Oncor facility extension agreement for Garden City
Company: Applied Digital - Project: Garden City
What the later record shows
Delivered; the record does not say when
The facility began energizing in the quarter ended November 30, 2023, which implies the Oncor metering installation was done. Its exact completion date relative to October 23 is not stated.
“provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
On Sept 8, 2023 the company entered a facility extension agreement with Oncor for power transmission and metering; installation expected to be completed by October 23, after which the site will be energized.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗
Quote: “On September 8, 2023, the Company entered into a facility extension agreement with Oncor Electricity Delivery Company LLC ("Oncor") for the transmission and metering of power... The installation is expected to be completed by October 23rd.”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The Datacenter Hosting Update describes the September 8, 2023 Oncor agreement, the October 23 expected installation completion, and energization following installation.
Confirmed in the source:
- On September 8, 2023, Applied Digital entered into a facility extension agreement with Oncor Electricity Delivery Company LLC
- The Oncor agreement covers the transmission and metering of power
- Oncor's metering and telemetry installation was expected to be completed by October 23
- The site will be energized once the installation is complete
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/72/applied-digital-reports-fiscal-first-quarter-2024-financial/) in full (23,346 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “On September 8, 2023, the Company entered into a facility extension agreement with Oncor Electricity Delivery Company LLC ("Oncor") for the transmission and metering of power... The installation is expected to be completed by October 23rd.”
confirms Applied Digital 10-Q filed 2024-01-16
Quote: “provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility”