Dorothy 3
Project of Applied Digital
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | -- | ||
| Contracted a customer is on the hook | -- | ||
| Under construction | -- | ||
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 50 MW | 2026-10-22 | Soluna–Applied Digital 50-MW wind-powered Texas data centre |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2026-10-21
ChronoScale Holdings - tenant source
Claims about this project
2026-10-21 - stated
2026-10-21 - stated
2026-10-21 - stated
Soluna JV agreement expected to close by year-end 2026. Promised by 2026-12-31.
2026-10-21 - stated
Soluna JV agreement completion by year-end. Promised by 2026-12-31.
2026-10-21 - stated
2026-10-21 - stated
2026-10-21 - stated
2026-10-21 - stated
2026-10-21 - stated
2026-10-21 - stated
2026-10-21 - stated
Joint venture with Soluna Holdings for Texas data center. Promised by 2026-12-31.
2026-10-21 - stated
Applied's 51% stake in the Soluna JV 51.0 percent.
2026-10-21 - stated
2026-10-21 - stated
2026-10-21 - stated
Soluna JV ownership split 51.0 percent.
2026-10-21 - stated
2026-10-21 - stated
2026-10-21 - stated
2026-10-21 - stated
2026-10-21 - stated
JV ownership: Applied Digital 51% controlling interest 51.0 percent.
2026-10-21 - stated
Project Dorothy 3 power source 150.0 MW.
2026-10-21 - stated
Soluna JV closing by year-end. Promised by 2026-12-31.
2026-10-21 - stated
2026-10-21 - stated
2026-10-21 - stated
2026-10-21 - stated
Applied Digital 51% JV stake and development capital 51.0 percent.
2026-10-22 - stated
Site intelligence
Analytical estimate. Each site below is located from public records (filings, releases, news, OpenStreetMap) and checked against free satellite imagery; "How we located this site" lists every step and the score it earned. The conclusion is computed from night-time lights, surface heat and year-over-year change, with the dates it rests on. These are hypotheses under active tracking, not legal parcels or an official endorsement.
near Silverton, Texas
Weak Briscoe County, TX
34.4742, -101.3046
Approximate address 603 Lone Star St, Silverton, TX 79257, USA Reverse-geocoded from the candidate centroid; not a permit-confirmed parcel address.
Conclusion so far We have not located the site yet. · confidence 30%
Undetermined: we have not yet located the actual site, only the town or county it is in, so imagery cannot say whether anything is running.
What would change this: A published address, parcel, coordinates or permit for the site itself.
Latest clear imagery: Google 2026-10-23
How we located this site
5/100 (weak): locality location 5
- Starting point (the project's stated locality) 2026-10-23
near Silverton, Texas → 34.47423, -101.30460 (locality) - No site-level evidence yet 2026-10-23
no address, road, landmark or coordinates tie this project to a specific parcel yet -- the town is shown, NOT the site - OpenStreetMap features nearby 2026-10-23
0 named match(es)