jain.com

Texas facility construction start

Company: Applied Digital - Project: Garden City

Subject kind
facility timeline
Statement date
2022-08-28
Event date
2022-04-25
Current status
stated

What the later record shows

Not a promise: a reported event · happened April 25, 2022

The claim reports that construction had already started on April 25, 2022. The FY2023 10-K restates that date.

“On April 25, 2022, we began construction on this site. This facility is collocated with a wind farm”
2023-08-01 · Applied Digital 10-K filed 2023-08-02 View cached copy (2026-09-13)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Construction began on Garden City, Texas facility on April 25, 2022

Source (primary)

Applied Digital 10-K filed 2022-08-29 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “On April 25, 2022 the Company began construction on this site.”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The filing states the company began construction on the Garden City, TX site on April 25, 2022.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000162828022023816/apld-20220531.htm) in full (312,378 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 10-K filed 2022-08-29

Quote: “On April 25, 2022 the Company began construction on this site.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.