Second facility 200 MW capacity and operational timeline

Company: Applied Digital - Project: Garden City

Subject kind
facility capacity
Statement date
2022-08-28
Promised by
2022-12-31
Promised amount
200.0 MW
Current status
verified

What the later record shows

Delivered late · happened November 30, 2023

The 200 MW facility was due to begin operating in Q4 2022; energizing began in the quarter ended November 30, 2023, and it was later described as launched before its April 2024 sale.

“to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗
“Launched 200 MW Blockchain Data Center, in Garden City, TX”
2026-04-22 · applied-digital 8-K exhibit (apld_invxinvestorpresent.htm) View cached copy (2026-09-09)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Second facility collocated with wind farm, expected to provide 200 MW of power, expected to begin operating Q4 2022 with capacity fully contracted

Source (primary)

Applied Digital 10-K filed 2022-08-29 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “This facility is collocated with a wind farm and upon completion is expected to provide 200 MW of power to hosting customers. The facility is expected to begin operating in calendar Q4 of 2022 and the 200 MW capacity is fully contracted with our customers.”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The 10-K states all four points about the Garden City facility. These were company expectations as of August 2022.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000162828022023816/apld-20220531.htm) in full (312,378 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 10-K filed 2022-08-29

Quote: “This facility is collocated with a wind farm and upon completion is expected to provide 200 MW of power to hosting customers. The facility is expected to begin operating in calendar Q4 of 2022 and the 200 MW capacity is fully contracted with our customers.”

View cached copy (2026-09-13)Live source ↗

confirms Applied Digital 10-Q filed 2024-01-16

Quote: “to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”

View cached copy (2026-08-31)Live source ↗

confirms applied-digital 8-K exhibit (apld_invxinvestorpresent.htm)

Quote: “Launched 200 MW Blockchain Data Center, in Garden City, TX”

View cached copy (2026-09-09)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.