Garden City Oncor metering installation

Company: Applied Digital - Project: Garden City

Subject kind
facility timeline
Statement date
2023-10-09
Promised by
2023-10-23
Current status
verified

What the later record shows

Delivered; the record does not say when

The site was to be energized once Oncor's installation was done, and energization began in the quarter ended November 30, 2023. That implies the installation was completed, but no passage says whether it finished by October 23.

“provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Oncor metering and telemetry installation at Garden City expected to be completed by October 23, after which the site will be energized.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-03)Live source ↗Archive.org ↗

Quote: “The installation is expected to be completed by October 23rd.”

How we checked this

Checked on October 12, 2026. The cited source supports every part of this claim.

The release's Garden City passage says Oncor will install metering and telemetry equipment onsite, that the site will be energized once installed, and that installation is expected to be completed by October 23rd.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/72/applied-digital-reports-fiscal-first-quarter-2024-financial/) in full (23,346 characters, retrieved October 3, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “The installation is expected to be completed by October 23rd.”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “The installation is expected to be completed by October 23rd.”

View cached copy (2026-10-06)Live source ↗

confirms Applied Digital 10-Q filed 2024-01-16

Quote: “provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility”

View cached copy (2026-08-31)Live source ↗

Record of changes

October 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-10-03 was the source's retrieval date; source published 2023-10-09.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.