Second facility 200 MW capacity and operational timeline
Company: Applied Digital - Project: Garden City
What the later record shows
Delivered late · happened November 30, 2023
The 200 MW facility was due to begin operating in Q4 2022; energizing began in the quarter ended November 30, 2023, and it was later described as launched before its April 2024 sale.
“to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗
“Launched 200 MW Blockchain Data Center, in Garden City, TX”
2026-04-22 · applied-digital 8-K exhibit (apld_invxinvestorpresent.htm) View cached copy (2026-09-09)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Second facility collocated with wind farm, expected to provide 200 MW of power, expected to begin operating Q4 2022 with capacity fully contracted
Source (primary)
Applied Digital 10-K filed 2022-08-29 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “This facility is collocated with a wind farm and upon completion is expected to provide 200 MW of power to hosting customers. The facility is expected to begin operating in calendar Q4 of 2022 and the 200 MW capacity is fully contracted with our customers.”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The 10-K states all four points about the Garden City facility. These were company expectations as of August 2022.
Confirmed in the source:
- The second facility (Garden City, TX) is collocated with a wind farm
- It was expected to provide 200 MW of power to hosting customers on completion
- It was expected to begin operating in calendar Q4 2022
- Its 200 MW capacity was described as fully contracted with customers
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000162828022023816/apld-20220531.htm) in full (312,378 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Applied Digital 10-K filed 2022-08-29
Quote: “This facility is collocated with a wind farm and upon completion is expected to provide 200 MW of power to hosting customers. The facility is expected to begin operating in calendar Q4 of 2022 and the 200 MW capacity is fully contracted with our customers.”
confirms Applied Digital 10-Q filed 2024-01-16
Quote: “to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
confirms applied-digital 8-K exhibit (apld_invxinvestorpresent.htm)
Quote: “Launched 200 MW Blockchain Data Center, in Garden City, TX”