Oncor equipment installation completion at Garden City facility

Company: Applied Digital - Project: Garden City

Subject kind
facility timeline
Statement date
2023-10-09
Promised by
2023-10-23
Current status
verified

What the later record shows

Delivered; the record does not say when

The site began energizing in the quarter ended November 30, 2023, which implies the Oncor installation was finished. The completion date versus October 23 is not given.

“provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Oncor metering and telemetry equipment installation at Garden City facility expected to be completed by October 23, 2023

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “The installation is expected to be completed by October 23rd.”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

In the Garden City update, the release says Oncor will install metering and telemetry equipment onsite. It says that installation is expected to be completed by October 23rd.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/72/applied-digital-reports-fiscal-first-quarter-2024-financial/) in full (23,308 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “The installation is expected to be completed by October 23rd.”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms Applied Digital 10-Q filed 2024-01-16

Quote: “provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2023-10-09.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.