Garden City, Texas facility energization planned for Q2 2023

Company: Applied Digital - Project: Garden City

Subject kind
facility timeline
Statement date
2023-06-25
Promised by
2023-06-30
Current status
verified

What the later record shows

Delivered late · happened November 30, 2023

Energizing was expected in calendar Q2 2023. The October 2023 10-Q moved it to Q4 2023, and energizing began in the quarter ended November 30, 2023.

“The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”
2023-10-09 · Applied Digital 10-Q filed 2023-10-10 View cached copy (2026-08-31)Live source ↗
“to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Applied Digital expects its facility in Garden City, Texas to begin energizing during the second calendar quarter of 2023

Source (primary)

Applied Digital 424B5 filed 2023-06-26 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Further, we expect our facility in Garden City, Texas to begin energizing during the second calendar quarter of 2023.”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The prospectus supplement, dated June 26, 2023, states this expectation directly. It does not confirm whether energization actually happened.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487923000166/apld-preliminaryprospectus.htm) in full (176,255 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 424B5 filed 2023-06-26

Quote: “Further, we expect our facility in Garden City, Texas to begin energizing during the second calendar quarter of 2023.”

View cached copy (2026-09-13)Live source ↗

confirms Applied Digital 10-Q filed 2023-10-10

Quote: “The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”

View cached copy (2026-08-31)Live source ↗

confirms Applied Digital 10-Q filed 2024-01-16

Quote: “to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 14, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.