Second datacenter facility Garden City, Texas - capacity and opening

Company: Applied Digital - Project: Garden City

Subject kind
facility capacity
Statement date
2022-09-26
Promised by
2022-10-01
Promised amount
200.0 MW
Current status
verified

What the later record shows

Delivered late

The 200 MW facility was still unenergized in October 2023 against a Q4 2022 target. A later presentation lists the 200 MW Garden City data center as launched, with no exact date. The facility was sold to Marathon on April 1, 2024.

“The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”
2023-10-09 · Applied Digital 10-Q filed 2023-10-10 View cached copy (2026-08-31)Live source ↗
“agreed to sell to Mara Garden City LLC its datacenter facility located in Garden City, Texas (the “Garden City Transaction”). The Garden City Transaction closed on April 1, 2024.”
2024-04-10 · Applied Digital 10-Q filed 2024-04-11 View cached copy (2026-08-31)Live source ↗
“Launched 200 MW Blockchain Data Center, in Garden City, TX Completed IPO and uplisted to NASDAQ”
2026-10-03 · Investor Presentation View cached copy (2026-10-03)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Applied Digital's second co-hosting facility in Garden City, Texas, collocated with a wind farm, is expected to provide 200 MW of power to hosting customers. The facility is expected to begin operating in Q4 2022 with 200 MW capacity fully contracted.

Source (primary)

Applied Digital 424B3 filed 2022-09-27 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “This facility is collocated with a wind farm and upon completion is expected to provide 200 MW of power to hosting customers. The facility is expected to begin operating in calendar Q4 of 2022 and the 200 MW capacity is fully contracted with our customers.”

How we checked this

Checked on October 11, 2026. The cited source supports part of this claim, but not all of it.

The prospectus supports every detail about the Garden City facility: the wind farm, the 200 MW, the Q4 2022 start, and that it was fully contracted. However, it names the company Applied Blockchain, Inc., and nothing in this document links that company to the name Applied Digital.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487922000044/a9262022424b3finalprospect.htm) in full (350,225 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 424B3 filed 2022-09-27

Quote: “This facility is collocated with a wind farm and upon completion is expected to provide 200 MW of power to hosting customers. The facility is expected to begin operating in calendar Q4 of 2022 and the 200 MW capacity is fully contracted with our customers.”

View cached copy (2026-09-13)Live source ↗

confirms Applied Digital 10-Q filed 2023-10-10

Quote: “The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”

View cached copy (2026-08-31)Live source ↗

confirms Applied Digital 10-Q filed 2024-04-11

Quote: “agreed to sell to Mara Garden City LLC its datacenter facility located in Garden City, Texas (the “Garden City Transaction”). The Garden City Transaction closed on April 1, 2024.”

View cached copy (2026-08-31)Live source ↗

confirms Investor Presentation

Quote: “Launched 200 MW Blockchain Data Center, in Garden City, TX Completed IPO and uplisted to NASDAQ”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.