jain.com

Texas wind facility letter of intent

Company: Applied Digital - Project: Garden City

Subject kind
facility capacity
Statement date
2022-03-20
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

Letter of intent entered into November 24, 2021 to develop facility in Texas with 200MW of wind power, subject to definitive agreements

Source (primary)

Applied Digital S-1/A filed 2022-03-21 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “On November 24, 2021, we entered into a letter of intent to develop a facility in Texas with 200MW of wind power. The arrangement is subject to entry into definitive agreements by the parties”

How we checked this

Checked on September 22, 2026. The cited source supports every part of this claim.

The document confirms the November 24, 2021 letter of intent, the 200MW Texas wind facility, and the condition of definitive agreements.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000110465922036163/tm2124821-21_s1a.htm) in full (555,375 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital S-1/A filed 2022-03-21

Quote: “On November 24, 2021, we entered into a letter of intent to develop a facility in Texas with 200MW of wind power. The arrangement is subject to entry into definitive agreements by the parties”

View cached copy (2026-09-13)Live source ↗