Polaris Forge 3 expected delivery

Company: Applied Digital - Project: Polaris Forge 3

Subject kind
facility timeline
Statement date
2026-07-28
Promised by
2028-06-30
Promised amount
300.0 MW
Current status
stated

The claim, verbatim

Polaris Forge 3 expected delivery beginning second half of 2027 through second half of 2028

Source (primary)

Applied Digital 10-K filed 2026-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-30)Live source ↗

Quote: “with expected delivery beginning in the second half of calendar year 2027 through the second half of calendar year 2028”

How we checked this

Checked on September 13, 2026. The cited source supports every part of this claim.

The 10-K gives this expected delivery window for Polaris Forge 3, and the lease portfolio table matches it (2H27–2H28).

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487926000048/apld-20260531.htm) in full (594,188 characters, retrieved August 30, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 10-K filed 2026-07-29

Quote: “with expected delivery beginning in the second half of calendar year 2027 through the second half of calendar year 2028”

View cached copy (2026-08-30)Live source ↗