Texas facility expected opening
Company: Applied Digital - Project: Garden City
What the later record shows
Delivered late
The facility was still not energized in January 2023 or in October 2023, when energization was expected in Q4 calendar 2023. It was later described as launched, so it came after Q4 2022, with no exact date.
“The site is currently expected to energize before the end of February.”
2023-01-09 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”
2023-10-09 · Applied Digital 10-Q filed 2023-10-10 View cached copy (2026-08-31)Live source ↗
“Launched 200 MW Blockchain Data Center, in Garden City, TX Completed IPO and uplisted to NASDAQ”
2026-10-03 · Investor Presentation View cached copy (2026-10-03)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The Garden City, Texas co-hosting facility is expected to begin operating in calendar Q4 of 2022
Source (primary)
Applied Digital 10-K filed 2022-08-29 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “The facility is expected to begin operating in calendar Q4 of 2022”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The 10-K states this expectation for the Garden City, TX facility.
Confirmed in the source:
- The Garden City, Texas co-hosting facility was expected to begin operating in calendar Q4 2022
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000162828022023816/apld-20220531.htm) in full (312,378 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 10-K filed 2022-08-29
Quote: “The facility is expected to begin operating in calendar Q4 of 2022”
confirms Applied Digital 10-Q filed 2023-10-10
Quote: “The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”
confirms Investor Presentation
Quote: “Launched 200 MW Blockchain Data Center, in Garden City, TX Completed IPO and uplisted to NASDAQ”
confirms Earnings Release
Quote: “The site is currently expected to energize before the end of February.”