First Texas 200MW wind site
Company: Applied Digital - Project: Garden City
What the later record shows
Delivered late · happened November 30, 2023
Promised operational in H2 2022; energizing only began in the quarter ended November 30, 2023, and the company later lists the 200 MW Garden City center as launched.
“to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗
“Launched 200 MW Blockchain Data Center, in Garden City, TX”
2026-04-22 · applied-digital 8-K exhibit (apld_invxinvestorpresent.htm) View cached copy (2026-09-09)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Texas facility with 200MW of wind power began construction in April 2022 and is expected to be operational in the latter half of calendar 2022.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-06)Live source ↗Archive.org ↗
Quote: “Construction of the facility began in April 2022 and is expected to be operational in the latter half of the calendar year”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The release, dated May 2022, describes the 200MW Texas wind facility, an April 2022 construction start, and expected operation in the latter half of the calendar year.
Confirmed in the source:
- Applied Blockchain planned a Texas facility with 200MW of wind power.
- Construction of the Texas facility began in April 2022.
- The Texas facility was expected to be operational in the latter half of calendar 2022.
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/10/applied-blockchain-reports-fiscal-third-quarter-2022-ended/) in full (19,893 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “Construction of the facility began in April 2022 and is expected to be operational in the latter half of the calendar year”
confirms Earnings Release
Quote: “Construction of the facility began in April 2022 and is expected to be operational in the latter half of the calendar year.”
confirms Applied Digital 10-Q filed 2024-01-16
Quote: “to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
confirms applied-digital 8-K exhibit (apld_invxinvestorpresent.htm)
Quote: “Launched 200 MW Blockchain Data Center, in Garden City, TX”