jain.com

Letter of intent for Texas facility development

Company: Applied Digital - Project: Garden City

Subject kind
facility timeline
Statement date
2022-03-27
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

Letter of intent dated November 24, 2021 to develop facility in Texas with 200MW of wind power, subject to definitive agreements

Source (primary)

Applied Digital S-1/A filed 2022-03-28 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “On November 24, 2021, we entered into a letter of intent to develop a facility in Texas with 200MW of wind power. The arrangement is subject to entry into definitive agreements by the parties”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital S-1/A filed 2022-03-28

Quote: “On November 24, 2021, we entered into a letter of intent to develop a facility in Texas with 200MW of wind power. The arrangement is subject to entry into definitive agreements by the parties”

View cached copy (2026-09-13)Live source ↗