustomer | 2026-09-03 | - | 36.2 billion USD | stated |
| Contracted long-term customer lease revenuecustomer | 2026-09-03 | - | 36000000000.0 USD | stated |
| Contracted data center capacityfacility capacity | 2026-09-03 | - | 1410.0 MW | stated |
| Data center build capacity delivery commitmentfacility capacity | 2026-09-03 | 2028-09-03 | 1500.0 MW | stated |
| Annual data center build capacityguidance | 2026-09-03 | - | 700.0 MW | stated |
| Base Electron natural gas generation partnershippartnership | 2026-09-03 | 2029-01-01 | 1200.0 MW | stated |
| Contracted capacityfacility capacity | 2026-09-03 | - | 1410.0 MW | stated |
| Base-term contracted revenuecustomer | 2026-09-03 | - | 36200000000.0 USD | stated |
| Jamestown HPC data center - 7.5 MWfacility capacity - Jamestown | 2026-09-01 | - | 7.5 MW | stated |
| Ellendale HPC data center - 100 MWfacility capacity - Ellendale | 2026-09-01 | - | 100.0 MW | stated |
| Ellendale HPC facility operational and revenue-generating in calendar year 2025facility timeline - Ellendale | 2026-09-01 | - | - | stated |
| Hyperscaler 400 MW capacity lease - letter of intentcustomer - Ellendale | 2026-09-01 | - | 400.0 MW | stated |
| Exclusivity extension with hyperscaler on July 26, 2024partnership - Ellendale | 2026-09-01 | 2024-07-26 | - | delayed |
| Seven crypto mining customers with multi-year contractscustomer | 2026-09-01 | - | 7.0 customers | stated |
| Two Cloud Services customerscustomer | 2026-09-01 | - | 2.0 customers | stated |
| Partnership with Super Micro for cloud services deliverypartnership | 2026-09-01 | - | - | stated |
| Partnership with HPE for supercomputers and facility designpartnership | 2026-09-01 | - | - | stated |
| Supply agreements with Dell for AI and GPU serverspartnership | 2026-09-01 | - | - | stated |
| GPU clusters with 1,024 GPUs eachproduct | 2026-09-01 | - | 1024.0 GPUs | stated |
| Advanced financing discussions for HPC Ellendale Facilityfinancing - Ellendale | 2026-09-01 | - | - | stated |
| Single crypto mining customer with multi-year contract termcustomer | 2026-09-01 | - | - | stated |
| Jamestown, North Dakota crypto mining facility capacityfacility capacity - Jamestown | 2026-09-01 | - | 106.0 MW | stated |
| Ellendale, North Dakota crypto mining facility capacityfacility capacity - Ellendale | 2026-09-01 | - | 180.0 MW | stated |
| Polaris Forge 1 first building expected operationalfacility timeline - Polaris Forge 1 | 2026-09-01 | - | - | stated |
| Polaris Forge 1 AI campus total planned capacityfacility capacity - Polaris Forge 1 | 2026-09-01 | - | 400.0 MW | stated |
| Lease agreements for Polaris Forge 1 AI campuspartnership - Polaris Forge 1 | 2026-09-01 | - | 250.0 MW | stated |
| Unit Purchase Agreement with MIP VI Holdingsacquisition | 2026-09-01 | - | - | stated |
| Cloud Services Business saleacquisition | 2026-09-01 | - | - | stated |
| Full-time employee headcountpersonnel | 2026-09-01 | - | 205.0 employees | stated |
| Polaris Forge 1 AI data center specificationsproduct | 2026-09-01 | - | - | stated |
| Capacity as of FQ4 2026facility capacity | 2026-09-01 | - | 100.0 MW | stated |
| Backlog capacity by 2028facility capacity | 2026-09-01 | 2028-12-31 | 1410.0 MW | stated |
| Expected capacity in late 2026facility capacity | 2026-09-01 | 2026-12-31 | 100.0 MW | stated |
| Expected capacity by 2028facility capacity | 2026-09-01 | 2028-12-31 | 1410.0 MW | stated |
| HPC backlog with take-or-pay contractscustomer | 2026-09-01 | - | 85.66 B USD | stated |
| Delta Forge 1 hyperscaler lease - 300 MW, $7.5B contractedcustomer - Delta Forge 1 | 2026-09-01 | - | 300.0 MW | stated |
| Polaris Forge 3 hyperscaler lease - 300 MW, $7.5B contractedcustomer - Polaris Forge 3 | 2026-09-01 | - | 300.0 MW | stated |
| Delta Forge 2 hyperscaler lease - 210 MW, $5.2B contractedcustomer - Delta Forge 2 | 2026-09-01 | - | 210.0 MW | stated |
| $2.15B 6.750% Senior Secured Notes offeringfinancing - Polaris Forge 2 | 2026-09-01 | - | 2.15 billion USD | stated |
| $550M revolving credit facilityfinancing | 2026-09-01 | 2029-05-31 | 550.0 million USD | stated |
| $300M senior secured bridge facilityfinancing - Polaris Forge 1 | 2026-09-01 | - | 300.0 million USD | stated |
| $1.59B 7.000% Senior Secured Notes offeringfinancing - Polaris Forge 1 | 2026-09-01 | - | 1.59 billion USD | stated |
| Revolving credit facility upsized to $430M committedfinancing | 2026-09-01 | - | 430.0 million USD | stated |
| ChronoScale formation via cloud services separation with Ekso Bionicsacquisition | 2026-09-01 | 2026-05-05 | 96.0 percent | delayed |
| Polaris Forge 1 Phase 1 (100 MW) operational October 2025facility timeline - Polaris Forge 1 | 2026-09-01 | 2025-10-31 | 100.0 MW | delayed |
| Polaris Forge 1 Building 2 Phase 1 (75 MW) delivered June 30, 2026facility timeline - Polaris Forge 1 | 2026-09-01 | 2026-06-30 | 75.0 MW | delayed |
| Polaris Forge 1 total live capacity 175 MWfacility capacity - Polaris Forge 1 | 2026-09-01 | - | 175.0 MW | stated |
| Total contracted critical IT load across all campusesfacility capacity | 2026-09-01 | - | 1.4 GW | stated |
| Base Electron Corp natural gas generation development - 1.2 GWpartnership | 2026-09-01 | - | 1.2 GW | stated |
| CoreWeave MOU for Polaris Forge 1 Building 4 (150 MW) lease assignmentpartnership - Polaris Forge 1 | 2026-09-01 | - | 150.0 MW | stated |
| CoreWeave lease credit enhancements and $50M letter of creditpartnership | 2026-09-01 | - | 50.0 million USD | stated |
| Jamestown, ND data center 106 MW at full capacityfacility capacity - Jamestown | 2026-09-01 | - | 106.0 MW | stated |
| Ellendale, ND data center 180 MW at full capacityfacility capacity - Ellendale | 2026-09-01 | - | 180.0 MW | stated |
| Bitcoin mining operations 286 MW across two North Dakota sitesfacility capacity | 2026-09-01 | - | 286.0 MW | stated |
| Actively marketing additional 1.7 GW capacity pipelineguidance | 2026-09-01 | - | 1.7 GW | stated |
| Raj Jegannathan appointed ChronoScale Chief Technology Officerpersonnel | 2026-09-01 | - | - | stated |
| Lawrence Lam appointed ChronoScale Chief Product Officerpersonnel | 2026-09-01 | - | - | stated |
| CoreWeave lease agreement - Polaris Forge 1customer - Polaris Forge 1 | 2026-09-01 | - | 11000000000.0 USD | stated |
| Polaris Forge 1 first phase operational datefacility timeline - Polaris Forge 1 | 2026-09-01 | 2025-12-31 | 100.0 MW | delayed |
| Polaris Forge 1 additional phases capacityfacility capacity - Polaris Forge 1 | 2026-09-01 | - | 150.0 MW | stated |
| Polaris Forge 1 ultimate capacity targetfacility capacity - Polaris Forge 1 | 2026-09-01 | - | 1000.0 MW | stated |
| Polaris Forge 2 construction investmentfinancing - Polaris Forge 2 | 2026-09-01 | - | 3000000000.0 USD | stated |
| Polaris Forge 2 initial operations datefacility timeline - Polaris Forge 2 | 2026-09-01 | 2026-12-31 | - | stated |
| Polaris Forge 2 full capacity datefacility timeline - Polaris Forge 2 | 2026-09-01 | 2027-12-31 | - | stated |
| Polaris Forge 2 major customer negotiationcustomer - Polaris Forge 2 | 2026-09-01 | - | - | stated |
| $1 billion Net Operating Income targetguidance | 2026-09-01 | 2031-09-01 | 1000000000.0 USD | stated |
| Power Usage Effectiveness specificationproduct | 2026-09-01 | - | 1.18 PUE | stated |
| 30-year cost savings projectionproduct | 2026-09-01 | 2056-09-01 | 2700000000.0 USD | stated |
| Delta Forge 1 Lease (300 MW)customer - Delta Forge 1 | 2026-09-01 | 2027-01-01 | 7.5 billion USD | stated |
| Polaris Forge 3 Lease (300 MW)customer - Polaris Forge 3 | 2026-09-01 | 2027-01-01 | 7.5 billion USD | stated |
| Delta Forge 2 Lease (210 MW)customer - Delta Forge 2 | 2026-09-01 | 2028-06-30 | 5.2 billion USD | stated |
| $2.15B Senior Secured Notes due 2031financing - Polaris Forge 2 | 2026-09-01 | 2031-01-01 | 2.15 billion USD | stated |
| $550M Revolving Credit Facilityfinancing | 2026-09-01 | 2029-05-31 | 550.0 million USD | stated |
| CoreWeave Lease Enhancement and Credit Supportpartnership - Polaris Forge 1 | 2026-09-01 | - | 50.0 million USD | stated |
| CoreWeave Building 4 Assignment MOUpartnership - Polaris Forge 1 | 2026-09-01 | - | - | stated |
| Base Electron Power Generation Partnershippartnership | 2026-09-01 | - | 1.2 GW | stated |
| ChronoScale Separation and Public Launchacquisition | 2026-09-01 | - | - | stated |
| ChronoScale Executive Appointmentspersonnel | 2026-09-01 | - | - | stated |
| $1.59B Senior Secured Notes due 2031financing - Polaris Forge 1 | 2026-09-01 | 2031-01-01 | 1.59 billion USD | stated |
| Revolving Credit Facility Upsizingfinancing | 2026-09-01 | - | 430.0 million USD | stated |
| Polaris Forge 1 Building 1 Operationalfacility capacity - Polaris Forge 1 | 2026-09-01 | 2025-10-31 | 100.0 MW | delayed |
| Polaris Forge 1 Building 2 Phase 1 Deliveredfacility capacity - Polaris Forge 1 | 2026-09-01 | 2026-06-30 | 75.0 MW | delayed |
| Joint venture with Antpool/Bitmain for co-hosting infrastructurepartnership | 2026-09-01 | - | 1.5 GW | stated |
| IPO completion and equity raisefinancing | 2026-09-01 | - | 36.0 USD | stated |
| Term loan from Vantage Bank Texasfinancing - Jamestown | 2026-09-01 | - | 7.5 USD | stated |
| Jamestown North Dakota facility total contracted capacityfacility capacity - Jamestown | 2026-09-01 | - | 100.0 MW | stated |
| Texas wind farm facility operational timingfacility timeline | 2026-09-01 | 2022-12-31 | 200.0 MW | delayed |
| Additional Texas wind farm groundbreaking timingfacility timeline | 2026-09-01 | 2023-09-01 | 200.0 MW | delayed |
| Multiple facility sites construction startfacility timeline | 2026-09-01 | 2022-12-31 | 600.0 MW | delayed |
| Fiscal year 2023 EBITDA targetguidance | 2026-09-01 | 2023-05-31 | 40.0 USD | delayed |
| Calendar 2023 year-end EBITDA run rateguidance | 2026-09-01 | 2023-12-31 | 200.0 USD | delayed |
| 800MW capacity target by May 2023guidance | 2026-09-01 | 2023-05-31 | 800.0 MW | delayed |
| 1.8GW capacity target by fiscal year-end 2024guidance | 2026-09-01 | 2024-05-31 | 1.8 GW | delayed |
| 5GW long-term capacity targetguidance | 2026-09-01 | 2031-09-01 | 5.0 GW | stated |
| Jamestown facility 100MW fully contractedfacility capacity - Jamestown | 2026-09-01 | - | 100.0 MW | stated |
| Jamestown facility 5-year power agreement with utilitypartnership - Jamestown | 2026-09-01 | - | - | stated |
| Marathon Digital Holdings 5-year 200MW hosting contractcustomer | 2026-09-01 | - | 200.0 MW | stated |
| $15M credit facility with North Dakota bankfinancing | 2026-09-01 | - | 15.0 USD | stated |
| Garden City facility energization Q4 2022facility timeline - Garden City | 2026-09-01 | 2022-12-31 | - | delayed |
| Garden City facility 200MW capacityfacility capacity - Garden City | 2026-09-01 | - | 200.0 MW | stated |
| Three datacenters 500MW operating by H1 2023guidance | 2026-09-01 | 2023-06-30 | 500.0 MW | delayed |
| Third facility groundbreaking Q3 2022facility timeline - Polaris Forge 1 | 2026-09-01 | 2022-09-30 | - | delayed |
| Third facility North Dakota locationfacility timeline - Polaris Forge 1 | 2026-09-01 | - | - | stated |
| Garden City facility fully contractedcustomer - Garden City | 2026-09-01 | - | - | stated |
| Third facility land purchase in North Dakotaacquisition | 2026-09-01 | - | - | stated |
| Third facility Marathon power contract with optioncustomer - Polaris Forge 1 | 2026-09-01 | - | - | stated |
| Jamestown, ND facility fully contracted capacityfacility capacity - Jamestown | 2026-09-01 | - | 100.0 MW | stated |
| Garden City, TX facility planned capacityfacility capacity - Garden City | 2026-09-01 | - | 200.0 MW | stated |
| Ellendale, ND facility planned capacityfacility capacity - Polaris Forge 1 | 2026-09-01 | - | 180.0 MW | stated |
| Marathon Digital Holdings contracted capacitycustomer - Ellendale | 2026-09-01 | - | 276.0 MW | stated |
| Total hosting capacity targetfacility capacity | 2026-09-01 | 2023-03-31 | 500.0 MW | delayed |
| Annualized EBITDA projection at 500MW capacityguidance | 2026-09-01 | - | 100.0 USD | stated |
| Ellendale facility energization timelinefacility timeline - Ellendale | 2026-09-01 | 2023-03-31 | - | delayed |
| Machine learning GPU pilot programcustomer | 2026-09-01 | 2022-10-31 | - | delayed |
| ML project scaling expectationscustomer | 2026-09-01 | 2023-03-31 | - | delayed |
| Highland Digital fund launchfinancing | 2026-09-01 | - | 100.0 USD | stated |
| Garden City Texas facility capacityfacility capacity - Garden City | 2026-09-01 | - | 200.0 MW | stated |
| Garden City facility energizationfacility timeline - Garden City | 2026-09-01 | 2023-02-28 | - | delayed |
| Ellendale North Dakota facility capacityfacility capacity - Ellendale | 2026-09-01 | - | 180.0 MW | stated |
| Ellendale facility energizationfacility timeline - Ellendale | 2026-09-01 | 2023-02-28 | - | delayed |
| 5 megawatt specialized processing centerfacility capacity - Jamestown | 2026-09-01 | - | 5.0 MW | stated |
| 5 megawatt processing center energizationfacility timeline - Jamestown | 2026-09-01 | 2023-03-31 | - | delayed |
| Non-cryptocurrency HPC customers signedcustomer - Jamestown | 2026-09-01 | - | - | stated |
| Total hosting capacity targetfacility capacity | 2026-09-01 | - | 500.0 MW | stated |
| Annualized adjusted EBITDA run rate targetguidance | 2026-09-01 | - | 100.0 USD | stated |
| Jamestown facility energy services agreementpartnership - Jamestown | 2026-09-01 | - | 5.0 years | stated |
| Ellendale facility energy services agreementpartnership - Ellendale | 2026-09-01 | - | 5.0 years | stated |
| Jamestown capacity fully contractedcustomer - Jamestown | 2026-09-01 | - | 100.0 MW | stated |
| Ellendale 180MW facility - first half capacity onlinefacility timeline - Ellendale | 2026-09-01 | 2023-04-30 | 90.0 MW | delayed |
| Ellendale 180MW facility - second half capacity onlinefacility timeline - Ellendale | 2026-09-01 | 2023-06-30 | 90.0 MW | delayed |
| Garden City facility energizationfacility timeline - Garden City | 2026-09-01 | - | - | stated |
| Garden City facility planned capacityfacility capacity - Garden City | 2026-09-01 | - | 200.0 MW | stated |
| Ellendale facility planned capacityfacility capacity - Ellendale | 2026-09-01 | - | 180.0 MW | stated |
| Jamestown facility fully contracted capacitycustomer - Jamestown | 2026-09-01 | - | 100.0 MW | stated |
| Jamestown facility energy services agreementpartnership - Jamestown | 2026-09-01 | - | - | stated |
| Ellendale facility energy services agreementpartnership - Ellendale | 2026-09-01 | - | - | stated |
| Jamestown HPC facility initial operationsfacility timeline - Jamestown | 2026-09-01 | - | - | stated |
| 5MW HPC processing center at Jamestownfacility capacity - Jamestown | 2026-09-01 | - | 5.0 MW | stated |
| HPC facility full capacity completionfacility timeline - Jamestown | 2026-09-01 | 2023-12-31 | - | delayed |
| Character A.I. AI cloud services agreementcustomer | 2026-09-01 | - | 360.0 USD | stated |
| Second AI customer agreementcustomer | 2026-09-01 | - | 460.0 USD | stated |
| AI Cloud Service launchproduct | 2026-09-01 | 2023-12-31 | - | delayed |
| Garden City, Texas 200MW facility energizationfacility timeline - Garden City | 2026-09-01 | - | 200.0 MW | stated |
| Fiscal 2024 revenue guidanceguidance | 2026-09-01 | 2024-05-31 | - | delayed |
| Fiscal 2024 Adjusted EBITDA guidanceguidance | 2026-09-01 | 2024-05-31 | - | delayed |
| North Dakota HPC data center capacity developmentfacility capacity | 2026-09-01 | - | 200.0 MW | stated |
| New state HPC data center capacity developmentfacility capacity | 2026-09-01 | - | 100.0 MW | stated |
| FY2024 total revenue guidanceguidance | 2026-09-01 | 2024-05-31 | - | delayed |
| FY2024 adjusted EBITDA guidanceguidance | 2026-09-01 | 2024-05-31 | - | delayed |
| Garden City, Texas 200 MW facility energizationfacility timeline - Garden City | 2026-09-01 | 2023-12-31 | 200.0 MW | delayed |
| Oncor equipment installation completion at Garden City facilityfacility timeline - Garden City | 2026-09-01 | 2023-10-23 | - | delayed |
| 34,000 GPUs ordered for Cloud servicesproduct | 2026-09-01 | - | 34000.0 units | stated |
| Over 300 MW of HPC datacenter capacity in developmentfacility capacity | 2026-09-01 | - | 300.0 MW | stated |
| 200 MW capacity in development in North Dakotafacility capacity | 2026-09-01 | - | 200.0 MW | stated |
| 100 MW capacity in development in Utahfacility capacity | 2026-09-01 | - | 100.0 MW | stated |
| Facility extension agreement with Oncor Electricity Delivery Companypartnership - Garden City | 2026-09-01 | - | - | stated |
| Garden City facility energizedfacility capacity - Garden City | 2026-09-01 | - | - | stated |
| Ellendale HPC facility construction begunfacility timeline - Polaris Forge 1 | 2026-09-01 | - | 100.0 MW | stated |
| Capacity in developmentfacility capacity | 2026-09-01 | - | 400.0 MW | stated |
| 500 MW hosting capacity targetfacility capacity | 2026-09-01 | - | 500.0 MW | stated |
| TerraForm Power energy supply agreementpartnership - Garden City | 2026-09-01 | - | - | stated |
| Ellendale customer capacity agreementcustomer - Polaris Forge 1 | 2026-09-01 | - | - | stated |
| FY2024 exit revenue run rateguidance | 2026-09-01 | 2024-05-31 | 500.0 million USD | delayed |
| FY2024 exit adjusted EBITDA run rateguidance | 2026-09-01 | 2024-05-31 | 250.0 million USD | delayed |
| Jamestown facility operationalfacility capacity - Jamestown | 2026-09-01 | - | - | stated |
| Ellendale existing facility operationalfacility capacity - Ellendale | 2026-09-01 | - | - | stated |
| $160 million private placement from NVIDIA and institutional investorsfinancing | 2026-09-01 | 2024-09-09 | 160.0 USD | delayed |
| Lease agreement with U.S.-based hyperscaler for 100 MW facilitycustomer - Polaris Forge 1 | 2026-09-01 | - | - | stated |
| 100 MW HPC facility under construction in Ellendale, North Dakotafacility timeline - Polaris Forge 1 | 2026-09-01 | - | 100.0 MW | stated |
| Two additional HPC buildings in design phase adding 300 MW at Ellendalefacility timeline - Polaris Forge 1 | 2026-09-01 | - | 300.0 MW | stated |
| Existing HPC hosting facilities operating at full capacityfacility capacity - Jamestown | 2026-09-01 | - | - | stated |
| Six GPU clusters with 1,024 GPUs each in Cloud Servicesfacility capacity | 2026-09-01 | - | 6.0 clusters | stated |
| Three additional HPC data centers totaling 1.4 GW capacity under developmentfacility capacity | 2026-09-01 | - | 1.4 GW | stated |
| Advanced negotiations with traditional financing institutions for expansion fundingfinancing - Polaris Forge 1 | 2026-09-01 | - | - | stated |
| New Chief Administrative Officer and Chief Financial Officer appointmentspersonnel | 2026-09-01 | 2024-10-14 | - | delayed |
| Macquarie $5 billion perpetual preferred equity financing facilityfinancing | 2026-09-01 | - | 5000000000.0 USD | stated |
| Macquarie up to $900 million investment in Ellendale HPC campusfinancing - Polaris Forge 1 | 2026-09-01 | - | 900000000.0 USD | stated |
| Macquarie right to invest up to $4.1 billion in future HPC pipelinefinancing | 2026-09-01 | - | 4100000000.0 USD | stated |
| Applied Digital retains 85% ownership in HPC business segmentpartnership | 2026-09-01 | - | 85.0 percent | stated |
| Macquarie investment to recover $300 million of Applied Digital equity in Ellendalefinancing - Polaris Forge 1 | 2026-09-01 | - | 300000000.0 USD | stated |
| Ellendale HPC data center main substation transformer energizedfacility timeline - Polaris Forge 1 | 2026-09-01 | - | - | stated |
| APLD ELN-02 Holdings $150 million senior secured debt from Macquarie Equipment Capitalfinancing - Polaris Forge 1 | 2026-09-01 | 2024-11-27 | 150000000.0 USD | delayed |
| $450 million 2.75% Convertible Senior Notes due 2030financing | 2026-09-01 | - | 450000000.0 USD | stated |
| Ellendale HPC data center 400 MW total capacity commitmentfacility capacity - Polaris Forge 1 | 2026-09-01 | - | 400.0 MW | stated |
| Ellendale 100 MW HPC facility under construction with late-stage hyperscaler lease discussionsfacility timeline - Polaris Forge 1 | 2026-09-01 | - | 100.0 MW | stated |
| Ellendale additional 300 MW through two buildings in design stagefacility capacity - Polaris Forge 1 | 2026-09-01 | - | 300.0 MW | stated |
| SMBC $375M financing closedfinancing | 2026-09-01 | - | 375000000.0 USD | stated |
| Macquarie Asset Management $5B investment rightfinancing | 2026-09-01 | - | 5000000000.0 USD | stated |
| Hyperscaler capacity leases 400 MW Ellendalecustomer - Polaris Forge 1 | 2026-09-01 | - | 400.0 MW | stated |
| Ellendale first 100 MW HPC facilityfacility capacity - Polaris Forge 1 | 2026-09-01 | 2025-12-31 | 100.0 MW | delayed |
| Ellendale HPC facility ready for servicefacility timeline - Polaris Forge 1 | 2026-09-01 | 2025-12-31 | - | delayed |
| Ellendale building 369,000+ square feetfacility capacity - Polaris Forge 1 | 2026-09-01 | 2025-12-31 | 369000.0 square feet | delayed |
| CoreWeave 250MW lease agreements at Polaris Forge 1customer - Polaris Forge 1 | 2026-09-01 | - | 7000.0 million USD | stated |
| CoreWeave 150MW lease option for additional capacitycustomer - Polaris Forge 1 | 2026-09-01 | - | 4000.0 million USD | stated |
| First 100MW facility at Polaris Forge 1 operational Q4 2025facility timeline - Polaris Forge 1 | 2026-09-01 | 2025-12-31 | 100.0 MW | delayed |
| Second 150MW facility at Polaris Forge 1 operational mid-2026facility timeline - Polaris Forge 1 | 2026-09-01 | 2026-06-30 | 150.0 MW | delayed |
| Third 150MW facility at Polaris Forge 1 planned 2027facility timeline - Polaris Forge 1 | 2026-09-01 | 2027-12-31 | 150.0 MW | stated |
| Polaris Forge 1 designed to scale to 1 gigawatt total capacityfacility capacity - Polaris Forge 1 | 2026-09-01 | - | 1000.0 MW | stated |
| Polaris Forge 1 facility Power Usage Effectiveness (PUE) 1.18product | 2026-09-01 | - | 1.18 PUE | stated |
| Polaris Forge 1 near-zero water consumption specificationproduct | 2026-09-01 | - | - | stated |
| Customer cost savings potential $2.7 billion over 30 years vs other regionsguidance | 2026-09-01 | - | 2700.0 million USD | stated |
| Over 200 days of naturally occurring free cooling annually at Polaris Forge 1product | 2026-09-01 | - | 200.0 days | stated |
| Data center build time reduced to 12-14 months from 24 monthsguidance | 2026-09-01 | - | 12.0 months | stated |
| CoreWeave 400 MW lease at Polaris Forge 1customer - Polaris Forge 1 | 2026-09-01 | - | 400.0 MW | stated |
| Investment-grade hyperscaler 200 MW lease at Polaris Forge 2customer - Polaris Forge 2 | 2026-09-01 | 2026-12-31 | 200.0 MW | stated |
| Polaris Forge 1 ELN-03 150 MW facility expected online 2026facility capacity - Polaris Forge 1 | 2026-09-01 | 2026-12-31 | 150.0 MW | stated |
| Polaris Forge 1 third 150 MW facility expected 2027facility capacity - Polaris Forge 1 | 2026-09-01 | 2027-12-31 | 150.0 MW | stated |
| Polaris Forge 2 200 MW phased capacity deployment 2026-2027facility capacity - Polaris Forge 2 | 2026-09-01 | 2027-06-30 | 200.0 MW | stated |
| Macquarie preferred equity draw during Q2 2026financing | 2026-09-01 | - | 562.5 USD | stated |
| Macquarie preferred equity draw after Q2 2026financing | 2026-09-01 | - | 337.5 USD | stated |
| $2.35 billion 9.25% senior secured notes due 2030financing | 2026-09-01 | 2030-12-31 | 2350.0 USD | stated |
| Macquarie Equipment Capital development loan facility initial $100 millionfinancing | 2026-09-01 | - | 100.0 USD | stated |
| Applied Digital $15 million investment in Corintis cooling technologypartnership | 2026-09-01 | - | 15.0 USD | stated |
| ChronoScale business combination (Applied Digital Cloud + EKSO Bionics) with 80%+ ownershipacquisition | 2026-09-01 | - | 80.0 percent | stated |
| CoreWeave prospective lease revenue $11 billionguidance | 2026-09-01 | - | 11.0 billion USD | stated |
| Polaris Forge 2 hyperscaler lease revenue $5 billionguidance | 2026-09-01 | - | 5.0 billion USD | stated |
| Applied Digital NOI target $1 billion within five yearsguidance | 2026-09-01 | 2031-09-01 | 1.0 billion USD | stated |
| Delta Forge 1 300 MW data centerfacility capacity - Delta Forge 1 | 2026-09-01 | 2027-07-01 | 300.0 MW | stated |
| Macquarie Equipment Capital DevCo Facilityfinancing | 2026-09-01 | - | 100.0 million USD | stated |
| Jason Zhang appointed Presidentpersonnel | 2026-09-01 | - | - | stated |
| $2.15 billion Senior Secured Notes due 2031financing | 2026-09-01 | - | 2150.0 million USD | stated |
| CoreWeave lease credit enhancements with $50 million letter of creditcustomer - Polaris Forge 1 | 2026-09-01 | - | 50.0 million USD | stated |
| Polaris Forge 1 second 150 MW facilityfacility capacity - Polaris Forge 1 | 2026-09-01 | 2026-12-31 | 150.0 MW | stated |
| Polaris Forge 1 third 150 MW facilityfacility capacity - Polaris Forge 1 | 2026-09-01 | 2027-12-31 | 150.0 MW | stated |
| Polaris Forge 2 200 MW data center capacity timelinefacility timeline - Polaris Forge 2 | 2026-09-01 | 2026-12-31 | 200.0 MW | stated |
| 15-year lease with investment-grade hyperscaler at Polaris Forge 2customer - Polaris Forge 2 | 2026-09-01 | - | 200.0 MW | stated |
| Four development sites with approximately 1 GW total grid power capacityfacility capacity | 2026-09-01 | - | 1.0 GW | stated |
| ChronoScale business combination with EKSO Bionicsacquisition | 2026-09-01 | 2026-05-31 | 97.0 percent | delayed |
| $1 billion NOI goal within five yearsguidance | 2026-09-01 | - | 1000.0 million USD | stated |
| Polaris Forge 1 Phase 2 expansionfacility capacity - Polaris Forge 1 | 2026-09-01 | - | 150.0 MW | stated |
| Polaris Forge 1 Phase 3 ready-for-service datefacility timeline - Polaris Forge 1 | 2026-09-01 | 2027-12-31 | 150.0 MW | stated |
| CoreWeave 250 MW lease at Polaris Forge 1customer - Polaris Forge 1 | 2026-09-01 | - | 250.0 MW | stated |
| CoreWeave Building 4 150 MW lease at Polaris Forge 1customer - Polaris Forge 1 | 2026-09-01 | - | 150.0 MW | stated |
| Polaris Forge 2 initial capacity timelinefacility timeline - Polaris Forge 2 | 2026-09-01 | 2026-12-31 | 200.0 MW | stated |
| Polaris Forge 2 full capacity timelinefacility timeline - Polaris Forge 2 | 2026-09-01 | 2027-03-31 | 200.0 MW | stated |
| Polaris Forge 2 hyperscaler lease 200 MWcustomer - Polaris Forge 2 | 2026-09-01 | - | 200.0 MW | stated |
| Delta Forge 1 hyperscaler leases 300 MWcustomer - Delta Forge 1 | 2026-09-01 | - | 300.0 MW | stated |
| Polaris Forge 3 contracted revenue and deliveryguidance | 2026-09-01 | 2028-12-31 | 7500000000.0 USD | stated |
| Polaris Forge 3 300 MW under constructionfacility capacity - Polaris Forge 3 | 2026-09-01 | - | 300.0 MW | stated |
| Delta Forge 2 contracted revenue and deliveryguidance | 2026-09-01 | 2028-06-30 | 5200000000.0 USD | stated |
| Delta Forge 2 210 MW under constructionfacility capacity - Delta Forge 2 | 2026-09-01 | - | 210.0 MW | stated |
| Base Electron power generation partnershippartnership | 2026-09-01 | - | 1200.0 MW | stated |
| ChronoScale cloud business separationacquisition | 2026-09-01 | - | 97.0 percent | stated |
| Polaris Forge 1 CoreWeave leasescustomer - Polaris Forge 1 | 2026-09-01 | - | 400.0 MW | stated |
| Polaris Forge 1 first data center operationalfacility capacity - Polaris Forge 1 | 2026-09-01 | - | 100.0 MW | stated |
| Polaris Forge 1 second data center 150 MWfacility capacity - Polaris Forge 1 | 2026-09-01 | - | 150.0 MW | stated |
| Polaris Forge 1 third data center ready for service 2027facility timeline - Polaris Forge 1 | 2026-09-01 | 2027-12-31 | 150.0 MW | stated |
| Polaris Forge 2 groundbreaking and expected deliveryfacility timeline - Polaris Forge 2 | 2026-09-01 | 2027-03-31 | 200.0 MW | stated |
| Polaris Forge 2 hyperscaler lease 200 MWcustomer - Polaris Forge 2 | 2026-09-01 | - | 200.0 MW | stated |
| Delta Forge 1 groundbreaking and expected deliveryfacility timeline - Delta Forge 1 | 2026-09-01 | 2028-06-30 | 300.0 MW | stated |
| Delta Forge 1 hyperscaler leases 300 MWcustomer - Delta Forge 1 | 2026-09-01 | - | 300.0 MW | stated |
| Polaris Forge 3 hyperscaler leases 300 MWcustomer - Polaris Forge 3 | 2026-09-01 | 2028-12-31 | 7500000000.0 USD | stated |
| Delta Forge 2 hyperscaler lease 210 MWcustomer - Delta Forge 2 | 2026-09-01 | 2028-06-30 | 5200000000.0 USD | stated |
| Total contracted lease portfoliofinancing | 2026-09-01 | - | 36200000000.0 USD | stated |
| Base Electron natural gas generation partnershippartnership | 2026-09-01 | - | 1.2 GW | stated |
| ChronoScale cloud business separation and public listingacquisition | 2026-09-01 | - | 97.0 percent | stated |
| ChronoScale Legacy Ekso business divestiture planacquisition | 2026-09-01 | - | - | stated |
| Legacy blockchain hosting customer contractcustomer | 2026-09-01 | 2027-12-31 | - | stated |
| Data Center Hosting legacy facilities capacityfacility capacity - Jamestown | 2026-09-01 | - | 286.0 MW | stated |
| Full-time employee countpersonnel | 2026-09-01 | - | 256.0 units | stated |
| Standardized AI factory build cycle capabilityproduct | 2026-09-01 | - | 150.0 MW | stated |
| Polaris Forge 1 third data centerfacility capacity - Polaris Forge 1 | 2026-09-01 | 2027-12-31 | 150.0 MW | stated |
| Polaris Forge 1 CoreWeave leasescustomer - Polaris Forge 1 | 2026-09-01 | - | 400.0 MW | stated |
| Polaris Forge 2 capacity milestonesfacility timeline - Polaris Forge 2 | 2026-09-01 | 2027-03-31 | 200.0 MW | stated |
| Polaris Forge 2 hyperscaler leasecustomer - Polaris Forge 2 | 2026-09-01 | - | 200.0 MW | stated |
| Delta Forge 1 capacity and customerfacility capacity - Delta Forge 1 | 2026-09-01 | - | 300.0 MW | stated |
| Polaris Forge 3 delivery and contracted revenuefacility timeline - Polaris Forge 3 | 2026-09-01 | 2028-12-31 | 7500000000.0 USD | stated |
| Delta Forge 2 delivery and contracted revenuefacility timeline - Delta Forge 2 | 2026-09-01 | 2028-06-30 | 5200000000.0 USD | stated |
| Total contracted lease portfoliofinancing | 2026-09-01 | - | 36200000000.0 USD | stated |
| HPC capacity under constructionfacility capacity | 2026-09-01 | - | 1500.0 MW | stated |
| Active development pipelinefacility capacity | 2026-09-01 | - | 3000.0 MW | stated |
| Extended development pipelinefacility capacity | 2026-09-01 | - | 5000.0 MW | stated |
| Base Electron natural gas generation partnershippartnership | 2026-09-01 | - | 1200.0 MW | stated |
| ChronoScale separation and ownership stakeacquisition | 2026-09-01 | - | 97.0 percent | stated |
| ChronoScale Legacy Ekso divestiture planacquisition | 2026-09-01 | - | - | stated |
| Data Center Hosting legacy blockchain customercustomer | 2026-09-01 | - | - | stated |
| Employee headcountpersonnel | 2026-09-01 | - | 256.0 employees | stated |
| Delta Forge 1 – 300 MW hyperscaler leasecustomer - Delta Forge 1 | 2026-09-01 | - | 7500000000.0 USD | stated |
| Polaris Forge 3 – 300 MW hyperscaler leasecustomer - Polaris Forge 3 | 2026-09-01 | - | 7500000000.0 USD | stated |
| Delta Forge 2 – 210 MW hyperscaler leasecustomer - Delta Forge 2 | 2026-09-01 | - | 5200000000.0 USD | stated |
| HPC Hosting contracted capacity portfoliofacility capacity | 2026-09-01 | - | 1410.0 MW | stated |
| $2.15 billion Senior Secured Notes offeringfinancing - Polaris Forge 2 | 2026-09-01 | 2031-12-31 | 2150000000.0 USD | stated |
| $1.59 billion Senior Secured Notes offeringfinancing - Polaris Forge 1 | 2026-09-01 | 2031-12-31 | 1590000000.0 USD | stated |
| $550 million revolving credit facilityfinancing | 2026-09-01 | 2029-05-31 | 550000000.0 USD | stated |
| Revolving credit facility upsizingfinancing | 2026-09-01 | - | 430000000.0 USD | stated |
| $50 million letter of credit from CoreWeavefinancing - Polaris Forge 1 | 2026-09-01 | - | 50000000.0 USD | stated |
| CoreWeave Building 4 lease assignment MOUpartnership - Polaris Forge 1 | 2026-09-01 | - | - | stated |
| Base Electron power generation partnershippartnership | 2026-09-01 | - | 1200.0 MW | stated |
| ChronoScale separation and ownership stakeacquisition | 2026-09-01 | - | 96.0 percent | stated |
| Additional capacity marketing pipelineguidance | 2026-09-01 | - | 1700.0 MW | stated |
| Raj Jegannathan appointed Chief Technology Officer of ChronoScalepersonnel | 2026-09-01 | - | - | stated |
| Lawrence Lam appointed Chief Product Officer of ChronoScalepersonnel | 2026-09-01 | - | - | stated |
| CoreWeave Polaris Forge 1 leasecustomer - Polaris Forge 1 | 2026-09-01 | 2027-06-30 | 400.0 MW | stated |
| High Investment Grade Hyperscaler Delta Forge 1 leasecustomer - Delta Forge 1 | 2026-09-01 | 2028-06-30 | 300.0 MW | stated |
| Investment Grade Hyperscaler Polaris Forge 2 leasecustomer - Polaris Forge 2 | 2026-09-01 | 2027-06-30 | 200.0 MW | stated |
| High Investment Grade Hyperscaler Polaris Forge 3 leasecustomer - Polaris Forge 3 | 2026-09-01 | 2028-12-31 | 300.0 MW | stated |
| High Investment Grade Hyperscaler Delta Forge 2 leasecustomer - Delta Forge 2 | 2026-09-01 | 2028-06-30 | 210.0 MW | stated |
| Macquarie Asset Management funding commitmentfinancing | 2026-09-01 | - | 5000000000.0 USD | stated |
| Total AI data center capacityfacility capacity | 2026-09-01 | 2028-12-31 | 1510.0 MW | stated |
| Majority of capacity online by 2028facility timeline | 2026-09-01 | 2028-12-31 | - | stated |
| 150 MW standard AI factory design delivery timelineproduct | 2026-09-01 | - | 150.0 MW | stated |
| Master service agreements with hyperscalerspartnership | 2026-09-01 | - | - | stated |
| Annual facility delivery rateguidance | 2026-09-01 | - | 500.0 MW | stated |
| 3 GW capacity target within five yearsguidance | 2026-09-01 | 2031-09-01 | 3000.0 MW | stated |
| Expected average annual net operating incomeguidance | 2026-09-01 | - | 2000000000.0 USD | stated |
| 100 MW capacity by late 2026facility capacity | 2026-09-01 | - | 100.0 MW | stated |
| 1,410 MW capacity backlog by 2028facility capacity | 2026-09-01 | 2028-12-31 | 1410.0 MW | stated |
| $85.66B HPC opportunities backlogcustomer | 2026-09-01 | - | 85.66 USD | stated |
| 1,410 MW backlog by 2028facility capacity | 2026-09-01 | 2028-12-31 | 1410.0 MW | stated |
| 15-year take-or-pay contract backlogpartnership | 2026-09-01 | - | - | stated |
| 1.4 GW critical IT load at end of fiscal 2026facility capacity | 2026-09-01 | - | 1.4 GW | stated |
| $36 billion in contracted lease revenues at end of fiscal 2026financing | 2026-09-01 | - | 36.0 billion USD | stated |
| Three 15-year take-or-pay leases with hyperscaler worth $20 billioncustomer | 2026-09-01 | - | 20.0 billion USD | stated |
| One HPC customer represented 59% of fiscal 2026 revenuescustomer | 2026-09-01 | - | 59.0 percent | stated |
| HPC Hosting segment revenueproduct | 2026-09-01 | - | 385.0 USD | stated |
| Data Center Hosting segment revenueproduct | 2026-09-01 | - | 154.0 USD | stated |
| Loss-making statusfinancing | 2026-09-01 | - | - | stated |
| Contracted IT load capacityfacility capacity | 2026-09-01 | - | 1.4 GW | stated |
| Total contracted lease revenuescustomer | 2026-09-01 | - | 36000000000.0 USD | stated |
| 15-year take-or-pay leases with primary hyperscalercustomer | 2026-09-01 | - | 20000000000.0 USD | stated |
| Largest single taxpayer in North Dakotaguidance | 2026-09-01 | 2029-12-31 | - | stated |
| Property tax payments of approximately $24M annuallyguidance | 2026-09-01 | 2029-12-31 | 24000000.0 USD | stated |
| Largest single taxpayer in North Dakota by 2029guidance | 2026-08-31 | 2029-12-31 | - | stated |
| Property tax payments of $24 million annually by 2029guidance | 2026-08-31 | 2029-12-31 | 24.0 Million USD | stated |
| Largest single taxpayer in North Dakota by 2029guidance | 2026-08-31 | 2029-12-31 | - | stated |
| Annual property tax payments of approximately $24 million by 2029guidance | 2026-08-31 | 2029-12-31 | 24000000.0 USD | stated |
| Largest state taxpayer by 2029guidance | 2026-08-29 | 2029-12-31 | - | stated |
| Annual property tax payments by 2029guidance | 2026-08-29 | 2029-12-31 | 24.0 USD | stated |
| FY2026 revenuefinancing | 2026-08-28 | - | 611.0 USD millions | stated |
| Diluted loss per share reductionfinancing | 2026-08-28 | - | 22.0 percent | stated |
| Data center capacity leasedfacility capacity | 2026-08-28 | - | 1.4 GW | stated |
| Lease revenue pipelinecustomer | 2026-08-28 | - | 36.0 USD billions | stated |
| Data center capacity delivery completionfacility timeline | 2026-08-28 | 2028-12-31 | 1.4 GW | stated |
| Long-term lease revenue with renewal optionscustomer | 2026-08-28 | - | 86.0 USD billions | stated |
| Estimated lease revenue from contracted capacityguidance | 2026-08-28 | - | 36000000000.0 USD | stated |
| Contracted data center capacity delivery completionfacility timeline | 2026-08-28 | 2028-12-31 | 1.4 GW | stated |
| Potential lease revenue with contract renewalsguidance | 2026-08-28 | - | 86000000000.0 USD | stated |
| Expansion of data center campuses and capacityfacility capacity | 2026-08-28 | - | - | stated |
| Direct-to-chip liquid-cooled AI campus designproduct | 2026-08-25 | - | - | stated |
| Polaris Forge liquid-cooled AI campus designproduct | 2026-08-25 | - | - | stated |
| Contracted critical IT loadfacility capacity | 2026-08-25 | - | 1.4 gigawatts | stated |
| Total contracted lease revenuefinancing | 2026-08-25 | - | 36.0 billion USD | stated |
| Active pipeline projectsfacility capacity | 2026-08-25 | - | 3.0 gigawatts | stated |
| Contracted IT loadfacility capacity | 2026-08-24 | - | 1.4 GW | stated |
| North Dakota power buildout with Base Electronpartnership | 2026-08-24 | - | 1.2 GW | stated |
| Contracted lease revenuefinancing | 2026-08-24 | - | - | stated |
| Base Electron natural gas generation partnershippartnership | 2026-08-24 | - | - | stated |
| Polaris Forge 1 operational capacityfacility capacity - Polaris Forge 1 | 2026-08-24 | - | - | stated |
| Delta Forge 1 and Polaris Forge 3 contracted capacityfacility capacity - Delta Forge 1 | 2026-08-24 | - | - | stated |
| Development pipelinefacility capacity | 2026-08-24 | - | - | stated |
| Path to 3 GW contracted power by 2031guidance | 2026-08-24 | 2031-12-31 | 3.0 GW | stated |
| Contracted critical IT load capacityfacility capacity | 2026-08-24 | - | 1.4 GW | stated |
| Base Electron natural gas generation partnershippartnership | 2026-08-24 | - | 1.2 GW | stated |
| Polaris Forge 1 operational capacityfacility capacity - Polaris Forge 1 | 2026-08-24 | - | 175.0 MW | stated |
| Contracted IT loadfacility capacity | 2026-08-24 | - | 1.4 GW | stated |
| Base Electron partnership for North Dakota power buildoutpartnership | 2026-08-24 | - | - | stated |
| North Dakota natural gas generation capacityfacility capacity | 2026-08-24 | - | 1.2 GW | stated |
| Contracted critical IT load capacity and revenuefacility capacity | 2026-08-23 | - | 1.4 GW | stated |
| Facility contracts with 15-year terms at named sitespartnership - Delta Forge 1 | 2026-08-23 | - | 300.0 MW | stated |
| Active development pipeline capacityfacility capacity | 2026-08-23 | - | 3.0 GW | stated |
| Contracted power capacity target by 2031guidance | 2026-08-23 | 2031-12-31 | 3.0 GW | stated |
| 1.4 gigawatts contracted critical IT loadfacility capacity | 2026-08-23 | - | 1.4 GW | stated |
| Total contracted lease revenuefinancing | 2026-08-23 | - | 36.0 USD billion | stated |
| Two 300 MW contracts at Delta Forge 1 and Polaris Forge 3 with 15-year termspartnership - Delta Forge 1 | 2026-08-23 | - | 300.0 MW | stated |
| Active pipeline of 3 gigawattsfacility capacity | 2026-08-23 | - | 3.0 GW | stated |
| Path to 3 gigawatts of contracted power by 2031guidance | 2026-08-23 | 2031-12-31 | 3.0 GW | stated |
| Contracted critical IT loadfacility capacity | 2026-08-23 | - | 1.4 GW | stated |
| Total contracted lease revenuecustomer | 2026-08-23 | - | 36.0 USD | stated |
| Delta Forge 1 and Polaris Forge 3 contractsfacility capacity - Delta Forge 1 | 2026-08-23 | - | 300.0 MW | stated |
| Active pipeline capacityfacility capacity | 2026-08-23 | - | 3.0 GW | stated |
| Contracted power target by 2031guidance | 2026-08-23 | 2031-12-31 | 3.0 GW | stated |
| Q4 2026 Revenuefinancing | 2026-08-22 | - | 258.7 USD millions | stated |
| AI Factory campuses under developmentfacility timeline - Delta Forge 2 | 2026-08-22 | - | - | stated |
| Fourth building construction started at Polaris Forge 1facility timeline - Polaris Forge 1 | 2026-08-22 | - | - | stated |
| Phase 1 of second building placed into service at Polaris Forge 1facility capacity - Polaris Forge 1 | 2026-08-22 | - | 75.0 MW | stated |
| Polaris Forge 1 campus at 175 MW live capacityfacility capacity - Polaris Forge 1 | 2026-08-22 | - | 175.0 MW | stated |
| CoreWeave has 400 MW leasedcustomer | 2026-08-22 | - | 400.0 MW | stated |
| $1.59 billion senior secured notes for Polaris Forge 1 building 4financing - Polaris Forge 1 | 2026-08-22 | - | 1.59 billion USD | stated |
| $300 million bridge facility for Polaris Forge 1financing - Polaris Forge 1 | 2026-08-22 | - | 300.0 million USD | stated |
| $2.15 billion senior secured notes for Polaris Forge 2financing - Polaris Forge 2 | 2026-08-22 | - | 2.15 billion USD | stated |
| Polaris Forge 1 Building 2 capacity additionfacility capacity - Polaris Forge 1 | 2026-08-22 | 2026-06-30 | 75.0 MW | delayed |
| Polaris Forge 1 total live capacityfacility capacity - Polaris Forge 1 | 2026-08-22 | - | - | stated |
| Polaris Forge 1 Building 2 construction durationfacility timeline - Polaris Forge 1 | 2026-08-22 | - | - | stated |
| Polaris Forge 1 Building 1 construction durationfacility timeline - Polaris Forge 1 | 2026-08-22 | - | - | stated |
| Polaris Forge 2 lease negotiationscustomer - Polaris Forge 2 | 2026-08-22 | - | - | stated |
| Delta Forge expansion lease negotiationscustomer - Delta Forge 2 | 2026-08-22 | - | - | stated |
| $2.15 billion senior secured notes offeringfinancing - Polaris Forge 2 | 2026-08-22 | - | - | stated |
| Legacy senior secured notesfinancing | 2026-08-22 | - | - | stated |
| Ownership stake in Base Electronpartnership | 2026-08-22 | - | - | stated |
| 15-year lease for 210 MW at Delta Forge 2facility capacity - Delta Forge 2 | 2026-08-22 | - | 210.0 MW | stated |
| 15-year lease for 210 MW at Delta Forge 2partnership - Delta Forge 2 | 2026-08-22 | - | 210.0 MW | stated |
| Building 2 capacity delivery at Polaris Forge 1facility capacity | 2026-08-22 | 2026-06-30 | 75.0 MW | stated |
| Polaris Forge 2 lease negotiationscustomer | 2026-08-22 | - | 100.0 MW | stated |
| Delta Forge expansion lease negotiationscustomer | 2026-08-22 | - | 150.0 MW | stated |
| Polaris Forge 2 capacity fundingfacility capacity | 2026-08-22 | - | 200.0 MW | stated |
| Senior secured debt issuancefinancing | 2026-08-22 | - | 2.15 USD | stated |
| Minority stake in Base Electronpartnership | 2026-08-22 | - | 10.0 percent | stated |
| Delta Forge 2 AI campus 15-year leasefacility capacity | 2026-08-22 | - | 210.0 MW | stated |
| Delta Forge 2 AI campus 210 MW leasefacility capacity | 2026-08-22 | - | 210.0 MW | stated |
| Polaris Forge 1 capacity placed in servicefacility capacity | 2026-08-22 | 2026-07-01 | 75.0 MW | stated |
| Construction of fourth building at Polaris Forge 1 underwayfacility timeline | 2026-08-22 | - | - | stated |
| Five AI Factory campuses under developmentfacility timeline | 2026-08-22 | - | - | stated |
| $1.59 billion senior secured notes for Polaris Forge 1 fourth buildingfinancing | 2026-08-22 | - | 1590.0 USD | stated |
| $300 million bridge facility for Polaris Forge 1financing | 2026-08-22 | - | 300.0 USD | stated |
| $2.15 billion senior secured notes for Polaris Forge 2financing | 2026-08-22 | - | 2150.0 USD | stated |
| 400 MW leased to CoreWeavecustomer | 2026-08-22 | - | 400.0 MW | stated |
| Contracted IT load capacityfacility capacity | 2026-08-21 | - | 1.4 GW | stated |
| Contracted lease revenuefinancing | 2026-08-21 | - | 36.0 billion USD | stated |
| Potential contracted lease revenue with renewal optionsfinancing | 2026-08-21 | - | 86.0 billion USD | stated |
| Contracted lease revenuefinancing | 2026-08-21 | - | 36.0 billion USD | stated |
| Nvidia investment roundfinancing | 2026-08-21 | - | 160.0 USD | stated |
| Nvidia Network Cloud Partner program membershippartnership | 2026-08-21 | - | - | stated |
| Contracted lease revenuecustomer | 2026-08-21 | - | 36000000000.0 USD | stated |
| Contracted IT loadfacility capacity | 2026-08-21 | - | 1400.0 MW | stated |
| US$36 billion AI data center lease contractspartnership | 2026-08-20 | - | 36000000000.0 USD | stated |
| Target timeline for $1 billion annual net operating incomeguidance | 2026-08-20 | - | 1000000000.0 USD | stated |
| 1.4 GW contracted IT loadfacility capacity | 2026-08-20 | - | 1.4 GW | stated |
| Delta Forge 2 lease agreementfacility timeline - Delta Forge 2 | 2026-08-20 | - | - | stated |
| Polaris Forge 3 lease agreementfacility timeline - Polaris Forge 3 | 2026-08-20 | - | - | stated |
| $5B co-location agreement with U.S. hyperscaler for Polaris Forge 2customer - Polaris Forge 2 | 2026-08-20 | - | 5000000000.0 USD | stated |
| Pricing guidance on new leasesguidance | 2026-08-20 | - | 15.0 percent | stated |
| Gross capacity being marketedfacility capacity | 2026-08-20 | - | 1.7 GW | stated |
| Contracted capacity planned for delivery by 2028facility capacity | 2026-08-20 | 2028-12-31 | 1.4 GW | stated |
| Expected base term lease value for contracted capacityfinancing | 2026-08-20 | - | 35.0 USD | stated |
| Percentage of investment-grade customerscustomer | 2026-08-20 | - | 70.0 percent | stated |
| Currently operational capacityfacility capacity | 2026-08-20 | - | 100.0 MW | stated |
| Annual incremental delivery capability through 2031guidance | 2026-08-20 | 2031-12-31 | 500.0 MW | stated |
| Capacity currently being marketedfacility capacity | 2026-08-20 | - | 1.5 GW | stated |
| Secured US$36 billion in long-term AI data center lease contractscustomer | 2026-08-20 | - | 36000000000.0 USD | stated |
| Confirmed 1.4 GW contracted IT load across campusesfacility capacity | 2026-08-20 | - | 1.4 GW | stated |
| Delta Forge 2 and Polaris Forge 3 are 15-year take-or-pay lease agreementscustomer | 2026-08-20 | - | - | stated |
| Brought forward target timeline for US$1 billion annual net operating incomeguidance | 2026-08-20 | - | 1000000000.0 USD | stated |
| AI data center lease contractscustomer | 2026-08-20 | - | 36000000000.0 USD | stated |
| Target for annual net operating incomeguidance | 2026-08-20 | - | 1000000000.0 USD | stated |
| Contracted IT load across campusesfacility capacity | 2026-08-20 | - | 1.4 GW | stated |
| Delta Forge 2 and Polaris Forge 3 facilitiescustomer | 2026-08-20 | - | - | stated |
| Revenue projection for 2029guidance | 2026-08-20 | 2029-12-31 | 2400000000.0 USD | stated |
| Earnings projection for 2029guidance | 2026-08-20 | 2029-12-31 | 117000000.0 USD | stated |
| $5B hyperscaler customer agreement for 200 MW at Polaris Forge 2customer | 2026-08-20 | - | 5000000000.0 USD | stated |
| Co-location leases with CoreWeave and hyperscaler; third agreement pendingpartnership | 2026-08-20 | - | - | stated |
| Cloud business spin-off merger with Ekso Bionics to form ChronoScaleacquisition | 2026-08-20 | - | - | stated |
| Q4 earnings and revenue beat expectationsguidance | 2026-08-18 | - | - | stated |
| Polaris Forge campus in full operationfacility timeline - Polaris Forge 1 | 2026-08-18 | - | - | stated |
| Contracted backlog of $35.7 billioncustomer | 2026-08-18 | - | - | stated |
| Potential backlog of $85.7 billion with lease extensionscustomer | 2026-08-18 | - | - | stated |
| Delta Forge 2 lease base-term revenuefinancing - Delta Forge 2 | 2026-08-18 | - | 5.2 Billion USD | stated |
| Total contracted portfolio base-term revenuefinancing | 2026-08-18 | - | 36.0 Billion USD | stated |
| Portfolio critical IT loadfacility capacity | 2026-08-18 | - | 1.4 GW | stated |
| Portfolio grid-connected utility powerfacility capacity | 2026-08-18 | - | 2.15 GW | stated |
| Investment-grade hyperscaler customer revenue concentrationcustomer | 2026-08-18 | - | 70.0 percent | stated |
| Delta Forge 2 initial operations startfacility timeline - Delta Forge 2 | 2026-08-18 | 2028-03-31 | - | stated |
| Delta Forge 2 total value with renewal optionsfinancing - Delta Forge 2 | 2026-08-18 | - | 12.7 Billion USD | stated |
| Total portfolio value with all renewal optionsfinancing | 2026-08-18 | - | 86.0 Billion USD | stated |
| Q4 2026 Revenuefinancing | 2026-08-17 | - | 258.7 USD millions | stated |
| Annual Revenue Growthfinancing | 2026-08-14 | - | - | stated |
| FY2026 Revenuefinancing | 2026-08-14 | - | 611.3 million USD | stated |
| FY2026 Net Lossfinancing | 2026-08-14 | - | 250.3 million USD | stated |
| Anchor customer revenue concentrationcustomer | 2026-08-14 | - | 59.0 percent | stated |
| CoreWeave 400 MW Polaris Forge 1 contractcustomer - Polaris Forge 1 | 2026-08-13 | - | 11000000000.0 USD | stated |
| Services revenue Q4 2026product | 2026-08-13 | - | 208200000.0 USD | stated |
| Data center rental revenue Q4 2026product | 2026-08-13 | - | 50600000.0 USD | stated |
| Adjusted EBITDA Q4 2026financing | 2026-08-13 | - | 42400000.0 USD | stated |
| Customer concentrationcustomer | 2026-08-12 | - | 59.0 percent | stated |
| FY 2026 Revenuefinancing | 2026-08-12 | - | 611.3 USD | stated |
| FY 2026 Revenue growth ratefinancing | 2026-08-12 | - | 183.7 percent | stated |
| FY 2026 Net lossfinancing | 2026-08-12 | - | -244.0 USD | stated |
| Free cash flowfinancing | 2026-08-12 | - | -2.8 USD | stated |
| Stock-based compensationfinancing | 2026-08-12 | - | 245.5 percent | stated |
| FY2026 Annual Revenuefinancing | 2026-07-29 | - | - | stated |
| FY2026 Net Incomefinancing | 2026-07-29 | - | - | stated |
| FY2026 Diluted EPSfinancing | 2026-07-29 | - | - | stated |
| FY2026 Capital Expendituresfinancing | 2026-07-29 | - | - | stated |
| FY2026 Free Cash Flowfinancing | 2026-07-29 | - | - | stated |
| FY2026 Operating Cash Flowfinancing | 2026-07-29 | - | - | stated |
| FY2026 Gross Marginproduct | 2026-07-29 | - | - | stated |
| FY2026 Operating Marginfinancing | 2026-07-29 | - | - | stated |
| FY2026 Total Assetsfinancing | 2026-07-29 | - | - | stated |
| FY2026 Cash Holdingsfinancing | 2026-07-29 | - | - | stated |
| FY2026 Debt-to-Equity Ratiofinancing | 2026-07-29 | - | - | stated |
| FY2026 Shares Outstandingfinancing | 2026-07-29 | - | - | stated |
| FY2026 SG&A Expensesfinancing | 2026-07-29 | - | - | stated |
| Polaris Forge 1 first facility operationalfacility timeline - Polaris Forge 1 | 2026-07-28 | 2025-10-01 | 100.0 MW | delayed |
| CoreWeave leases at Polaris Forge 1customer - Polaris Forge 1 | 2026-07-28 | - | 400.0 MW | stated |
| Polaris Forge 1 third facility ready-for-servicefacility timeline - Polaris Forge 1 | 2026-07-28 | 2027-12-31 | 150.0 MW | stated |
| Polaris Forge 2 groundbreaking and construction timelinefacility timeline - Polaris Forge 2 | 2026-07-28 | 2026-12-31 | 200.0 MW | stated |
| Investment-grade hyperscaler lease at Polaris Forge 2customer - Polaris Forge 2 | 2026-07-28 | 2025-10-22 | 5.0 billion USD | delayed |
| Delta Forge 1 groundbreakingfacility timeline - Delta Forge 1 | 2026-07-28 | 2026-01-22 | 300.0 MW | delayed |
| Investment-grade hyperscaler leases at Delta Forge 1customer - Delta Forge 1 | 2026-07-28 | 2026-04-23 | 7.5 billion USD | delayed |
| Polaris Forge 3 contracted capacity and revenuefacility capacity - Polaris Forge 3 | 2026-07-28 | - | 7.5 billion USD | stated |
| Polaris Forge 3 expected deliveryfacility timeline - Polaris Forge 3 | 2026-07-28 | 2028-06-30 | 300.0 MW | stated |
| Delta Forge 2 contracted capacity and revenuefacility capacity - Delta Forge 2 | 2026-07-28 | - | 5.2 billion USD | stated |
| Delta Forge 2 expected deliveryfacility timeline - Delta Forge 2 | 2026-07-28 | 2028-06-30 | 210.0 MW | stated |
| Total contracted lease portfoliofacility capacity | 2026-07-28 | - | 36.2 billion USD | stated |
| Secured and under construction pipelinefacility capacity | 2026-07-28 | - | 1.5 GW | stated |
| Active development pipelinefacility capacity | 2026-07-28 | - | 3.0 GW | stated |
| Extended development pipelinefacility capacity | 2026-07-28 | - | 5.0 GW | stated |
| Base Electron power generation partnershippartnership | 2026-07-28 | - | 1.2 GW | stated |
| ChronoScale separation and trading launchacquisition | 2026-07-28 | 2026-05-05 | 97.0 percent | delayed |
| ChronoScale Legacy Ekso divestment commitmentacquisition | 2026-07-28 | 2026-06-04 | - | delayed |
| AI factory standardized designproduct | 2026-07-28 | - | 150.0 MW | stated |
| Full-time employee countpersonnel | 2026-07-28 | - | 256.0 employees | stated |
| Restricted stock unit awards to employeespersonnel | 2026-07-28 | - | - | stated |
| Polaris Forge 1 first data center operational capacityfacility capacity - Polaris Forge 1 | 2026-07-28 | - | 100.0 MW | stated |
| Polaris Forge 1 second data centerfacility capacity - Polaris Forge 1 | 2026-07-28 | - | 150.0 MW | stated |
| Polaris Forge 1 third data center delivery timelinefacility timeline - Polaris Forge 1 | 2026-07-28 | 2027-12-31 | 150.0 MW | stated |
| CoreWeave leases at Polaris Forge 1customer - Polaris Forge 1 | 2026-07-28 | - | 400.0 MW | stated |
| Polaris Forge 2 groundbreakingfacility timeline - Polaris Forge 2 | 2026-07-28 | 2025-08-18 | 200.0 MW | delayed |
| Polaris Forge 2 customer leasecustomer - Polaris Forge 2 | 2026-07-28 | 2025-10-22 | 200.0 MW | delayed |
| Polaris Forge 2 capacity delivery timelinefacility timeline - Polaris Forge 2 | 2026-07-28 | 2027-03-31 | 200.0 MW | stated |
| Delta Forge 1 groundbreakingfacility timeline - Delta Forge 1 | 2026-07-28 | 2026-01-22 | 300.0 MW | delayed |
| Delta Forge 1 customer leasescustomer - Delta Forge 1 | 2026-07-28 | 2026-04-23 | 300.0 MW | delayed |
| Delta Forge 1 contracted revenuefinancing - Delta Forge 1 | 2026-07-28 | 2028-06-30 | 7.5 billion USD | stated |
| Polaris Forge 3 contracted capacity and revenuefacility capacity - Polaris Forge 3 | 2026-07-28 | - | 7.5 billion USD | stated |
| Polaris Forge 3 expected deliveryfacility timeline - Polaris Forge 3 | 2026-07-28 | 2028-06-30 | 300.0 MW | stated |
| Delta Forge 2 contracted capacity and revenuefacility capacity - Delta Forge 2 | 2026-07-28 | - | 5.2 billion USD | stated |
| Delta Forge 2 expected deliveryfacility timeline - Delta Forge 2 | 2026-07-28 | 2028-06-30 | 210.0 MW | stated |
| Total contracted HPC lease portfoliofinancing | 2026-07-28 | 2028-06-30 | 36.2 billion USD | stated |
| ChronoScale separation and ownershipacquisition | 2026-07-28 | 2026-05-05 | 97.0 percent | delayed |
| ChronoScale Holdings formationacquisition | 2026-07-28 | 2026-07-01 | - | delayed |
| ChronoScale stock tradingproduct | 2026-07-28 | 2026-05-05 | - | delayed |
| ChronoScale cloud business operationsproduct | 2026-07-28 | - | - | stated |
| Legacy Ekso Bionics divestiture planacquisition | 2026-07-28 | 2026-06-04 | - | delayed |
| Base Electron natural gas generation partnershippartnership | 2026-07-28 | - | 1.2 GW | stated |
| Secured and under-construction HPC development pipelineguidance | 2026-07-28 | - | 1.5 GW | stated |
| Active development pipelineguidance | 2026-07-28 | - | 3.0 GW | stated |
| Extended development pipelineguidance | 2026-07-28 | - | 5.0 GW | stated |
| Data Center Hosting Business crypto customercustomer | 2026-07-28 | 2027-11-28 | - | stated |
| Data Center Hosting Business total capacityfacility capacity - Jamestown | 2026-07-28 | - | 286.0 MW | stated |
| Full-time employee countpersonnel | 2026-07-28 | - | 256.0 units | stated |
| Polaris Forge 1 - First HPC data center operationalfacility timeline - Polaris Forge 1 | 2026-07-28 | 2025-10-31 | 100.0 MW | delayed |
| Polaris Forge 1 - Second data center partially operationalfacility capacity - Polaris Forge 1 | 2026-07-28 | - | 150.0 MW | stated |
| Polaris Forge 1 - Third data center under constructionfacility timeline - Polaris Forge 1 | 2026-07-28 | 2027-12-31 | 150.0 MW | stated |
| CoreWeave leases ELN-02 and ELN-03 at Polaris Forge 1customer - Polaris Forge 1 | 2026-07-28 | - | 250.0 MW | stated |
| CoreWeave Building 4 Lease at Polaris Forge 1customer - Polaris Forge 1 | 2026-07-28 | - | 150.0 MW | stated |
| Polaris Forge 2 groundbreaking and construction timelinefacility timeline - Polaris Forge 2 | 2026-07-28 | 2027-06-30 | 200.0 MW | stated |
| Polaris Forge 2 hyperscaler leasecustomer - Polaris Forge 2 | 2026-07-28 | - | 200.0 MW | stated |
| Delta Forge 1 groundbreakingfacility timeline - Delta Forge 1 | 2026-07-28 | - | 300.0 MW | stated |
| Delta Forge 1 hyperscaler leasescustomer - Delta Forge 1 | 2026-07-28 | - | 300.0 MW | stated |
| Polaris Forge 3 contracted capacity and revenuecustomer - Polaris Forge 3 | 2026-07-28 | 2028-12-31 | 7500.0 USD | stated |
| Delta Forge 2 contracted capacity and revenuecustomer - Delta Forge 2 | 2026-07-28 | 2028-06-30 | 5200.0 USD | stated |
| Contracted lease portfolio as of May 31, 2026customer | 2026-07-28 | 2028-12-31 | 36200.0 USD | stated |
| Secured and under construction capacity pipelinefacility capacity | 2026-07-28 | - | 1500.0 MW | stated |
| Active development pipelinefacility capacity | 2026-07-28 | - | 3000.0 MW | stated |
| Extended development pipelinefacility capacity | 2026-07-28 | - | 5000.0 MW | stated |
| Base Electron natural gas generation partnershippartnership | 2026-07-28 | - | 1200.0 MW | stated |
| Legacy Data Center Hosting Business crypto customercustomer | 2026-07-28 | - | - | stated |
| Data Center Hosting Business capacityfacility capacity - Jamestown | 2026-07-28 | - | 286.0 MW | stated |
| ChronoScale cloud business separation completedacquisition | 2026-07-28 | 2026-05-05 | 97.0 percent | delayed |
| Employee countpersonnel | 2026-07-28 | - | 256.0 employees | stated |
| CFO Saidal Mohmandpersonnel | 2026-07-26 | - | - | stated |
| 15-year 210 MW hyperscaler leasecustomer - Delta Forge 2 | 2026-06-30 | - | 5200000000.0 USD | stated |
| Secured revolving credit facilityfinancing | 2026-06-25 | 2029-05-28 | 430000000.0 USD | stated |
| Incremental revolving commitments or term loans capacityfinancing | 2026-06-25 | - | 120000000.0 USD | stated |
| Series G Convertible Preferred Stock commitment increasefinancing | 2026-06-25 | - | 2000000000.0 USD | stated |
| Completion of 6.75% Senior Secured Notes private offeringfinancing | 2026-06-16 | - | - | stated |
| Release of escrow funds from debt offering upon ESA Condition satisfactionfinancing | 2026-06-16 | - | - | stated |
| Senior Secured Notes offeringfinancing | 2026-06-16 | 2031-06-15 | 1.59 USD billion | stated |
| 150 MW critical IT load (ELN-04) at Polaris Forge 1, Ellendale, North Dakotafacility capacity - Polaris Forge 1 | 2026-06-16 | - | 150.0 MW | stated |
| Repayment of Goldman Sachs bridge loan facilityfinancing | 2026-06-16 | - | - | stated |
| Revolving credit facility with Goldman Sachsfinancing | 2026-06-08 | 2026-05-29 | 350.0 USD | delayed |
| $1.59 billion senior secured notes offeringfinancing | 2026-06-08 | - | 1590.0 USD | stated |
| Memorandum of Understanding with CoreWeave for ELN-04 lease assignmentpartnership - Polaris Forge 1 | 2026-06-08 | - | - | stated |
| 150 MW data center construction at Polaris Forge 1facility capacity - Polaris Forge 1 | 2026-06-08 | - | 150.0 MW | stated |
| Long-term lease agreement for Delta Forge 2 Campuspartnership - Delta Forge 2 | 2026-06-08 | - | - | stated |
| $1.59 billion senior secured notes offeringfinancing | 2026-06-08 | 2026-06-16 | 1590000000.0 USD | delayed |
| 150 MW AI Factory construction at Polaris Forge 1, Ellendale, North Dakota (ELN-04)facility capacity - Polaris Forge 1 | 2026-06-08 | - | 150.0 MW | stated |
| Goldman Sachs bridge loan repaymentfinancing | 2026-06-08 | - | - | stated |
| Revolving credit facilityfinancing | 2026-06-08 | - | 350000000.0 USD | stated |
| Debt-to-equity ratiofinancing | 2026-05-31 | - | 2.9 x | stated |
| Current ratiofinancing | 2026-05-31 | - | 4.0 x | stated |
| Polaris Forge 3 15-year hyperscaler leasecustomer - Polaris Forge 3 | 2026-05-20 | - | 7500000000.0 USD | stated |
| Polaris Forge 3 critical IT load and utility power capacityfacility capacity - Polaris Forge 3 | 2026-05-20 | 2027-08-01 | 300.0 MW | stated |
| Polaris Forge 3 operations start datefacility timeline - Polaris Forge 3 | 2026-05-20 | 2027-08-01 | - | stated |
| Total contracted lease revenue across four AI Factory campusesguidance | 2026-05-20 | - | 31000000000.0 USD | stated |
| Total contracted AI Factory capacityfacility capacity | 2026-05-20 | - | 1200.0 MW | stated |
| $300 million senior secured bridge facilityfinancing | 2026-05-20 | - | 300000000.0 USD | stated |
| Investment-grade hyperscaler backing of contracted revenueguidance | 2026-05-20 | - | 65.0 percent | stated |
| Business combination with Ekso Bionics; control of ChronoScaleacquisition | 2026-05-04 | 2026-05-05 | 138216820.0 shares of Ekso Common Stock | delayed |
| Equity investment in Ekso/ChronoScalefinancing | 2026-05-04 | 2026-05-05 | 15.75 USD (millions) | delayed |
| Management and corporate services agreement with ChronoScalepartnership | 2026-05-04 | 2026-05-05 | 1.0 percent of gross revenue (quarterly) | delayed |
| Board designation rights at ChronoScalepersonnel | 2026-05-04 | 2026-05-05 | 4.0 directors | delayed |
| SEC registration statement filing requirementregulatory | 2026-05-04 | 2026-07-04 | - | delayed |
| Lease agreement at Delta Forge 1 Campusfacility timeline - Delta Forge 1 | 2026-04-23 | - | - | stated |
| Proposed transaction with Ekso Bionics Holdingsacquisition | 2026-04-15 | - | - | stated |
| Executive equity awards in EKSO transactionpersonnel | 2026-04-15 | - | 5.25 percent | stated |
| Business combination with EKSO Bionics Holdings to form ChronoScaleacquisition | 2026-04-07 | - | 97.0 percent | stated |
| ELN-02 data center capacityfacility capacity - Polaris Forge 1 | 2026-03-31 | - | 100.0 MW | stated |
| ELN-03 data center capacityfacility capacity - Polaris Forge 1 | 2026-03-31 | - | 150.0 MW | stated |
| CoreWeave tenancy at Polaris Forge 1customer - Polaris Forge 1 | 2026-03-31 | - | - | stated |
| ELN-02 Parent Lease Amendmentpartnership - Polaris Forge 1 | 2026-03-31 | - | - | stated |
| ELN-02 SPV Lease executionpartnership - Polaris Forge 1 | 2026-03-31 | - | - | stated |
| ELN-02 CoreWeave Parent Guarantypartnership - Polaris Forge 1 | 2026-03-31 | - | - | stated |
| ELN-02 Letter of Credit commitmentfinancing - Polaris Forge 1 | 2026-03-31 | 2026-04-29 | 50000000.0 USD | delayed |
| ELN-03 Lease Assignmentpartnership - Polaris Forge 1 | 2026-03-31 | - | - | stated |
| ELN-03 CoreWeave Parent Guarantypartnership - Polaris Forge 1 | 2026-03-31 | - | - | stated |
| Polaris Forge 1 data centersfacility timeline - Polaris Forge 1 | 2026-03-12 | - | - | stated |
| CoreWeave datacenter leasescustomer | 2026-03-12 | - | - | stated |
| Polaris Forge 2 campusfacility timeline - Polaris Forge 2 | 2026-03-12 | - | - | stated |
| 6.750% Senior Secured Notes due 2031financing | 2026-03-09 | 2031-03-15 | 2150000000.0 USD | stated |
| Polaris Forge 2 expansion to 200 MWfacility capacity - Polaris Forge 2 | 2026-03-09 | - | 200.0 MW | stated |
| Oracle lease at Polaris Forge 2customer - Polaris Forge 2 | 2026-03-09 | - | - | stated |
| Chief Financial Officer bonuspersonnel | 2026-03-09 | - | 750000.0 USD | stated |
| Guarantee of Base Electron obligations to B&Wpartnership | 2026-03-03 | - | - | stated |
| 1.2 GW power generation facility capacityfacility capacity | 2026-03-03 | - | 1.2 GW | stated |
| 10% equity stake in Base Electronacquisition | 2026-03-03 | - | 10.0 percent | stated |
| Design-Build Agreement contract pricefinancing | 2026-03-03 | - | 2400.0 million USD | stated |
| Guarantee termination fee—$50M by August 1, 2026financing | 2026-03-03 | 2026-08-01 | 50.0 million USD | delayed |
| Guarantee termination fee—$100Mfinancing | 2026-03-03 | - | 100.0 million USD | stated |
| Guarantee termination option—Base Electron $50M financingfinancing | 2026-03-03 | - | 50.0 million USD | stated |
| $2.15 billion senior secured notes offering by APLD ComputeCo 2financing | 2026-03-03 | 2026-03-10 | 2150.0 USD | delayed |
| 200 MW critical IT load development at Polaris Forge 2 in Harwood, NDfacility capacity - Polaris Forge 2 | 2026-03-03 | - | 200.0 MW | stated |
| Oracle lease of Polaris Forge 2customer - Polaris Forge 2 | 2026-03-03 | - | - | stated |
| Senior secured notes offering by APLD ComputeCo 2financing | 2026-03-01 | - | 2150000000.0 USD | stated |
| Polaris Forge 2 IT load capacity developmentfacility capacity - Polaris Forge 2 | 2026-03-01 | - | 200.0 MW | stated |
| Oracle lease at Polaris Forge 2customer - Polaris Forge 2 | 2026-03-01 | - | - | stated |
| Business combination equity exchange with Ekso Bionicsacquisition | 2026-02-16 | - | 138216820.0 shares | stated |
| Post-combination ownership stakeacquisition | 2026-02-16 | - | 97.0 percent | stated |
| Expected business combination closing dateacquisition | 2026-02-16 | 2026-06-30 | - | delayed |
| Business combination termination deadlineacquisition | 2026-02-16 | 2026-07-15 | - | delayed |
| Board director designation rights for majority ownerpersonnel | 2026-02-16 | - | 4.0 directors | stated |
| Initial board director appointmentspersonnel | 2026-02-16 | - | - | stated |
| PIPE investment in combined companyfinancing | 2026-02-16 | - | - | stated |
| Business combination with Ekso via Cloud contributionacquisition | 2026-02-15 | 2026-07-15 | 138216820.0 shares | delayed |
| Expected ownership stake in combined companyacquisition | 2026-02-15 | - | 97.0 percent | stated |
| Target company name changeacquisition | 2026-02-15 | 2026-07-15 | - | delayed |
| APLD investor board designation rightspartnership | 2026-02-15 | - | - | stated |
| Initial APLD-designated board memberspersonnel | 2026-02-15 | 2026-07-15 | - | delayed |
| Jason Zhang PSU and RSU grantpersonnel | 2026-02-08 | - | - | stated |
| Saidal Mohmand PSU and RSU grantpersonnel | 2026-02-08 | - | - | stated |
| Polaris Forge 1 data center capacityfacility capacity - Polaris Forge 1 | 2026-02-08 | - | 400.0 MW | stated |
| Polaris Forge 2 data center capacity and leasefacility capacity - Polaris Forge 2 | 2026-02-08 | - | 200.0 MW | stated |
| Delta Forge 1 expected data center capacityfacility capacity - Delta Forge 1 | 2026-02-08 | - | 430.0 MW | stated |
| 2026 revenue growth expectationguidance | 2026-02-08 | - | - | stated |
| Jason Zhang appointed President and Co-Founderpersonnel | 2026-01-15 | - | - | stated |
| Jason Zhang annual base salarypersonnel | 2026-01-15 | - | 700000.0 USD | stated |
| Data center leases executed in North Dakotafacility timeline - Polaris Forge 2 | 2026-01-15 | - | - | stated |
| CEO equity compensation grantpersonnel | 2026-01-07 | - | 6000000.0 shares | stated |
| Ellendale data center fully leasedfacility capacity - Polaris Forge 1 | 2026-01-07 | - | 400.0 MW | stated |
| Harwood data center lease signedfacility capacity - Polaris Forge 2 | 2026-01-07 | - | 200.0 MW | stated |
| 2026 revenue increase guidanceguidance | 2026-01-07 | 2026-12-31 | - | stated |
| Proposed business combination with EKSO Bionicsacquisition | 2025-12-28 | - | - | stated |
| $45M first draw from Macquarie Equipment Capitalfinancing | 2025-12-21 | - | 45.0 USD | stated |
| $55M second drawfinancing | 2025-12-21 | - | 55.0 USD | stated |
| 8.0% annual interest ratefinancing | 2025-12-21 | - | 8.0 percent | stated |
| New data center project developmentfacility timeline | 2025-12-21 | - | - | stated |
| Initial Lease Execution deadlinefacility timeline | 2025-12-21 | 2026-04-18 | - | delayed |
| Loan maturity datefinancing | 2025-12-21 | 2027-12-18 | - | stated |
| Ongoing credit arrangement with Macquarie Equipment Capitalpartnership | 2025-12-21 | - | - | stated |
| Existing Data Center Hosting Capacityfacility capacity - Jamestown | 2025-12-04 | - | 286.0 MW | stated |
| Polaris Forge 1 ELN-02 Operationsfacility capacity - Polaris Forge 1 | 2025-12-04 | - | 100.0 MW | stated |
| Polaris Forge 1 ELN-03 Under Constructionfacility capacity - Polaris Forge 1 | 2025-12-04 | - | 150.0 MW | stated |
| Polaris Forge 1 ELN-04 Construction Timelinefacility timeline - Polaris Forge 1 | 2025-12-04 | - | 150.0 MW | stated |
| CoreWeave Lease Polaris Forge 1 ELN-02 and ELN-03customer - Polaris Forge 1 | 2025-12-04 | - | 250.0 MW | stated |
| CoreWeave Lease Polaris Forge 1 ELN-04 and Total Contractcustomer - Polaris Forge 1 | 2025-12-04 | - | 400.0 MW | stated |
| Polaris Forge 2 Construction and Capacity Timelinefacility timeline - Polaris Forge 2 | 2025-12-04 | - | 280.0 MW | stated |
| Polaris Forge 2 Hyperscaler Leasecustomer - Polaris Forge 2 | 2025-12-04 | - | 200.0 MW | stated |
| Polaris Forge 2 Hyperscaler Total Contract Revenuecustomer - Polaris Forge 2 | 2025-12-04 | - | 5000.0 USD millions | stated |
| Polaris Forge 2 Hyperscaler Right of Refusalcustomer - Polaris Forge 2 | 2025-12-04 | - | 800.0 MW | stated |
| Macquarie Promissory Note Fundingfinancing - Polaris Forge 2 | 2025-12-04 | - | 50.0 USD millions | stated |
| Macquarie Asset Management Equity Investmentfinancing | 2025-12-04 | - | 112.5 USD millions | stated |
| Macquarie Asset Management Additional Investment Optionfinancing | 2025-12-04 | - | 4900.0 USD millions | stated |
| Macquarie Warrant Issuancefinancing - Polaris Forge 1 | 2025-12-04 | - | 2.4 shares | stated |
| Series G Preferred Stock Commitment Increasefinancing | 2025-12-04 | - | 1590.0 USD millions | stated |
| CoreWeave Warrant Issuancefinancing - Polaris Forge 1 | 2025-12-04 | - | 8393611.0 shares | stated |
| Senior Secured Notes Offeringfinancing | 2025-12-04 | - | 2350.0 USD millions | stated |
| Senior Secured Notes Maturity Datefinancing | 2025-12-04 | 2030-12-15 | - | stated |
| Authorized Common Stock Increaseregulatory | 2025-12-04 | - | 600.0 shares | stated |
| Cloud business spun off and merged with Ekso Bionics to form ChronoScaleacquisition | 2025-12-01 | - | 97.0 percent | stated |
| Senior Secured Notes offeringfinancing | 2025-11-19 | 2030-12-15 | 2350000000.0 USD | stated |
| Data center ELN-02 at Ellendale campusfacility capacity - Polaris Forge 1 | 2025-11-19 | - | 100.0 MW | stated |
| Data center ELN-03 at Ellendale campusfacility capacity - Polaris Forge 1 | 2025-11-19 | - | 150.0 MW | stated |
| Repayment of prior credit facilityfinancing | 2025-11-19 | - | - | stated |
| Senior secured notes offering by subsidiaryfinancing | 2025-11-13 | 2025-11-20 | 2350000000.0 USD | delayed |
| Anticipated additional equity financing for Polaris Forge campusesfinancing - Polaris Forge 2 | 2025-11-11 | - | - | stated |
| $65 million revolving credit agreement with First National Bank of Omahafinancing | 2025-11-11 | - | 65.0 USD | stated |
| Senior secured notes offeringfinancing | 2025-11-10 | - | 2350.0 million USD | stated |
| Senior secured notes offeringfinancing | 2025-11-09 | - | 2350.0 million USD | stated |
| Polaris Forge 2 Campus lease agreement near Harwood, North Dakotapartnership - Polaris Forge 2 | 2025-10-22 | - | - | stated |
| Series G Preferred Stock aggregate commitment increasefinancing | 2025-10-20 | - | 1590000000.0 USD | stated |
| Series G Preferred Stock original discount increasefinancing | 2025-10-20 | - | 3.0 percent | stated |
| Maximum put issuance amount for Series G Preferred Stockfinancing | 2025-10-20 | - | 75000000.0 USD | stated |
| Series G Preferred Stock authorized shares increasefinancing | 2025-10-20 | - | 1030000.0 shares | stated |
| Maximum aggregate stated value of Series G Preferred Stockfinancing | 2025-10-20 | - | 75000000.0 USD | stated |
| Common stock registration deadlinefinancing | 2025-10-20 | 2025-11-12 | - | delayed |
| Series G Preferred Stock Floor Price limit increasefinancing | 2025-10-20 | - | 4.48 USD | stated |
| Put issuance frequency limitationfinancing | 2025-10-20 | - | - | stated |
| Polaris Forge data center construction fundingfacility timeline - Polaris Forge 2 | 2025-10-20 | - | - | stated |
| Series G Preferred Stock Floor Price Increasedfinancing | 2025-10-16 | - | 34.0 USD | stated |
| CoreWeave lease - 150 MW additional at Polaris Forge 1customer - Polaris Forge 1 | 2025-10-09 | - | 150.0 MW | stated |
| CoreWeave lease - $11 billion total contracted revenuecustomer - Polaris Forge 1 | 2025-10-09 | - | 11000.0 USD millions | stated |
| Polaris Forge 1 - 100 MW building completionfacility timeline - Polaris Forge 1 | 2025-10-09 | 2025-12-31 | 100.0 MW | delayed |
| Polaris Forge 1 - 150 MW building construction initiatedfacility timeline - Polaris Forge 1 | 2025-10-09 | 2026-06-30 | 150.0 MW | delayed |
| Macquarie preferred equity - $112.5 million drawn from $5 billion facilityfinancing - Polaris Forge 1 | 2025-10-09 | - | 112.5 USD millions | stated |
| Macquarie Equipment Capital - $50 million for Polaris Forge 2financing - Polaris Forge 2 | 2025-10-09 | - | 50.0 USD millions | stated |
| Series G Preferred Stock - $200 million raisedfinancing | 2025-10-09 | - | 200.0 USD millions | stated |
| Polaris Forge 2 - groundbreaking and construction commencedfacility timeline - Polaris Forge 2 | 2025-10-09 | - | - | stated |
| Polaris Forge 2 - initial 200 MW capacity timelinefacility timeline - Polaris Forge 2 | 2025-10-09 | 2027-12-31 | 200.0 MW | stated |
| Polaris Forge 2 - potential expansion to 1 GWfacility capacity - Polaris Forge 2 | 2025-10-09 | - | 1.0 GW | stated |
| Polaris Forge 2 - hyperscaler tenant in advanced discussionscustomer - Polaris Forge 2 | 2025-10-09 | - | - | stated |
| Projected annualized NOI - $500 millionguidance | 2025-10-09 | - | 500.0 USD millions | stated |
| NOI target - $1 billion within five yearsguidance | 2025-10-09 | 2030-10-09 | 1000.0 USD millions | stated |
| HPC Hosting - 100 MW facility operational Q4 2025facility timeline - Polaris Forge 1 | 2025-10-09 | 2025-12-31 | 100.0 MW | delayed |
| HPC Hosting - 150 MW facility scheduled mid-2026facility timeline - Polaris Forge 1 | 2025-10-09 | 2026-06-30 | 150.0 MW | delayed |
| HPC Hosting - 150 MW facility planned 2027facility timeline - Polaris Forge 1 | 2025-10-09 | 2027-12-31 | 150.0 MW | stated |
| Liquid cooling system Design PUE 1.18product | 2025-10-09 | - | 1.18 PUE | stated |
| Customer cost savings estimate - $2.7 billion over 30 yearsproduct | 2025-10-09 | - | 2700.0 USD millions | stated |
| Polaris Forge 1 - expansion beyond 1 GW potential 2028-2030facility capacity - Polaris Forge 1 | 2025-10-09 | 2028-01-01 | 1.0 GW | stated |
| Series G convertible preferred stock issuancefinancing | 2025-10-08 | - | 170386.0 USD | stated |
| Common stock offeringfinancing | 2025-10-08 | - | 190421.0 USD | stated |
| Series G convertible preferred stock conversion to commonfinancing | 2025-10-08 | - | - | stated |
| Garden City facility divestiturefacility timeline - Garden City | 2025-10-08 | - | 25000.0 USD | stated |
| Initial Macquarie investment closedfinancing - Polaris Forge 1 | 2025-10-08 | 2025-10-06 | 112.5 million USD | delayed |
| Macquarie conditional investment right for Polaris Forge 1 additional phasesfinancing - Polaris Forge 1 | 2025-10-08 | - | 337.5 million USD | stated |
| Total potential Macquarie investment in Polaris Forge 1financing - Polaris Forge 1 | 2025-10-08 | - | 450.0 million USD | stated |
| Applied Digital equity contributions to Polaris Forge 1financing - Polaris Forge 1 | 2025-10-08 | - | 990.0 million USD | stated |
| Macquarie investment right in future HPC data center projectsfinancing | 2025-10-08 | 2028-04-06 | 4550.0 million USD | stated |
| Conditional Macquarie investment obligation in Polaris Forge 1financing - Polaris Forge 1 | 2025-10-08 | 2028-04-06 | 250.0 million USD | stated |
| Polaris Forge 1 data center capacityfacility capacity - Polaris Forge 1 | 2025-10-08 | - | 100.0 MW | stated |
| Ellendale, North Dakota datacenter campus capacityfacility capacity - Polaris Forge 1 | 2025-10-08 | - | 400.0 MW | stated |
| Warrants issued to Macquarie affiliatesfinancing - Polaris Forge 1 | 2025-10-08 | - | 2400000.0 shares | stated |
| Registration statement filing obligation for warrant sharesfinancing | 2025-10-08 | 2025-12-05 | - | delayed |
| Macquarie Asset Management investment partnership closedpartnership - Polaris Forge 1 | 2025-10-08 | 2025-10-06 | - | delayed |
| Series G Convertible Preferred Stock Floor Price increasefinancing | 2025-09-25 | - | 22.0 USD | stated |
| CoreWeave Polaris Forge 1 lease agreementcustomer - Polaris Forge 1 | 2025-09-21 | - | 11000000000.0 USD | stated |
| Polaris Forge 1 first phase 100 MW operationalfacility capacity - Polaris Forge 1 | 2025-09-21 | 2025-12-31 | 100.0 MW | delayed |
| Polaris Forge 1 additional 150 MW expansionfacility capacity - Polaris Forge 1 | 2025-09-21 | 2027-12-31 | 150.0 MW | stated |
| Polaris Forge 2 facility capacityfacility capacity - Polaris Forge 2 | 2025-09-21 | - | 200.0 MW | stated |
| Polaris Forge 2 capital investmentfinancing - Polaris Forge 2 | 2025-09-21 | - | 3000000000.0 USD | stated |
| Polaris Forge 2 operational timelinefacility timeline - Polaris Forge 2 | 2025-09-21 | 2027-12-31 | - | stated |
| Polaris Forge 2 hyperscaler customer negotiationscustomer - Polaris Forge 2 | 2025-09-21 | - | - | stated |
| $1 billion NOI target within five yearsguidance | 2025-09-21 | 2030-09-21 | 1000000000.0 USD | stated |
| Direct-to-chip cooling system PUE specificationproduct | 2025-09-21 | - | 1.18 PUE | stated |
| 30-year cost savings from energy efficiencyguidance | 2025-09-21 | - | 2700000000.0 USD | stated |
| CoreWeave 15-year lease agreement for Polaris Forge 1customer - Polaris Forge 1 | 2025-09-11 | - | 11000000000.0 USD | stated |
| Polaris Forge 2 investmentfinancing - Polaris Forge 2 | 2025-09-11 | - | 3000000000.0 USD | stated |
| Polaris Forge 1 phased rolloutfacility timeline - Polaris Forge 1 | 2025-09-11 | 2025-12-31 | - | delayed |
| Polaris Forge 1 design capacityfacility capacity - Polaris Forge 1 | 2025-09-11 | - | 1.0 GW | stated |
| Polaris Forge 2 operational timelinefacility timeline - Polaris Forge 2 | 2025-09-11 | 2026-12-31 | - | stated |
| Polaris Forge 2 IT load capacityfacility capacity - Polaris Forge 2 | 2025-09-11 | - | 200.0 MW | stated |
| U.S.-based hyperscaler customer in advanced negotiations for Polaris Forge 2customer - Polaris Forge 2 | 2025-09-11 | - | - | stated |
| Net Operating Income five-year targetguidance | 2025-09-11 | 2030-09-11 | 1000000000.0 USD | stated |
| Direct-to-chip cooling system with Power Usage Effectiveness specificationproduct | 2025-09-11 | - | 1.18 PUE | stated |
| Initial loan from Macquarie Equipment Capitalfinancing | 2025-09-11 | 2027-09-09 | 50.0 USD | stated |
| Additional loans available under Macquarie promissory notefinancing | 2025-09-11 | - | 25.0 USD | stated |
| 200 MW Lease Execution deadline for Polaris Forge 2facility timeline - Polaris Forge 2 | 2025-09-11 | 2025-10-31 | 200.0 MW | delayed |
| Series G Preferred Stock commitment increasefinancing | 2025-09-11 | - | 450.0 USD | stated |
| Building 4 Datacenter Lease with CoreWeavepartnership - Polaris Forge 1 | 2025-09-02 | - | - | stated |
| Polaris Forge 1 total capacityfacility capacity - Polaris Forge 1 | 2025-08-28 | - | 400.0 MW | stated |
| Building 4 capacityfacility capacity - Polaris Forge 1 | 2025-08-28 | - | 150.0 MW | stated |
| Building 4 service-ready datefacility timeline - Polaris Forge 1 | 2025-08-28 | - | - | stated |
| CoreWeave total leased capacity at Polaris Forge 1customer - Polaris Forge 1 | 2025-08-28 | - | 400.0 MW | stated |
| Building 4 Lease contract valuefinancing - Polaris Forge 1 | 2025-08-28 | - | 4000000000.0 USD | stated |
| Building 4 Warrant issuancefinancing | 2025-08-28 | - | 8393611.0 shares | stated |
| Series G Preferred Stock commitment increasefinancing | 2025-08-14 | - | 300.0 USD | stated |
| Removal of Put Issuance limitationfinancing | 2025-08-14 | - | - | stated |
| Polaris Forge I data center constructionfacility timeline - Polaris Forge 1 | 2025-08-14 | - | - | stated |
| Current data center hosting capacityfacility capacity | 2025-07-29 | - | 286.0 MW | stated |
| Polaris Forge 1 under construction capacityfacility capacity - Polaris Forge 1 | 2025-07-29 | - | 250.0 MW | stated |
| Polaris Forge 1 total planned capacityfacility capacity - Polaris Forge 1 | 2025-07-29 | - | 400.0 MW | stated |
| Polaris Forge 1 lease agreementspartnership - Polaris Forge 1 | 2025-07-29 | - | 250.0 MW | stated |
| Data Center Hosting customer concentrationcustomer | 2025-07-29 | - | - | stated |
| HPC Hosting Business customercustomer | 2025-07-29 | - | - | stated |
| Polaris Forge 1 revenue generation timingfacility timeline - Polaris Forge 1 | 2025-07-29 | - | - | stated |
| Full-time employee headcountpersonnel | 2025-07-29 | - | 205.0 employees | stated |
| Jamestown, North Dakota facility capacityfacility capacity - Jamestown | 2025-07-29 | - | 106.0 MW | stated |
| Ellendale, North Dakota facility capacityfacility capacity - Ellendale | 2025-07-29 | - | 180.0 MW | stated |
| Total current operating capacityfacility capacity | 2025-07-29 | - | 286.0 MW | stated |
| Polaris Forge 1 first building capacityfacility capacity - Polaris Forge 1 | 2025-07-29 | - | 100.0 MW | stated |
| Polaris Forge 1 second building capacityfacility capacity - Polaris Forge 1 | 2025-07-29 | - | 150.0 MW | stated |
| Polaris Forge 1 third building capacityfacility capacity - Polaris Forge 1 | 2025-07-29 | - | 150.0 MW | stated |
| Polaris Forge 1 total planned capacityfacility capacity - Polaris Forge 1 | 2025-07-29 | - | 400.0 MW | stated |
| Polaris Forge 1 lease agreements executionfacility timeline - Polaris Forge 1 | 2025-07-29 | - | 250.0 MW | stated |
| Polaris Forge 1 first building operational datefacility timeline - Polaris Forge 1 | 2025-07-29 | - | - | stated |
| Data Center Hosting Business customer contractcustomer | 2025-07-29 | - | 2.5 years | stated |
| HPC Hosting Business customer contractcustomer | 2025-07-29 | - | 15.0 years | stated |
| Full-time employee headcountpersonnel | 2025-07-29 | - | 205.0 employees | stated |
| Single crypto mining customer with 2.5-year remaining contractcustomer | 2025-07-29 | - | - | stated |
| Single HPC customer with 15-year lease agreementscustomer | 2025-07-29 | - | - | stated |
| Jamestown, North Dakota facility capacityfacility capacity - Jamestown | 2025-07-29 | - | 106.0 MW | stated |
| Ellendale, North Dakota existing facility capacityfacility capacity - Ellendale | 2025-07-29 | - | 180.0 MW | stated |
| Total current hosting capacity across all existing facilitiesfacility capacity | 2025-07-29 | - | 286.0 MW | stated |
| Polaris Forge 1 first building capacity under constructionfacility capacity - Polaris Forge 1 | 2025-07-29 | - | 100.0 MW | stated |
| Polaris Forge 1 second building capacity under constructionfacility capacity - Polaris Forge 1 | 2025-07-29 | - | 150.0 MW | stated |
| Polaris Forge 1 third building planned capacityfacility capacity - Polaris Forge 1 | 2025-07-29 | - | 150.0 MW | stated |
| Polaris Forge 1 first two buildings leased capacityfacility capacity - Polaris Forge 1 | 2025-07-29 | - | 250.0 MW | stated |
| Polaris Forge 1 first building operational datefacility timeline - Polaris Forge 1 | 2025-07-29 | 2025-12-31 | - | delayed |
| Unit Purchase Agreement with MIP VI Holdings II, LLCacquisition | 2025-07-29 | - | - | stated |
| Jamestown facility capacityfacility capacity - Jamestown | 2025-07-29 | - | 106.0 MW | stated |
| Ellendale facility capacityfacility capacity - Ellendale | 2025-07-29 | - | 180.0 MW | stated |
| Polaris Forge 1 leased capacityfacility capacity - Polaris Forge 1 | 2025-07-29 | - | 250.0 MW | stated |
| Polaris Forge 1 operational startfacility timeline - Polaris Forge 1 | 2025-07-29 | 2025-12-31 | - | delayed |
| Polaris Forge 1 campus total capacityfacility capacity - Polaris Forge 1 | 2025-07-29 | - | 400.0 MW | stated |
| Crypto mining customer contractcustomer | 2025-07-29 | - | - | stated |
| HPC hosting customer leasecustomer | 2025-07-29 | - | - | stated |
| Employee countpersonnel | 2025-07-29 | - | 205.0 employees | stated |
| Unit Purchase Agreement with MIP VI Holdings IIpartnership | 2025-07-29 | - | - | stated |
| CoreWeave datacenter leases for 250 MWcustomer - Ellendale | 2025-06-01 | - | 250.0 MW | stated |
| Building 2 capacityfacility capacity - Ellendale | 2025-06-01 | - | 100.0 MW | stated |
| Building 3 capacityfacility capacity - Ellendale | 2025-06-01 | - | 150.0 MW | stated |
| Ellendale Campus total capacityfacility capacity - Ellendale | 2025-06-01 | - | 400.0 MW | stated |
| Building 2 service commencementfacility timeline - Ellendale | 2025-06-01 | - | - | stated |
| Building 3 service commencementfacility timeline - Ellendale | 2025-06-01 | - | - | stated |
| Building 2 lease contract valuefinancing - Ellendale | 2025-06-01 | - | 3000000000.0 USD | stated |
| Building 3 lease contract valuefinancing - Ellendale | 2025-06-01 | - | 4000000000.0 USD | stated |
| CoreWeave warrant issuancepartnership | 2025-06-01 | - | 13062521.0 shares | stated |
| At-the-market offeringfinancing | 2025-06-01 | - | 200000000.0 USD | stated |
| Cloud Services Business divestitureacquisition | 2025-05-29 | - | - | stated |
| Series G Preferred Stock put rightfinancing | 2025-04-30 | - | 150.0 USD | stated |
| Registration deadline for conversion sharesfinancing | 2025-04-30 | 2025-06-09 | - | delayed |
| Termination of prior equity purchase agreementfinancing | 2025-04-30 | 2025-05-07 | - | delayed |
| Series G Preferred Stock designationregulatory | 2025-04-30 | - | 156000.0 shares | stated |
| Series G put limit escalation schedulefinancing | 2025-04-30 | - | - | stated |
| David Rench consulting transition and compensationpersonnel | 2025-02-20 | 2026-04-30 | 593750.0 USD | delayed |
| David Rench PSU vesting conditions and forfeiturepersonnel | 2025-02-20 | 2026-04-30 | 306250.0 units | delayed |
| Michael Maniscalco severance paymentpersonnel | 2025-02-20 | 2025-07-31 | 200000.0 USD | delayed |
| Michael Maniscalco RSU accelerationpersonnel | 2025-02-20 | - | 159979.0 units | stated |
| Credit facility with Sumitomo Mitsui Banking Corporationfinancing | 2025-02-12 | - | - | stated |
| Amendment to Unit Purchase Agreement with MIP VI HPC Holdingspartnership | 2025-02-12 | - | - | stated |
| $375M term loan facilityfinancing | 2025-02-11 | - | 375.0 USD | stated |
| Loan maturity datefinancing | 2025-02-11 | 2026-08-11 | - | delayed |
| Ellendale HPC data center capacityfacility capacity - Ellendale | 2025-02-11 | - | 400.0 MW | stated |
| Use of loan proceedsfinancing - Ellendale | 2025-02-11 | - | - | stated |
| Expected permanent project financing termsguidance | 2025-02-11 | - | - | stated |
| Non-dilutive nature of financingguidance | 2025-02-11 | - | - | stated |
| UPA Amendment extended deadlinepartnership | 2025-02-11 | 2025-02-28 | - | delayed |
| Unit issuance to Macquarie affiliatepartnership | 2025-02-11 | - | - | stated |
| Chief Operating Officer hiredpersonnel | 2025-02-05 | - | - | stated |
| General Counsel hiredpersonnel | 2025-02-05 | - | - | stated |
| Chief Administrative Officer transitioning to consultingpersonnel | 2025-02-05 | 2025-01-31 | - | delayed |
| Chief Administrative Officer position eliminatedpersonnel | 2025-02-05 | - | - | stated |
| Chief Technology Officer resignationpersonnel | 2025-02-05 | 2025-01-31 | - | delayed |
| Chief Technology Officer searchpersonnel | 2025-02-05 | - | - | stated |
| $225M Preferred Units from Macquariefinancing | 2025-01-13 | - | 225000000.0 USD | stated |
| 15% Common Units equity to Macquariefinancing | 2025-01-13 | - | 15.0 percent | stated |
| Optional $675M funding for 300 MW expansionfinancing - Ellendale | 2025-01-13 | - | 675000000.0 USD | stated |
| Optional $4.1B for future HPC projectsfinancing | 2025-01-13 | - | 4100000000.0 USD | stated |
| 12.75% annual dividend on Preferred Unitsfinancing | 2025-01-13 | - | 12.75 percent | stated |
| 1.80x liquidation preference multiplefinancing | 2025-01-13 | - | 1.8 multiple | stated |
| 8.9M share warrants at $8.29 exercise pricefinancing | 2025-01-13 | - | 8916138.0 shares | stated |
| ELN Campus 100 MW initial phasefacility capacity - Ellendale | 2025-01-13 | - | 100.0 MW | stated |
| ELN Campus 300 MW expansion phasefacility capacity - Ellendale | 2025-01-13 | - | 300.0 MW | stated |
| Closing expected within 15 business daysfacility timeline | 2025-01-13 | - | 15.0 business days | stated |
| Transaction Documents finalization deadline February 15, 2025facility timeline | 2025-01-13 | 2025-02-15 | - | delayed |
| 15 months to execute remaining 300 MW leasesfacility timeline - Ellendale | 2025-01-13 | - | 15.0 months | stated |
| $1.0M per MW Company matching contribution for ELN Campusfinancing - Ellendale | 2025-01-13 | - | 1.0 million USD per MW | stated |
| $750K per MW Company matching for future projectsfinancing | 2025-01-13 | - | 0.75 million USD per MW | stated |
| First warrant exercisable 6 months post-Closing upon $900M fundingfacility timeline - Ellendale | 2025-01-13 | - | 6.0 months | stated |
| Second warrant requires 250+ MW lease with 100+ MW on modified net termsfacility capacity | 2025-01-13 | - | 250.0 MW | stated |
| Estimated Closing Distribution of $432Mfinancing | 2025-01-13 | - | 432000000.0 USD | stated |
| Macquarie Asset Management equity investment partnershippartnership - Ellendale | 2025-01-13 | - | - | stated |
| PSU grant to Wes Cumminspersonnel | 2025-01-07 | - | 1600000.0 units | stated |
| PSU grant to Saidal Mohmandpersonnel | 2025-01-07 | - | 490000.0 units | stated |
| PSU grant to David Renchpersonnel | 2025-01-07 | - | 612500.0 units | stated |
| 100MW data center Building A at Ellendale, North Dakotafacility capacity - Polaris Forge 1 | 2025-01-07 | - | 100.0 MW | stated |
| 100MW data center Building B at Ellendale, North Dakotafacility capacity - Polaris Forge 1 | 2025-01-07 | - | 100.0 MW | stated |
| Entry into lease with hyperscaler for 100MW Building Afacility timeline - Polaris Forge 1 | 2025-01-07 | 2027-12-31 | - | stated |
| Real estate project financing for Building A constructionfinancing - Polaris Forge 1 | 2025-01-07 | 2027-12-31 | - | stated |
| Entry into lease with hyperscaler for 100MW Building Bfacility timeline - Polaris Forge 1 | 2025-01-07 | 2027-12-31 | - | stated |
| Sustainable revenue and positive net operating income from Building Aguidance | 2025-01-07 | 2027-12-31 | - | stated |
| Laura Laltrello appointed Chief Operating Officerpersonnel | 2025-01-05 | 2025-01-06 | - | delayed |
| Employment inducement award to Chief Operating Officerpersonnel | 2025-01-05 | 2025-01-06 | - | delayed |
| COO appointment - Laura Laltrellopersonnel | 2024-12-03 | 2025-01-06 | - | delayed |
| COO annual base salarypersonnel | 2024-12-03 | - | 550000.0 USD | stated |
| COO annual performance bonus targetpersonnel | 2024-12-03 | - | 80.0 percent | stated |
| COO sign-on bonuspersonnel | 2024-12-03 | - | 300000.0 USD | stated |
| COO restricted stock unit grantpersonnel | 2024-12-03 | - | 600000.0 units | stated |
| $150 million loan from Macquarie Equipment Capitalfinancing | 2024-12-01 | - | 150.0 USD | stated |
| Promissory note maturity May 27, 2026financing | 2024-12-01 | 2026-05-27 | 150.0 USD | delayed |
| ELN-02 Project completion deadlinefacility timeline - Polaris Forge 1 | 2024-12-01 | 2025-12-06 | - | delayed |
| Warrant issuance for 1,035,197 shares at $9.66 per sharefinancing | 2024-12-01 | - | 1035197.0 shares | stated |
| CEO and Chairmanpersonnel | 2024-11-28 | - | - | stated |
| CEO equity compensation - April 2023 grantpersonnel | 2024-11-28 | 2026-04-04 | 600000.0 RSUs | delayed |
| CEO equity compensation - October 2024 grantpersonnel | 2024-11-28 | 2027-10-10 | 600000.0 RSUs | stated |
| Crypto mining customer contractscustomer | 2024-11-21 | - | 7.0 customers | stated |
| Data center hosting capacity in North Dakotafacility capacity - Jamestown | 2024-11-21 | - | 286.0 MW | stated |
| Electric service agreement with upper Midwest utilitypartnership | 2024-11-21 | - | - | stated |
| HPC Jamestown facility nearing completionfacility timeline - Jamestown | 2024-11-21 | - | 7.5 MW | stated |
| HPC Ellendale 100 MW facility groundbreakingfacility timeline - Polaris Forge 1 | 2024-11-21 | - | 100.0 MW | stated |
| HPC Ellendale expected operational in 2025facility timeline - Polaris Forge 1 | 2024-11-21 | - | - | stated |
| GPU cluster deploymentproduct | 2024-11-21 | - | 1024.0 GPUs | stated |
| Future GPU acquisition and deploymentguidance | 2024-11-21 | - | - | stated |
| Super Micro partnership for cloud servicespartnership | 2024-11-21 | - | - | stated |
| HPE partnership for AI supercomputerspartnership | 2024-11-21 | - | - | stated |
| Dell supply agreementpartnership | 2024-11-21 | - | - | stated |
| Series E-1 Preferred Stock offeringfinancing | 2024-11-21 | - | 62500.0 shares | stated |
| Convertible Notes offeringfinancing | 2024-11-21 | 2030-06-01 | 450.0 USD | stated |
| Private Investment in Public Equity (PIPE)financing | 2024-11-21 | - | 160.0 USD | stated |
| Chief Financial Officer transitionpersonnel | 2024-11-21 | - | - | stated |
| David Rench Chief Administrative Officerpersonnel | 2024-11-20 | - | - | stated |
| David Rench annual base salarypersonnel | 2024-11-20 | - | 475000.0 USD | stated |
| David Rench annual performance bonus targetpersonnel | 2024-11-20 | - | 100.0 percent | stated |
| David Rench restricted stock unit awardpersonnel | 2024-11-20 | - | 490000.0 units | stated |
| David Rench performance stock unit awardpersonnel | 2024-11-20 | - | 612500.0 units | stated |
| Wes Cummins performance stock unit awardpersonnel | 2024-11-20 | - | 1600000.0 units | stated |
| Saidal Mohmand performance stock unit awardpersonnel | 2024-11-20 | - | 490000.0 units | stated |
| 2024 Omnibus Equity Incentive Plan approvalregulatory | 2024-11-20 | - | 10000000.0 shares | stated |
| 100 MW Ellendale building constructionfacility capacity - Polaris Forge 1 | 2024-11-14 | - | 100.0 MW | stated |
| Series E-1 Preferred Stock offering initiatedfinancing | 2024-11-13 | - | 62500000.0 USD | stated |
| Series E-1 Preferred Stock dividend commitmentfinancing | 2024-11-13 | - | 9.0 percent | stated |
| Series E-1 Preferred Stock redemption upon holder deathfinancing | 2024-11-13 | - | - | stated |
| Initial warrant issuancefinancing | 2024-11-07 | - | 9265366.0 shares | stated |
| Conditional accordion warrant commitmentfinancing | 2024-11-07 | - | 5559220.0 shares | stated |
| Convertible notes offering completedfinancing | 2024-11-04 | - | 450.0 USD | stated |
| Convertible notes net proceedsfinancing | 2024-11-04 | - | 434.5 USD | stated |
| Intended use of proceeds for share repurchasesfinancing | 2024-11-04 | - | 84.0 USD | stated |
| Intended use of proceeds for capped call transactionsfinancing | 2024-11-04 | - | 51.8 USD | stated |
| Convertible notes interest rate and maturity datefinancing | 2024-11-04 | 2030-06-01 | 2.75 percent | stated |
| Convertible notes initial conversion pricefinancing | 2024-11-04 | - | 9.75 per share | stated |
| Convertible notes redemption eligibility datefinancing | 2024-11-04 | 2027-12-01 | - | stated |
| Prepaid forward repurchase transactionfinancing | 2024-11-04 | - | 7.2 shares | stated |
| Capped call transactions cap pricefinancing | 2024-11-04 | - | 14.72 per share | stated |
| Termination of at-the-market sales agreementfinancing | 2024-11-04 | - | - | stated |
| Yorkville funding agreement amendmentspartnership | 2024-11-04 | - | - | stated |
| Convertible Notes offeringfinancing | 2024-10-30 | 2024-11-04 | 375.0 USD | delayed |
| Option for initial purchasers to purchase additional Convertible Notesfinancing | 2024-10-30 | - | 75.0 USD | stated |
| Estimated net proceeds from offeringfinancing | 2024-10-30 | - | 361.8 USD | stated |
| Use of proceeds for capped call transactionsfinancing | 2024-10-30 | - | 43.1 USD | stated |
| Use of proceeds for prepaid forward transactionfinancing | 2024-10-30 | - | 52.7 USD | stated |
| Use of proceeds for share repurchasefinancing | 2024-10-30 | - | 31.3 USD | stated |
| $300M Convertible Senior Notes Offering Due 2030financing | 2024-10-29 | - | 300.0 USD | stated |
| $45M Greenshoe Option on Convertible Notesfinancing | 2024-10-29 | - | 45.0 USD | stated |
| Share Repurchase Programfinancing | 2024-10-29 | - | - | stated |
| Promissory Note Repaymentfinancing | 2024-10-29 | - | 6.9 USD | stated |
| PIPE Private Placementfinancing | 2024-10-28 | - | 160.0 million USD | stated |
| Standby Equity Purchase Agreement with YA Fundfinancing | 2024-10-28 | - | 250.0 million USD | stated |
| Series E-1 Redeemable Preferred Stock Offeringfinancing | 2024-10-28 | - | 62.5 million USD | stated |
| HPC Ellendale Facility Expected Operational Datefacility timeline - Ellendale | 2024-10-28 | 2025-12-31 | 100.0 MW | delayed |
| HPC Jamestown Facility Under Constructionfacility capacity - Jamestown | 2024-10-28 | - | 7.5 MW | stated |
| HPE Partnership for AI Supercomputerspartnership | 2024-10-28 | - | - | stated |
| Wes Cummins CEO and Chairmanpersonnel | 2024-10-22 | - | - | stated |
| Ella Benson Directorpersonnel | 2024-10-22 | - | - | stated |
| Rachel Lee Directorpersonnel | 2024-10-22 | - | - | stated |
| 2024 Equity Compensation Planfinancing | 2024-10-22 | 2024-11-20 | 10000000.0 shares | delayed |
| Series F Convertible Preferred Stock conversion authorizationfinancing | 2024-10-22 | 2024-11-20 | - | delayed |
| Articles amendment to increase authorized sharesregulatory | 2024-10-22 | 2024-11-20 | - | delayed |
| Crypto mining customer basecustomer | 2024-10-22 | - | - | stated |
| Current data center hosting capacityfacility capacity - Jamestown | 2024-10-22 | - | 286.0 MW | stated |
| Sale of Garden City, TX data center campusacquisition | 2024-10-22 | 2024-04-01 | - | delayed |
| HPC data center facility in Jamestownfacility capacity - Jamestown | 2024-10-22 | - | 7.5 MW | stated |
| HPC data center facility in Ellendalefacility capacity - Ellendale | 2024-10-22 | - | 100.0 MW | stated |
| HPC Ellendale facility operational timelinefacility timeline - Ellendale | 2024-10-22 | - | - | stated |
| Cloud Services Business launchproduct | 2024-10-22 | - | - | stated |
| Cloud Services GPU deploymentproduct | 2024-10-22 | - | 6144.0 units | stated |
| Cloud Services customer basecustomer | 2024-10-22 | - | - | stated |
| Partnership with Super Micropartnership | 2024-10-22 | - | - | stated |
| Partnership with HPEpartnership | 2024-10-22 | - | - | stated |
| Supply agreement with Dellpartnership | 2024-10-22 | - | - | stated |
| Chief Financial Officer appointmentpersonnel | 2024-10-22 | 2024-10-15 | - | delayed |
| PIPE common stock offeringfinancing | 2024-10-22 | 2024-09-09 | 160.0 USD | delayed |
| Series F Preferred Stock offeringfinancing | 2024-10-22 | 2024-08-30 | 50.0 USD | delayed |
| Standby Equity Purchase Agreementfinancing | 2024-10-22 | 2027-10-01 | 250.0 USD | stated |
| Series E-1 Preferred Stock offeringfinancing | 2024-10-22 | - | - | stated |
| Series E Preferred Stock offering proceedsfinancing | 2024-10-17 | - | 6.9 USD | stated |
| At-the-Market Sales Agreement capacity and proceedsfinancing | 2024-10-17 | - | 125000000.0 USD | stated |
| Garden City escrow releasefinancing - Garden City | 2024-10-17 | - | 25.0 USD | stated |
| Standby Equity Purchase Agreement with YA Fundfinancing | 2024-10-17 | 2027-09-30 | 250.0 USD | stated |
| PIPE offering proceedsfinancing | 2024-10-17 | 2024-09-09 | 160.0 USD | delayed |
| CIM Promissory Note total outstanding balancefinancing | 2024-10-17 | - | 125.0 USD | stated |
| YA Notes conversion and outstanding balancefinancing | 2024-10-17 | - | 85.9 USD | stated |
| Crypto mining customer contractscustomer | 2024-10-17 | - | - | stated |
| Cloud Services Business customerscustomer | 2024-10-17 | - | - | stated |
| Existing data center hosting capacityfacility capacity - Jamestown | 2024-10-17 | - | 286.0 MW | stated |
| Jamestown HPC facility nearing completionfacility timeline - Jamestown | 2024-10-17 | - | 7.5 MW | stated |
| Ellendale HPC facility expected operational datefacility timeline - Polaris Forge 1 | 2024-10-17 | 2025-12-31 | 100.0 MW | delayed |
| Sale of Garden City hosting facility to Marathon Digital Holdingsacquisition | 2024-10-17 | 2024-04-01 | 200.0 MW | delayed |
| Strategy advisory partnership with GMR and SparkPoolpartnership | 2024-10-17 | - | 7440148.0 shares | stated |
| Partnership with Super Micro for cloud servicespartnership | 2024-10-17 | - | - | stated |
| Partnership with HPE for supercomputerspartnership | 2024-10-17 | - | - | stated |
| Supply agreement with Dell for AI serverspartnership | 2024-10-17 | - | - | stated |
| GPU deployment and revenue recognition statusproduct | 2024-10-17 | - | 6144.0 units | stated |
| GPU cluster capacity for cloud servicesproduct | 2024-10-17 | - | 1024.0 units | stated |
| Cloud Services Business growth expectationsguidance | 2024-10-17 | - | - | stated |
| David Rench transitioning from CFO to Chief Administrative Officerpersonnel | 2024-10-14 | 2024-10-15 | - | delayed |
| Saidal Mohmand appointed Chief Financial Officerpersonnel | 2024-10-14 | 2024-10-15 | - | delayed |
| Saidal Mohmand CFO base salarypersonnel | 2024-10-14 | 2024-10-15 | 475000.0 USD | delayed |
| Saidal Mohmand target annual bonuspersonnel | 2024-10-14 | - | 75.0 percent | stated |
| Saidal Mohmand restricted stock units awardpersonnel | 2024-10-14 | - | 490000.0 units | stated |
| Saidal Mohmand performance stock units awardpersonnel | 2024-10-14 | - | 490000.0 units | stated |
| Wes Cummins CEO base salarypersonnel | 2024-10-14 | 2024-06-01 | 750000.0 USD | delayed |
| Wes Cummins target annual bonuspersonnel | 2024-10-14 | - | 100.0 percent | stated |
| Wes Cummins Employment Agreement termpersonnel | 2024-10-14 | 2027-10-10 | - | stated |
| 2024 Equity Compensation Plan - 10 million share reservationfinancing | 2024-10-10 | - | 10000000.0 shares | stated |
| Jason Zhang RSU Vestingpersonnel | 2024-10-10 | 2024-11-07 | 613152.0 shares | delayed |
| Jason Zhang RSU Vestingpersonnel | 2024-10-10 | 2025-04-04 | 40000.0 shares | delayed |
| Jason Zhang RSU Vestingpersonnel | 2024-10-10 | 2025-10-04 | 40000.0 shares | delayed |
| Jason Zhang RSU Vestingpersonnel | 2024-10-10 | 2026-04-04 | 40000.0 shares | delayed |
| Series E Preferred Stock issuancefinancing | 2024-10-08 | - | 301673.0 shares | stated |
| Series F Preferred Stock issuancefinancing | 2024-10-08 | - | 53191.0 shares | stated |
| Long-term debt borrowingfinancing | 2024-10-08 | - | 105000.0 USD | stated |
| Common stock offeringfinancing | 2024-10-08 | - | 6124218.0 shares | stated |
| Debt conversion to equityfinancing | 2024-10-08 | - | 11392978.0 shares | stated |
| Yorkville amendment shares issuancefinancing | 2024-10-08 | - | 100000.0 shares | stated |
| CIM warrants issuancefinancing | 2024-10-08 | - | 36479.0 USD | stated |
| SAFE agreement proceedsfinancing | 2024-10-08 | - | 12000.0 USD | stated |
| Data Center Hosting customerscustomer | 2024-10-03 | - | - | stated |
| Jamestown, ND data center capacityfacility capacity - Jamestown | 2024-10-03 | - | 106.0 MW | stated |
| Ellendale, ND data center capacityfacility capacity - Ellendale | 2024-10-03 | - | 180.0 MW | stated |
| Total Data Center Hosting capacityfacility capacity | 2024-10-03 | - | 286.0 MW | stated |
| HPC facility in Jamestownfacility capacity - Jamestown | 2024-10-03 | - | 7.5 MW | stated |
| HPC Ellendale Facility capacityfacility capacity - Polaris Forge 1 | 2024-10-03 | - | 100.0 MW | stated |
| HPC Ellendale Facility operational timelinefacility timeline - Polaris Forge 1 | 2024-10-03 | 2025-12-31 | - | delayed |
| Services Agreement with GMR, SparkPool, and Valuefinderpartnership | 2024-10-03 | - | - | stated |
| Super Micro partnershippartnership | 2024-10-03 | - | - | stated |
| HPE partnershippartnership | 2024-10-03 | - | - | stated |
| Dell supply agreementpartnership | 2024-10-03 | - | - | stated |
| Sale of Garden City, TX facilityacquisition | 2024-10-03 | 2024-04-01 | - | delayed |
| GPU deploymentproduct | 2024-10-03 | - | 6144.0 units | stated |
| Cloud Services customerscustomer | 2024-10-03 | - | - | stated |
| Series F Preferred Stock offeringfinancing | 2024-10-03 | 2024-08-30 | 50.0 USD | delayed |
| Series E Preferred Stock proceedsfinancing | 2024-10-03 | - | 6.9 USD | stated |
| CIM Promissory Note initial borrowingfinancing | 2024-10-03 | 2024-06-07 | 15.0 USD | delayed |
| CIM Promissory Note subsequent borrowingsfinancing | 2024-10-03 | - | 110.0 USD | stated |
| CIM Promissory Note accordion featurefinancing | 2024-10-03 | - | 75.0 USD | stated |
| CIM Promissory Note outstanding balancefinancing | 2024-10-03 | - | 105.0 USD | stated |
| SEPA commitment with YA Fundfinancing | 2024-10-03 | 2027-09-30 | 250.0 USD | stated |
| At-the-Market Sales Agreementfinancing | 2024-10-03 | - | 125.0 USD | stated |
| YA Notes conversionsfinancing | 2024-10-03 | - | 6.2 USD | stated |
| Garden City escrow releasefinancing - Garden City | 2024-10-03 | 2024-07-30 | 25.0 USD | delayed |
| Chief Executive Officerpersonnel | 2024-10-03 | - | - | stated |
| Series E-1 Preferred Stock offeringfinancing | 2024-09-26 | - | 2500000.0 shares | stated |
| Dealer Manager Agreement with Preferred Capital Securities, LLCpartnership | 2024-09-26 | - | - | stated |
| Amended and Restated Services Agreement with Preferred Shareholder Services, LLCpartnership | 2024-09-26 | - | - | stated |
| Form S-1 Registration Statement filingregulatory | 2024-09-26 | - | - | stated |
| Series E-1 Preferred Stock offeringfinancing | 2024-09-22 | - | 62500000.0 USD | stated |
| Series E Preferred Stock completed salesfinancing | 2024-09-22 | - | 6900000.0 USD | stated |
| Series F Convertible Preferred Stock placementfinancing | 2024-09-22 | - | 50000000.0 USD | stated |
| Standby Equity Purchase Agreement with YA Fundfinancing | 2024-09-22 | 2027-09-30 | 250000000.0 USD | stated |
| CIM credit facility with tranchesfinancing | 2024-09-22 | - | 200000000.0 USD | stated |
| Additional CIM Promissory Note borrowingfinancing | 2024-09-22 | - | 20000000.0 USD | stated |
| Crypto-mining customers with active contractscustomer | 2024-09-22 | - | - | stated |
| Jamestown North Dakota datacenter capacityfacility capacity - Jamestown | 2024-09-22 | - | 106.0 MW | stated |
| Ellendale North Dakota datacenter capacityfacility capacity - Ellendale | 2024-09-22 | - | 180.0 MW | stated |
| HPC focused facility in Jamestown nearing completionfacility capacity - Jamestown | 2024-09-22 | - | 7.5 MW | stated |
| 100 MW HPC facility in Ellendale with ground brokenfacility capacity - Ellendale | 2024-09-22 | - | 100.0 MW | stated |
| 400 MW capacity lease with U.S.-based hyperscalerpartnership - Ellendale | 2024-09-22 | - | 400.0 MW | stated |
| Extended exclusivity for hyperscaler 400 MW leasepartnership - Ellendale | 2024-09-22 | - | - | stated |
| Cloud Services Business customerscustomer | 2024-09-22 | - | - | stated |
| GPU deployment in Cloud Servicesproduct | 2024-09-22 | - | 6144.0 units | stated |
| HPC Ellendale facility revenue timingguidance | 2024-09-22 | 2025-12-31 | - | delayed |
| Partnership with Super Micro for GPU solutionspartnership | 2024-09-22 | - | - | stated |
| Partnership with HPE for supercomputerspartnership | 2024-09-22 | - | - | stated |
| Dell supply agreement for serverspartnership | 2024-09-22 | - | - | stated |
| Contractual energy cost ceilingregulatory | 2024-09-22 | - | - | stated |
| Services agreement for crypto asset mining managementpartnership | 2024-09-22 | - | - | stated |
| Jamestown Data Center Hosting Facilityfacility capacity - Jamestown | 2024-09-12 | - | 106.0 MW | stated |
| Ellendale Data Center Hosting Facilityfacility capacity - Ellendale | 2024-09-12 | - | 180.0 MW | stated |
| Crypto Mining Customerscustomer | 2024-09-12 | - | - | stated |
| HPC Jamestown Facilityfacility capacity - Jamestown | 2024-09-12 | - | 7.5 MW | stated |
| HPC Ellendale Facilityfacility capacity - Ellendale | 2024-09-12 | - | 100.0 MW | stated |
| HPC Ellendale Facility Operationalizationfacility timeline - Ellendale | 2024-09-12 | 2025-12-31 | - | delayed |
| Hyperscaler Capacity Lease Agreementpartnership - Ellendale | 2024-09-12 | - | 400.0 MW | stated |
| Super Micro Partnershippartnership | 2024-09-12 | - | - | stated |
| HPE Partnershippartnership | 2024-09-12 | - | - | stated |
| Electric Service Agreementpartnership | 2024-09-12 | - | - | stated |
| Cloud Services Customerscustomer | 2024-09-12 | - | - | stated |
| CIM Promissory Note Additional Borrowingfinancing | 2024-09-12 | - | 20.0 USD | stated |
| Warrant Exercise Potential Proceedsfinancing | 2024-09-12 | - | 30.2 USD | stated |
| At-the-Market Sales Agreementfinancing | 2024-09-12 | - | 125.0 USD | stated |
| Standby Equity Purchase Agreementfinancing | 2024-09-12 | 2027-10-01 | 250.0 USD | stated |
| Series F Preferred Stock Issuancefinancing | 2024-09-12 | - | 50.0 USD | stated |
| Private Placement of Common Stockfinancing | 2024-09-12 | - | 160.0 USD | stated |
| Prepaid Advance Agreement - $40M Promissory Notefinancing | 2024-09-10 | 2024-03-27 | 40000000.0 USD | delayed |
| Prepaid Advance Agreement - $10M Promissory Notefinancing | 2024-09-10 | - | 10000000.0 USD | stated |
| Current data center hosting capacityfacility capacity | 2024-09-10 | - | 286.0 MW | stated |
| Crypto mining customers with long-term contractscustomer | 2024-09-10 | - | 7.0 customers | stated |
| Sale of Garden City, TX campus to Marathon Digital Holdingsacquisition | 2024-09-10 | 2024-04-01 | 200.0 MW | delayed |
| Cloud Services Business launchproduct | 2024-09-10 | - | - | stated |
| Super Micro partnership for GPU server solutionspartnership | 2024-09-10 | - | - | stated |
| HPE partnership for AI supercomputerspartnership | 2024-09-10 | - | - | stated |
| 7.5 MW HPC facility in Jamestown, ND nearing completionfacility capacity - Jamestown | 2024-09-10 | - | 7.5 MW | stated |
| 100 MW HPC facility in Ellendale, ND with ground brokenfacility capacity - Polaris Forge 1 | 2024-09-10 | - | 100.0 MW | stated |
| HPC Ellendale Facility expected operational dateguidance | 2024-09-10 | 2025-12-31 | - | delayed |
| Letter of intent with hyperscaler for 400 MW capacity leasepartnership - Polaris Forge 1 | 2024-09-10 | - | 400.0 MW | stated |
| CIM Note senior secured term loan facilityfinancing | 2024-09-10 | 2024-06-07 | 125000000.0 USD | delayed |
| At-the-Market sales agreementfinancing | 2024-09-10 | 2024-07-09 | 125000000.0 USD | delayed |
| Hyperscaler exclusivity extension for HPC Ellendale Facilityfacility timeline - Polaris Forge 1 | 2024-09-10 | 2024-07-26 | - | delayed |
| Standby Equity Purchase Agreement (SEPA)financing | 2024-09-10 | 2024-08-28 | 250000000.0 USD | delayed |
| Series F Convertible Preferred Stock offeringfinancing | 2024-09-10 | 2024-08-30 | 50000000.0 USD | delayed |
| Cloud Services Business current customerscustomer | 2024-09-10 | - | 2.0 customers | stated |
| Expected GPU acquisition and deployment expansionguidance | 2024-09-10 | - | - | stated |
| CIM Waiver Agreement enabling additional borrowingfinancing | 2024-09-10 | 2024-08-11 | 20000000.0 USD | delayed |
| Seven established crypto mining customerscustomer | 2024-09-10 | - | - | stated |
| Total operating capacity Jamestown and Ellendalefacility capacity | 2024-09-10 | - | 286.0 MW | stated |
| Jamestown crypto mining facility capacityfacility capacity - Jamestown | 2024-09-10 | - | 106.0 MW | stated |
| Ellendale crypto mining facility capacityfacility capacity - Ellendale | 2024-09-10 | - | 180.0 MW | stated |
| Crypto mining services and equipment partnershippartnership | 2024-09-10 | - | - | stated |
| Long-term electricity supply agreementpartnership | 2024-09-10 | - | - | stated |
| Sale of Garden City hosting facilityacquisition | 2024-09-10 | - | 200.0 MW | stated |
| GPU cluster deploymentsproduct | 2024-09-10 | - | 1024.0 units | stated |
| Super Micro server and storage partnershippartnership | 2024-09-10 | - | - | stated |
| HPE supercomputer partnershippartnership | 2024-09-10 | - | - | stated |
| Dell AI and GPU server supply agreementpartnership | 2024-09-10 | - | - | stated |
| Cloud Services Business customerscustomer | 2024-09-10 | - | - | stated |
| 7.5 MW HPC facility Jamestown completion statusfacility timeline - Jamestown | 2024-09-10 | - | 7.5 MW | stated |
| 100 MW HPC facility Ellendale construction commencedfacility timeline - Polaris Forge 1 | 2024-09-10 | - | 100.0 MW | stated |
| 400 MW capacity lease with hyperscalerpartnership - Polaris Forge 1 | 2024-09-10 | - | 400.0 MW | stated |
| Extended hyperscaler exclusivity HPC Ellendalepartnership - Polaris Forge 1 | 2024-09-10 | - | - | stated |
| HPC Ellendale Facility operational timelineguidance | 2024-09-10 | 2025-12-31 | - | delayed |
| At-the-Market offering facilityfinancing | 2024-09-10 | - | 125000000.0 USD | stated |
| Garden City sale escrow funds releasefinancing - Garden City | 2024-09-10 | - | 25000000.0 USD | stated |
| Standby Equity Purchase Agreement with YA Fundfinancing | 2024-09-10 | 2027-09-30 | 250000000.0 USD | stated |
| Series F Convertible Preferred Stock offeringfinancing | 2024-09-10 | - | 50000000.0 USD | stated |
| Goldman-backed PIPE offeringfinancing | 2024-09-10 | - | 160000000.0 USD | stated |
| Private placement of common stockfinancing | 2024-09-09 | - | 160.0 USD | stated |
| Standby Equity Purchase Agreement with YA Fundfinancing | 2024-09-09 | - | 250.0 USD | stated |
| Placement agent fee to Northland Securities for SEPAfinancing | 2024-09-09 | - | 528541.0 shares | stated |
| Series F offering proceedsfinancing | 2024-08-29 | 2024-08-30 | 50.0 USD | delayed |
| Series F Preferred Stock convertible share countfinancing | 2024-08-29 | - | 7598714.0 units | stated |
| Series F Preferred Stock dividend ratefinancing | 2024-08-29 | - | 8.0 percent | stated |
| Series F registration rights commitmentfinancing | 2024-08-29 | 2024-10-13 | - | delayed |
| Prepaid Advance conversion limitation eliminationfinancing | 2024-08-29 | - | - | stated |
| Prepaid Advance early redemption datefinancing | 2024-08-29 | 2025-01-01 | - | delayed |
| Series F Preferred Stock redemption windowfinancing | 2024-08-29 | 2024-12-31 | 1000.0 USD | delayed |
| Placement agent transaction feesfinancing | 2024-08-29 | - | 3.5 percent | stated |
| Jamestown data center hosting capacityfacility capacity - Jamestown | 2024-08-29 | - | 106.0 MW | stated |
| Ellendale data center hosting capacityfacility capacity - Ellendale | 2024-08-29 | - | 180.0 MW | stated |
| HPC Jamestown facility nearing completionfacility timeline - Jamestown | 2024-08-29 | - | 7.5 MW | stated |
| HPC Ellendale facility under constructionfacility timeline - Polaris Forge 1 | 2024-08-29 | - | 100.0 MW | stated |
| Hyperscaler lease for 400 MW HPC capacitycustomer - Polaris Forge 1 | 2024-08-29 | - | 400.0 MW | stated |
| HPC Ellendale facility expected operational in calendar year 2025guidance | 2024-08-29 | - | - | stated |
| Partnership with Super Micro for cloud servicespartnership | 2024-08-29 | - | - | stated |
| Partnership with HPE for AI supercomputerspartnership | 2024-08-29 | - | - | stated |
| Supply agreement with Dell for AI and GPU serverspartnership | 2024-08-29 | - | - | stated |
| GPU clusters for cloud servicesproduct | 2024-08-29 | - | 1024.0 GPUs | stated |
| Financing discussions for HPC Ellendalefinancing - Polaris Forge 1 | 2024-08-29 | - | - | stated |
| Amended and Restated Electric Service Agreementpartnership | 2024-08-29 | - | - | stated |
| Crypto mining customers with multi-year contractscustomer | 2024-08-29 | - | 7.0 customers | stated |
| 7.5 MW HPC data center facility in Jamestown, North Dakotafacility capacity - Jamestown | 2024-08-29 | - | 7.5 MW | stated |
| 100 MW HPC data center facility in Ellendale, North Dakotafacility capacity - Polaris Forge 1 | 2024-08-29 | - | 100.0 MW | stated |
| Letter of intent with US-based hyperscaler for HPC capacity leasecustomer - Polaris Forge 1 | 2024-08-29 | - | 400.0 MW | stated |
| HPC Ellendale Facility expected to become operationalfacility timeline - Polaris Forge 1 | 2024-08-29 | - | - | stated |
| Multiple GPU clusters with 1,024 GPU capacityproduct | 2024-08-29 | - | - | stated |
| Cloud Services GPU deployment and revenue growth expectationsguidance | 2024-08-29 | - | - | stated |
| Partnership with HPE for AI supercomputer provisionpartnership | 2024-08-29 | - | - | stated |
| Partnership with Super Micro for cloud services deliverypartnership | 2024-08-29 | - | - | stated |
| Supply agreement with Dell for AI and GPU serverspartnership | 2024-08-29 | - | - | stated |
| Seven crypto mining customers with multi-year hosting contractscustomer | 2024-08-29 | - | 7.0 | stated |
| Crypto mining customer basecustomer | 2024-08-29 | - | 7.0 customers | stated |
| Current data center hosting capacityfacility capacity | 2024-08-29 | - | 286.0 MW | stated |
| Sale of Garden City, TX data center campus to Marathon Digitalacquisition | 2024-08-29 | 2024-04-01 | 200.0 MW | delayed |
| Super Micro partnership for cloud infrastructurepartnership | 2024-08-29 | - | - | stated |
| HPE partnership for AI supercomputerspartnership | 2024-08-29 | - | - | stated |
| Electric Service Agreement with energy cost ceilingpartnership | 2024-08-29 | - | - | stated |
| GPU deployment for cloud servicesproduct | 2024-08-29 | - | 6144.0 GPUs | stated |
| Cloud Services Business launch and customer baseproduct | 2024-08-29 | - | 2.0 customers | stated |
| Jamestown HPC facility under developmentfacility timeline - Jamestown | 2024-08-29 | - | 7.5 MW | stated |
| Ellendale HPC facility under constructionfacility timeline - Polaris Forge 1 | 2024-08-29 | - | 100.0 MW | stated |
| Hyperscaler capacity lease commitmentcustomer - Polaris Forge 1 | 2024-08-29 | - | 400.0 MW | stated |
| HPC Ellendale Facility operational timingfacility timeline - Polaris Forge 1 | 2024-08-29 | - | - | stated |
| Financing discussions for HPC Ellendale Facilityfinancing - Polaris Forge 1 | 2024-08-29 | - | - | stated |
| Employee workforcepersonnel | 2024-08-29 | - | 150.0 employees | stated |
| Total hosting capacity across North Dakota sitesfacility capacity | 2024-08-29 | - | 286.0 MW | stated |
| Jamestown data center hosting capacityfacility capacity - Jamestown | 2024-08-29 | - | 106.0 MW | stated |
| Ellendale data center hosting capacityfacility capacity - Ellendale | 2024-08-29 | - | 180.0 MW | stated |
| Data center hosting customerscustomer | 2024-08-29 | - | 7.0 customers | stated |
| Ongoing partnership with GMR as strategic equity investorpartnership | 2024-08-29 | - | - | stated |
| Amended and Restated Electric Service Agreementpartnership | 2024-08-29 | - | - | stated |
| Partnership with Super Micro for cloud servicespartnership | 2024-08-29 | - | - | stated |
| Partnership with HPE for cloud services and AIpartnership | 2024-08-29 | - | - | stated |
| Supply agreement with Dell for AI and GPU serverspartnership | 2024-08-29 | - | - | stated |
| Cloud Services Business customerscustomer | 2024-08-29 | - | 2.0 customers | stated |
| Jamestown HPC facility nearing completionfacility timeline - Jamestown | 2024-08-29 | - | 7.5 MW | stated |
| Ellendale HPC data center groundbreakingfacility timeline - Polaris Forge 1 | 2024-08-29 | - | 100.0 MW | stated |
| Letter of intent with US-based hyperscaler for capacity leasecustomer - Polaris Forge 1 | 2024-08-29 | - | 400.0 MW | stated |
| Advanced financing discussions for HPC Ellendale facilityfinancing - Polaris Forge 1 | 2024-08-29 | - | - | stated |
| HPC Ellendale facility expected operational dateguidance | 2024-08-29 | 2025-12-31 | - | delayed |
| Full-time employee countpersonnel | 2024-08-29 | - | 150.0 employees | stated |
| GPU clusters for cloud servicesproduct | 2024-08-29 | - | 1024.0 GPUs per cluster | stated |
| Secured $150M in fundingfinancing | 2024-08-28 | - | 150.0 USD | stated |
| $25M released from Garden City sale escrowfinancing - Garden City | 2024-08-28 | 2024-07-30 | 25.0 USD | delayed |
| Together AI as new Cloud Services customercustomer | 2024-08-28 | - | - | stated |
| 286 MW of operating data center hosting capacityfacility capacity | 2024-08-28 | - | 286.0 MW | stated |
| Ellendale facility restored to full operating capacityfacility timeline - Ellendale | 2024-08-28 | 2024-06-28 | - | delayed |
| 400 MW LOI with US-based hyperscalerpartnership - Polaris Forge 1 | 2024-08-28 | - | 400.0 MW | stated |
| Extended LOI exclusivity period for Ellendale campusfacility timeline - Polaris Forge 1 | 2024-08-28 | 2024-07-26 | - | delayed |
| Next two buildings with 300 MW capacity under designfacility capacity - Polaris Forge 1 | 2024-08-28 | - | 300.0 MW | stated |
| Three additional campuses totaling 1.4 GW under developmentfacility capacity | 2024-08-28 | - | 1.4 GW | stated |
| 100 MW facility with liquid-cooled HPC infrastructureproduct | 2024-08-28 | - | - | stated |
| Loan agreement with Tranche 1 warrant issuancefinancing | 2024-06-16 | - | - | stated |
| Conditional Tranche 2 warrant rightfinancing | 2024-06-16 | - | - | stated |
| Accordion loan and warrant programfinancing | 2024-06-16 | - | - | stated |
| CIM Warrant Offeringfinancing | 2024-06-16 | 2024-06-17 | 6300449.0 shares | delayed |
| CIM Initial Borrowingfinancing | 2024-06-16 | 2024-06-07 | 15000000.0 USD | delayed |
| CIM Subsequent Borrowing Availabilityfinancing | 2024-06-16 | - | 110000000.0 USD | stated |
| CIM Accordion Feature Availabilityfinancing | 2024-06-16 | - | 75000000.0 USD | stated |
| Jamestown North Dakota Hosting Facilityfacility capacity - Jamestown | 2024-06-16 | - | 106.0 MW | stated |
| Ellendale North Dakota Hosting Facilityfacility capacity - Ellendale | 2024-06-16 | - | 180.0 MW | stated |
| Total Datacenter Hosting Capacityfacility capacity | 2024-06-16 | - | 286.0 MW | stated |
| Jamestown GPU Hosting Buildingfacility capacity - Jamestown | 2024-06-16 | - | 9.0 MW | stated |
| HPC Ellendale Datacenter Construction and Operational Timelinefacility timeline - Polaris Forge 1 | 2024-06-16 | - | 100.0 MW | stated |
| Sale of Garden City Campus to Marathon Digital Holdingsacquisition | 2024-06-16 | 2024-04-01 | 200.0 MW | delayed |
| Cloud Services Business Launchproduct | 2024-06-16 | - | - | stated |
| Cloud Services AI Customerscustomer | 2024-06-16 | - | 36.0 months | stated |
| GPU Cluster Rolloutproduct | 2024-06-16 | - | 1024.0 GPUs | stated |
| AI Bridge Warrant Issuancefinancing | 2024-06-16 | 2024-04-26 | 3000000.0 shares | delayed |
| Roth Capital Partners Sales Agreementfinancing | 2024-06-16 | 2024-05-06 | 25000000.0 USD | delayed |
| Series E Redeemable Preferred Stock Offeringfinancing | 2024-06-16 | 2024-05-16 | 2000000.0 shares | delayed |
| Share Issuance to YA II PN for Consentfinancing | 2024-06-16 | - | 100000.0 shares | stated |
| Super Micro Partnership for Cloud Servicespartnership | 2024-06-16 | - | - | stated |
| HPE Partnership for AI Supercomputerspartnership | 2024-06-16 | - | - | stated |
| Dell GPU Server Supply Agreementpartnership | 2024-06-16 | - | - | stated |
| Authorized Shares Charter Amendmentregulatory | 2024-06-16 | 2024-06-11 | 300000000.0 shares | delayed |
| Cloud Services Business Revenue Contribution Guidanceguidance | 2024-06-16 | - | 13.0 percent | stated |
| Initial borrowing under CIM promissory notefinancing | 2024-06-16 | - | 15.0 USD | stated |
| Subsequent borrowings available under CIM promissory notefinancing | 2024-06-16 | - | 110.0 USD | stated |
| Accordion feature for additional borrowingsfinancing | 2024-06-16 | - | 75.0 USD | stated |
| Warrant issued to CIM for common stock purchasefinancing | 2024-06-16 | - | 6300449.0 shares | stated |
| Initial borrowing from CIM APLD Lender Holdingsfinancing | 2024-06-06 | - | 15.0 USD | stated |
| Subsequent borrowing tranches from CIMfinancing | 2024-06-06 | - | 110.0 USD | stated |
| Accordion feature for additional borrowingfinancing | 2024-06-06 | - | 75.0 USD | stated |
| Warrant issuance (first tranche)financing | 2024-06-06 | 2024-06-17 | 6300449.0 shares | delayed |
| Warrant issuance (second tranche, private placement)financing | 2024-06-06 | - | 2964917.0 shares | stated |
| Additional warrant issuance contingent on accordion drawsfinancing | 2024-06-06 | - | 5559220.0 shares | stated |
| Common share issuance to Yorkville in exchange for consentfinancing | 2024-06-06 | - | 100000.0 shares | stated |
| Form S-1 registration of Private Placement Warrant sharesregulatory | 2024-06-06 | - | - | stated |
| ELN-02 Project hyperscale lease as condition for final $40M tranchefacility timeline - Polaris Forge 1 | 2024-06-06 | - | 40.0 USD | stated |
| Yorkville consent for future project-level financing at Ellendale Campuspartnership - Ellendale | 2024-06-06 | - | - | stated |
| Conditional prepayment obligation to Yorkville if registration statement not effective by July 8financing | 2024-06-06 | 2024-07-08 | 2.5 USD per week | delayed |
| Loan received from B. Riley Commercial Capitalfinancing | 2024-06-04 | - | - | stated |
| Early loan repaymentfinancing | 2024-06-04 | - | - | stated |
| Cryptocurrency mining business segmentproduct | 2024-06-04 | - | - | stated |
| Prepaid Advance Agreement with YA II PN, LTD.financing | 2024-05-30 | - | 42131579.0 USD | stated |
| First Promissory Note to YA II PN, LTD.financing | 2024-05-30 | 2024-03-27 | 40000000.0 USD | delayed |
| Second Promissory Note to YA II PN, LTD.financing | 2024-05-30 | 2024-04-24 | 10000000.0 USD | delayed |
| Sales Agreement with Roth Capital Partnersfinancing | 2024-05-30 | 2024-05-06 | 25000000.0 USD | delayed |
| Series E Redeemable Preferred Stock offeringfinancing | 2024-05-30 | 2024-05-16 | 2000000.0 shares | delayed |
| Jamestown, North Dakota datacenter facilityfacility capacity - Jamestown | 2024-05-30 | - | 106.0 MW | stated |
| Ellendale, North Dakota datacenter facilityfacility capacity - Ellendale | 2024-05-30 | - | 180.0 MW | stated |
| Jamestown GPU facilityfacility capacity - Jamestown | 2024-05-30 | - | 9.0 MW | stated |
| HPC Ellendale Facility under constructionfacility timeline - Polaris Forge 1 | 2024-05-30 | 2025-01-01 | 100.0 MW | delayed |
| Sale of Garden City, Texas facility to Marathon Digital Holdingsacquisition | 2024-05-30 | 2024-04-01 | 200.0 MW | delayed |
| Services Agreement with GMR, SparkPool, and Valuefinderpartnership | 2024-05-30 | - | - | stated |
| Partnership with Super Micro Computer Inc.partnership | 2024-05-30 | - | - | stated |
| Partnership with Hewlett Packard Enterprisepartnership | 2024-05-30 | - | - | stated |
| Supply agreements with Dell Technologiespartnership | 2024-05-30 | - | - | stated |
| Electric Service Agreement with upper Midwest utilitypartnership | 2024-05-30 | - | - | stated |
| GPU clusters for cloud servicesproduct | 2024-05-30 | - | 1024.0 GPUs | stated |
| Cloud Services Business launchproduct | 2024-05-30 | - | - | stated |
| First major AI customer in Cloud Services Businesscustomer | 2024-05-30 | - | - | stated |
| Second Cloud Services customer with 36-month contractcustomer | 2024-05-30 | - | 36.0 months | stated |
| Four crypto-mining customerscustomer | 2024-05-30 | - | - | stated |
| Cloud Services Business revenue guidanceguidance | 2024-05-30 | - | 10.0 percent | stated |
| Wes Cummins, Chief Executive Officerpersonnel | 2024-05-30 | - | - | stated |
| Convertible promissory note issuancefinancing | 2024-05-23 | - | 42131579.0 USD | stated |
| Promissory Note maturity datefinancing | 2024-05-23 | 2025-06-06 | - | delayed |
| Form S-1 registration statement effective date requirementfinancing | 2024-05-23 | 2024-07-01 | - | delayed |
| Financing for Ellendale data center facilityfacility timeline - Ellendale | 2024-05-23 | - | - | stated |
| Promissory Note interest ratefinancing | 2024-05-23 | - | - | stated |
| Monthly conversion limitfinancing | 2024-05-23 | - | 16000000.0 USD | stated |
| Promissory Note conversion price termsfinancing | 2024-05-23 | - | - | stated |
| Subsidiary guaranty of promissory note obligationsfinancing | 2024-05-23 | - | - | stated |
| Series E Preferred Stock Offeringfinancing | 2024-05-16 | - | 50000000.0 USD | stated |
| Net Proceeds from Series E Offeringfinancing | 2024-05-16 | - | 46000000.0 USD | stated |
| Jamestown Datacenter Capacityfacility capacity - Jamestown | 2024-05-16 | - | 106.0 MW | stated |
| Ellendale Datacenter Capacityfacility capacity - Ellendale | 2024-05-16 | - | 180.0 MW | stated |
| Cloud Services Hosting Capacityfacility capacity - Jamestown | 2024-05-16 | - | 9.0 MW | stated |
| HPC Ellendale Facility Constructionfacility timeline - Polaris Forge 1 | 2024-05-16 | - | 100.0 MW | stated |
| HPC Ellendale Operational Startfacility timeline - Polaris Forge 1 | 2024-05-16 | 2025-01-01 | - | delayed |
| Super Micro Partnershippartnership | 2024-05-16 | - | - | stated |
| HPE Partnershippartnership | 2024-05-16 | - | - | stated |
| Crypto Mining Customerscustomer | 2024-05-16 | - | 4.0 customers | stated |
| Cloud Services Customer Contractcustomer | 2024-05-16 | 2026-06-01 | 36.0 months | delayed |
| Garden City Campus Sale to Marathon Digitalacquisition | 2024-05-16 | 2024-04-01 | 200.0 MW | delayed |
| GPU Cluster Configurationproduct | 2024-05-16 | - | 1024.0 GPUs | stated |
| GPU Deployment Progressproduct | 2024-05-16 | 2024-02-29 | 3072.0 GPUs | delayed |
| Cloud Services Revenue Guidance FY2024guidance | 2024-05-16 | - | 13.0 percent | stated |
| Future GPU Acquisition Plansguidance | 2024-05-16 | - | - | stated |
| Series E Preferred Stock offering via dealer managerfinancing | 2024-05-16 | - | 2000000.0 shares | stated |
| Series E Preferred Stock dividend ratefinancing | 2024-05-16 | - | 9.0 percent | stated |
| AI Bridge Funding promissory note prepaid via common stock issuancefinancing | 2024-05-16 | - | 8421146.0 shares | stated |
| Common stock issuance cap for Series E Preferred Stock redemptionsregulatory | 2024-05-16 | - | 19.99 percent | stated |
| Notice requirement before Series E Preferred Stock exchange listingregulatory | 2024-05-16 | - | 60.0 days | stated |
| Ownership of SAI Computing LLC businessacquisition | 2024-05-13 | - | - | stated |
| Cloud services business operationproduct | 2024-05-13 | - | - | stated |
| Wes Cummins appointed to Board of Applied Digital Cloudpersonnel | 2024-05-13 | - | - | stated |
| Richard Nottenburg appointed Chairman of Applied Digital Cloudpersonnel | 2024-05-13 | - | - | stated |
| Board appointment of Ella Bensonpersonnel | 2024-05-06 | 2024-05-06 | - | delayed |
| 400 MW hyperscaler capacity lease LOIpartnership - Ellendale | 2024-04-11 | - | 400.0 MW | stated |
| Together AI Cloud Services customercustomer | 2024-04-11 | - | - | stated |
| Ellendale facility capacity recovery targetfacility timeline - Ellendale | 2024-04-11 | 2024-05-31 | - | delayed |
| Ellendale campus future capacity potentialfacility capacity - Ellendale | 2024-04-11 | - | 600.0 MW | stated |
| Project-level financing for 400 MW hyperscaler leasefinancing - Ellendale | 2024-04-11 | - | - | stated |
| 100 MW HPC facility under construction in Ellendalefacility capacity - Ellendale | 2024-04-11 | - | 100.0 MW | stated |
| Ellendale facility building specificationsfacility capacity - Ellendale | 2024-04-11 | - | 342000.0 sq ft | stated |
| Asset sales and financing transactionsfinancing | 2024-04-11 | - | 160.0 USD | stated |
| Independent director appointmentpersonnel | 2024-02-21 | 2024-02-22 | - | delayed |
| Board committee assignmentpersonnel | 2024-02-21 | - | - | stated |
| Director equity compensationpersonnel | 2024-02-21 | - | - | stated |
| Director resignationspersonnel | 2024-02-21 | 2024-02-22 | - | delayed |
| Garden City datacenter outage durationfacility timeline - Garden City | 2024-02-14 | 2024-02-17 | 3.0 days | delayed |
| Potential material revenue impact from Garden City outage in Q1 2024guidance | 2024-02-14 | 2024-02-29 | - | delayed |
| Ellendale datacenter power outage beganfacility timeline - Ellendale | 2024-02-08 | - | - | stated |
| Ellendale facility expected restorationfacility timeline - Ellendale | 2024-02-08 | - | - | stated |
| Ellendale facility revenues materially impacted Q1 2024guidance | 2024-02-08 | - | - | stated |
| B. Riley term loan early terminationfinancing | 2024-02-05 | - | - | stated |
| AI Bridge Funding unsecured loanfinancing | 2024-02-05 | 2026-01-30 | 20000000.0 USD | delayed |
| Jason Zhang consultant rolepersonnel | 2023-11-16 | - | - | stated |
| RSU grant April 2024personnel | 2023-11-16 | 2024-04-04 | 80000.0 RSUs | delayed |
| RSU grant October 2024personnel | 2023-11-16 | 2024-10-04 | 40000.0 RSUs | delayed |
| RSU grant April 2025personnel | 2023-11-16 | 2025-04-04 | 40000.0 RSUs | delayed |
| RSU grant October 2025personnel | 2023-11-16 | 2025-10-04 | 40000.0 RSUs | delayed |
| RSU grant April 2026personnel | 2023-11-16 | 2026-04-04 | 40000.0 RSUs | delayed |
| RSU grant November 2024personnel | 2023-11-16 | 2024-11-07 | 613152.0 RSUs | delayed |
| Marcum LLP appointed as independent auditorregulatory | 2023-11-12 | 2024-05-31 | - | delayed |
| Board of directors electedpersonnel | 2023-11-12 | - | - | stated |
As reported in the company's DEF 14A Summary Compensation Table (SEC Reg S-K Item 402(c)). Stock and option awards are grant-date fair values — what the award was worth on the day it was granted, not cash received and not what it is worth now. Every row here reconciles: its columns add up to the total the filing printed.