Garden City, TX facility expected launch date
Company: Applied Digital - Project: Garden City
What the later record shows
Delivered late · happened November 30, 2023
Expected to begin operating in Q4 2022; the date slipped repeatedly and energizing began only in the quarter ended November 30, 2023.
“The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”
2023-10-09 · Applied Digital 10-Q filed 2023-10-10 View cached copy (2026-08-31)Live source ↗
“to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Second facility in Garden City, TX expected to begin operating in calendar Q4 2022
Source (primary)
Applied Digital 424B3 filed 2022-10-11 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “The facility is expected to begin operating in calendar Q4 of 2022”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The prospectus states the company entered a 99-year ground lease in Garden City, TX to build its second datacenter facility, and that this facility is expected to begin operating in calendar Q4 of 2022.
Confirmed in the source:
- The company's second datacenter facility is in Garden City, TX
- The Garden City, TX facility was expected to begin operating in calendar Q4 2022
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000114487922000048/aplds1finalresaleseptember.htm) in full (349,714 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 424B3 filed 2022-10-11
Quote: “The facility is expected to begin operating in calendar Q4 of 2022”
confirms Applied Digital 10-Q filed 2023-10-10
Quote: “The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar 2023.”
confirms Applied Digital 10-Q filed 2024-01-16
Quote: “to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”