Garden City
Project of Applied Digital
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | -- | ||
| Contracted a customer is on the hook | -- | ||
| Under construction | 200 MW | 2026-09-01 | Garden City, Texas 200 MW facility energization |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 200 MW | 2026-09-01 | Garden City facility planned capacity |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2026-09-01
Marathon Digital Holdings - offtaker source
Claims about this project
2024-02-14 - delayed
2024-08-28 - delayed
2024-09-10 - stated
Garden City sale escrow funds release 25000000.0 USD.
2024-10-03 - delayed
2024-10-17 - stated
Garden City escrow release 25.0 USD.
2025-10-08 - stated
Garden City facility divestiture 25000.0 USD.
2026-09-01 - delayed
2026-09-01 - delayed
Oncor equipment installation completion at Garden City facility. Promised by 2023-10-23.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - delayed
Garden City facility energization. Promised by 2023-02-28.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
Garden City facility 200MW capacity 200.0 MW.
2026-09-01 - stated
2026-09-01 - stated
Garden City Texas facility capacity 200.0 MW.
2026-09-01 - stated
Garden City facility planned capacity 200.0 MW.
2026-09-01 - stated
2026-09-01 - delayed
Garden City facility energization Q4 2022. Promised by 2022-12-31.