Garden City TX facility capacity

Company: Applied Digital - Project: Garden City

Subject kind
facility capacity
Statement date
2023-05-16
Promised by
2023-06-30
Promised amount
200.0 MW
Current status
verified

What the later record shows

Delivered late · happened November 30, 2023

The 200 MW facility was due by Q2 2023. Energizing began in the quarter ended November 30, 2023, and the company later lists the 200 MW Garden City data center as launched. No passage says when the full 200 MW was reached.

“to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗
“Launched 200 MW Blockchain Data Center, in Garden City, TX”
2026-04-22 · applied-digital 8-K exhibit (apld_invxinvestorpresent.htm) View cached copy (2026-09-09)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The Garden City, Texas facility is expected to provide 200 MW of power to hosting customers with capacity fully contracted

Source (primary)

Applied Digital S-3 filed 2023-05-17 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “This facility is collocated with a wind farm and upon completion is expected to provide 200 MW of power to hosting customers. The facility is expected to begin operating in calendar Q2 of 2023 and the 200 MW capacity is fully contracted with our customers.”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The filing says the Garden City facility is expected to provide 200 MW of power to hosting customers upon completion and that the 200 MW capacity is fully contracted.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487923000148/apld-forms3shelfregistrati.htm) in full (99,038 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital S-3 filed 2023-05-17

Quote: “This facility is collocated with a wind farm and upon completion is expected to provide 200 MW of power to hosting customers. The facility is expected to begin operating in calendar Q2 of 2023 and the 200 MW capacity is fully contracted with our customers.”

View cached copy (2026-09-13)Live source ↗

confirms Applied Digital 10-Q filed 2024-01-16

Quote: “to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”

View cached copy (2026-08-31)Live source ↗

confirms applied-digital 8-K exhibit (apld_invxinvestorpresent.htm)

Quote: “Launched 200 MW Blockchain Data Center, in Garden City, TX”

View cached copy (2026-09-09)Live source ↗

Record of changes

September 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 14, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.