Texas facility expected opening

Company: Applied Digital - Project: Garden City

Subject kind
facility timeline
Statement date
2022-08-28
Promised by
2022-10-01
Current status
verified

What the later record shows

Delivered late

The facility was still not energized in January 2023 or in October 2023, when energization was expected in Q4 calendar 2023. It was later described as launched, so it came after Q4 2022, with no exact date.

“The site is currently expected to energize before the end of February.”
2023-01-09 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”
2023-10-09 · Applied Digital 10-Q filed 2023-10-10 View cached copy (2026-08-31)Live source ↗
“Launched 200 MW Blockchain Data Center, in Garden City, TX Completed IPO and uplisted to NASDAQ”
2026-10-03 · Investor Presentation View cached copy (2026-10-03)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The Garden City, Texas co-hosting facility is expected to begin operating in calendar Q4 of 2022

Source (primary)

Applied Digital 10-K filed 2022-08-29 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “The facility is expected to begin operating in calendar Q4 of 2022”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The 10-K states this expectation for the Garden City, TX facility.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000162828022023816/apld-20220531.htm) in full (312,378 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 10-K filed 2022-08-29

Quote: “The facility is expected to begin operating in calendar Q4 of 2022”

View cached copy (2026-09-13)Live source ↗

confirms Applied Digital 10-Q filed 2023-10-10

Quote: “The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”

View cached copy (2026-08-31)Live source ↗

confirms Investor Presentation

Quote: “Launched 200 MW Blockchain Data Center, in Garden City, TX Completed IPO and uplisted to NASDAQ”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “The site is currently expected to energize before the end of February.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.