Applied Digital–Soluna JV for Project Dorothy 3
Company: Applied Digital
The claim, verbatim
Applied Digital entered a definitive agreement with Soluna to form a Project Company to develop a planned 50 MW critical IT AI/HPC data center at Project Dorothy 3; Applied provides development capital and holds 51%.
Source (primary)
Soluna Agrees Joint Venture with Applied Digital to Build 50 MW Wind-Powered AI Data Center - TradingView (-, news_article)
View cached copy (2026-10-24)Live source ↗Archive.org ↗
Quote: “Definitive agreement to form a Project Company with Applied Digital to develop a 50 MW critical IT AI/HPC facility. Soluna to contribute land and power-related assets from Dorothy 3; Applied to provide development capital; Applied to hold 51%.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Soluna Agrees Joint Venture with Applied Digital to Build 50 MW Wind-Powered AI Data Center - TradingView
Quote: “Definitive agreement to form a Project Company with Applied Digital to develop a 50 MW critical IT AI/HPC facility. Soluna to contribute land and power-related assets from Dorothy 3; Applied to provide development capital; Applied to hold 51%.”