Garden City, Texas facility energization planned for Q2 2023
Company: Applied Digital - Project: Garden City
The claim, verbatim
Applied Digital expects its facility in Garden City, Texas to begin energizing during the second calendar quarter of 2023
Source (primary)
Applied Digital 424B5 filed 2023-06-26 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Further, we expect our facility in Garden City, Texas to begin energizing during the second calendar quarter of 2023.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Applied Digital 424B5 filed 2023-06-26
Quote: “Further, we expect our facility in Garden City, Texas to begin energizing during the second calendar quarter of 2023.”
Record of changes
September 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 14, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.