Garden City TX facility expected Q2 2023 operation
Company: Applied Digital - Project: Garden City
What the later record shows
Delivered late · happened November 30, 2023
Expected to begin operating in calendar Q2 2023. The 10-K pushed this to H2 2023, and energizing began in the quarter ended November 30, 2023.
“The facility is expected to begin operating in the second half of calendar 2023 and the 200 MW capacity is fully contracted with our customers.”
2023-08-01 · Applied Digital 10-K filed 2023-08-02 View cached copy (2026-09-13)Live source ↗
“to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The Garden City, Texas facility is expected to begin operating in calendar Q2 2023
Source (primary)
Applied Digital S-3 filed 2023-05-17 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “The facility is expected to begin operating in calendar Q2 of 2023”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The filing states that the Garden City, TX datacenter facility is expected to begin operating in calendar Q2 of 2023.
Confirmed in the source:
- The Garden City, Texas facility was expected to begin operating in calendar Q2 2023
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487923000148/apld-forms3shelfregistrati.htm) in full (99,038 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital S-3 filed 2023-05-17
Quote: “The facility is expected to begin operating in calendar Q2 of 2023”
confirms Applied Digital 10-Q filed 2024-01-16
Quote: “to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
confirms Applied Digital 10-K filed 2023-08-02
Quote: “The facility is expected to begin operating in the second half of calendar 2023 and the 200 MW capacity is fully contracted with our customers.”