First Texas 200MW wind site

Company: Applied Digital - Project: Garden City

Subject kind
facility timeline
Statement date
2022-05-13
Promised by
2022-12-31
Promised amount
200.0 MW
Current status
verified

What the later record shows

Delivered late · happened November 30, 2023

Promised operational in H2 2022; energizing only began in the quarter ended November 30, 2023, and the company later lists the 200 MW Garden City center as launched.

“to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗
“Launched 200 MW Blockchain Data Center, in Garden City, TX”
2026-04-22 · applied-digital 8-K exhibit (apld_invxinvestorpresent.htm) View cached copy (2026-09-09)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Texas facility with 200MW of wind power began construction in April 2022 and is expected to be operational in the latter half of calendar 2022.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-06)Live source ↗Archive.org ↗

Quote: “Construction of the facility began in April 2022 and is expected to be operational in the latter half of the calendar year”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The release, dated May 2022, describes the 200MW Texas wind facility, an April 2022 construction start, and expected operation in the latter half of the calendar year.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/10/applied-blockchain-reports-fiscal-third-quarter-2022-ended/) in full (19,893 characters, retrieved October 6, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “Construction of the facility began in April 2022 and is expected to be operational in the latter half of the calendar year”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Construction of the facility began in April 2022 and is expected to be operational in the latter half of the calendar year.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

confirms Applied Digital 10-Q filed 2024-01-16

Quote: “to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”

View cached copy (2026-08-31)Live source ↗

confirms applied-digital 8-K exhibit (apld_invxinvestorpresent.htm)

Quote: “Launched 200 MW Blockchain Data Center, in Garden City, TX”

View cached copy (2026-09-09)Live source ↗

Record of changes

October 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 7, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-10-06 was the source's retrieval date; source published 2022-05-13.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.