Polaris Forge 3

Project of Applied Digital

Kind
datacenter
Location
Oliver County, North Dakota
County
Oliver
State/region
ND
Country
US
Status
under construction as of October 16, 2026

Where it stands

Applied Digital's 10-Q filed October 7, 2026 says both Polaris Forge 3 buildings, 300 MW in total, are under construction. The campus is leased to a tier-one investment-grade hyperscaler, with expected delivery from 2H 2027 to 2H 2028. As of mid-October 2026 its project financing was still pending, and a separate 1,200 MW gas plant from Base Electron is intended to supply power to the campus, with deliveries expected in 2030. Analysts report talks about a 150 MW expansion, but no contract is disclosed.

300 MW under construction

PhaseMWStatusDateSource
Buildings 1-2 (aggregate)300under constructionOur two buildings at our Polaris Forge 3 campus, with an aggregate 300MW capacity, are currently under construction.
2026-10-07 View cached copy (2026-10-08)Live source ↗

Assessed October 18, 2026 from the newest filings, releases and reporting that name this project (newest relied on: October 16, 2026).

Capacity

What has actually been delivered, against what has been promised. Each figure links to the statement it came from.

StageCapacityAs ofSource
Energized power flowing today--
Contracted a customer is on the hook300 MW IT load2026-10-08Hyperscaler leases at Polaris Forge 3
Under construction300 MW IT load2026-09-01Polaris Forge 3 300 MW under construction
Permitted--
Interconnect approved utility has agreed to deliver--
Interconnect requested in a queue, nothing approved--
Announced a press-release figure300 MW2026-10-08Polaris Forge 3 initial operations

Who has claimed this site

Capacity commitments in the order they were announced. A commitment that ended shows why.

2026-07-26
Undisclosed counterparty (one or more) - tenant · 300 MW · 15-year term source

Claims about this project

2026-05-20 - stated
Polaris Forge 3 operations start date. Promised by 2027-08-01.
2026-05-20 - stated
2026-05-20 - stated
2026-07-27 - stated
Polaris Forge 3 Lease (300 MW) 7.5 billion USD. Promised by 2027-01-01.
2026-07-27 - stated
Polaris Forge 3 hyperscaler lease 7500000000.0 USD. Promised by 2027-12-31.
2026-07-28 - stated
Polaris Forge 3 expected delivery 300.0 MW. Promised by 2028-06-30.
2026-07-28 - stated
Polaris Forge 3 contracted capacity and revenue 7500.0 USD. Promised by 2028-12-31.
2026-07-28 - stated
2026-07-29 - stated
2026-07-29 - stated
Polaris Forge 3 hyperscaler leases 300 MW 7500000000.0 USD. Promised by 2028-12-31.
2026-09-01 - stated
2026-09-17 - withdrawn
2026-09-25 - stated
High-grade hyperscaler Polaris Forge 3 lease 300.0 MW. Promised by 2028-12-31.
2026-09-29 - stated
Polaris Forge 3 delivery dates 300.0 MW. Promised by 2028-12-31.
2026-10-03 - stated
Polaris Forge 3 delivery 300.0 MW. Promised by 2028-12-31.
2026-10-06 - stated
Polaris Forge 3 delivery 300.0 MW. Promised by 2028-12-31.
2026-10-08 - stated
Hyperscaler leases at Polaris Forge 3 300.0 MW. Promised by 2028-12-31.
2026-10-08 - stated
2026-10-08 - stated