Garden City, Texas datacenter facility

Company: Applied Digital - Project: Garden City

Subject kind
facility timeline
Statement date
2023-05-16
Promised by
2023-06-30
Current status
verified

What the later record shows

Delivered late · happened November 30, 2023

Expected to begin operating in calendar Q2 2023; energizing began in the quarter ended November 30, 2023. By February 2024 the facility was being re-energized after maintenance, so it had been operating.

“to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗
“On February 23, 2024, we began re-energizing our Garden City facility, which was de-energized on February 14, 2024”
2024-07-18 · Applied Digital 8-K filed 2024-07-19 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Facility expected to begin operating in calendar Q2 2023

Source (primary)

Applied Digital S-3 filed 2023-05-17 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “The facility is expected to begin operating in calendar Q2 of 2023 and the 200 MW capacity is fully contracted with our customers.”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The May 2023 S-3 says the facility on the Garden City, TX ground-lease site is expected to begin operating in calendar Q2 of 2023.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487923000148/apld-forms3shelfregistrati.htm) in full (99,038 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital S-3 filed 2023-05-17

Quote: “The facility is expected to begin operating in calendar Q2 of 2023 and the 200 MW capacity is fully contracted with our customers.”

View cached copy (2026-09-13)Live source ↗

confirms Applied Digital 10-Q filed 2024-01-16

Quote: “to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”

View cached copy (2026-08-31)Live source ↗

confirms Applied Digital 8-K filed 2024-07-19

Quote: “On February 23, 2024, we began re-energizing our Garden City facility, which was de-energized on February 14, 2024”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 13, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 14, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.