Garden City, TX 200 MW energization

Company: Applied Digital - Project: Garden City

Subject kind
facility timeline
Statement date
2023-10-09
Promised by
2023-12-31
Promised amount
200.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

No passage gives an energization date. The FY2025 10-K cites power and depreciation costs tied to the Garden City facility before its sale on April 1, 2024, which implies it operated, but nothing confirms the full 200 MW or when it energized relative to Q4 2023.

“agreed to sell to Mara Garden City LLC its datacenter facility located in Garden City, Texas (the “Garden City Transaction”). The Garden City Transaction closed on April 1, 2024.”
2024-04-10 · Applied Digital 10-Q filed 2024-04-11 View cached copy (2026-08-31)Live source ↗
“Other operating expenses attributable to the Garden City facility including power and depreciation decreased by approximately $20.6 million, since this facility was sold between the periods.”
2025-07-29 · Applied Digital 10-K filed 2025-07-30 View cached copy (2026-08-31)Live source ↗

Checked November 19, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The 200 MW Garden City, Texas hosting facility is expected to energize during Q4 of calendar 2023.

Source (primary)

applied-digital 8-K exhibit (apld1q24earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-18)Live source ↗

Quote: “The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar year 2023.”

How we checked this

Checked on November 21, 2026. The cited source supports every part of this claim.

Applied Digital's October 9, 2023 earnings release states that its 200 MW Garden City, Texas facility was expected to energize in the fourth quarter of calendar 2023. It presents this facility as one of the company's three hosting facilities.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000189884423000007/apld1q24earningsrelease.htm) in full (22,391 characters, retrieved November 18, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (apld1q24earningsrelease.htm)

Quote: “The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar year 2023.”

View cached copy (2026-11-18)Live source ↗

confirms Applied Digital 10-Q filed 2024-04-11

Quote: “agreed to sell to Mara Garden City LLC its datacenter facility located in Garden City, Texas (the “Garden City Transaction”). The Garden City Transaction closed on April 1, 2024.”

View cached copy (2026-08-31)Live source ↗

confirms Applied Digital 10-K filed 2025-07-30

Quote: “Other operating expenses attributable to the Garden City facility including power and depreciation decreased by approximately $20.6 million, since this facility was sold between the periods.”

View cached copy (2026-08-31)Live source ↗

Record of changes

November 19, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 19, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.