Second facility expected operational date

Company: Applied Digital - Project: Garden City

Subject kind
facility timeline
Statement date
2022-08-28
Promised by
2022-10-01
Current status
verified

What the later record shows

Delivered late

Operation was pushed from Q4 2022 to February 2023, then to the second half of 2023, then to Q4 calendar 2023. A later investor presentation says the 200 MW Garden City data center was launched, which was after Q4 2022, but no exact date is given.

“The site is currently expected to energize before the end of February.”
2023-01-09 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”
2023-10-09 · Applied Digital 10-Q filed 2023-10-10 View cached copy (2026-08-31)Live source ↗
“Launched 200 MW Blockchain Data Center, in Garden City, TX Completed IPO and uplisted to NASDAQ”
2026-10-03 · Investor Presentation View cached copy (2026-10-03)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Second facility in Garden City, Texas expected to begin operating in calendar Q4 2022

Source (primary)

Applied Digital 10-K filed 2022-08-29 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “The facility is expected to begin operating in calendar Q4 of 2022 and the 200 MW capacity is fully contracted with our customers.”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The filing states the Garden City facility was expected to begin operating in calendar Q4 of 2022.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000162828022023816/apld-20220531.htm) in full (312,378 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 10-K filed 2022-08-29

Quote: “The facility is expected to begin operating in calendar Q4 of 2022 and the 200 MW capacity is fully contracted with our customers.”

View cached copy (2026-09-13)Live source ↗

confirms Applied Digital 10-Q filed 2023-10-10

Quote: “The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”

View cached copy (2026-08-31)Live source ↗

confirms Investor Presentation

Quote: “Launched 200 MW Blockchain Data Center, in Garden City, TX Completed IPO and uplisted to NASDAQ”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “The site is currently expected to energize before the end of February.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.