Five hosting customers at second facility

Company: Applied Digital - Project: Garden City

Subject kind
customer
Statement date
2022-09-15
Promised amount
85.0 MW
Current status
stated

The claim, verbatim

Five customers contracted to utilize 85 MW at second facility once constructed and operational

Source (primary)

Applied Digital S-1 filed 2022-09-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “We also entered into agreements with five customers...and 85MW of energy at our second facility, once it is built and able to provide such energy.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital S-1 filed 2022-09-16

Quote: “We also entered into agreements with five customers...and 85MW of energy at our second facility, once it is built and able to provide such energy.”

View cached copy (2026-09-13)Live source ↗