Garden City, Texas facility energization planned for Q2 2023
Company: Applied Digital - Project: Garden City
What the later record shows
Delivered late · happened November 30, 2023
Energizing was expected in calendar Q2 2023. The October 2023 10-Q moved it to Q4 2023, and energizing began in the quarter ended November 30, 2023.
“The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”
2023-10-09 · Applied Digital 10-Q filed 2023-10-10 View cached copy (2026-08-31)Live source ↗
“to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Applied Digital expects its facility in Garden City, Texas to begin energizing during the second calendar quarter of 2023
Source (primary)
Applied Digital 424B5 filed 2023-06-26 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Further, we expect our facility in Garden City, Texas to begin energizing during the second calendar quarter of 2023.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The prospectus supplement, dated June 26, 2023, states this expectation directly. It does not confirm whether energization actually happened.
Confirmed in the source:
- As of June 2023, Applied Digital expected its Garden City, Texas facility to begin energizing during the second calendar quarter of 2023
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487923000166/apld-preliminaryprospectus.htm) in full (176,255 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 424B5 filed 2023-06-26
Quote: “Further, we expect our facility in Garden City, Texas to begin energizing during the second calendar quarter of 2023.”
confirms Applied Digital 10-Q filed 2023-10-10
Quote: “The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”
confirms Applied Digital 10-Q filed 2024-01-16
Quote: “to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”