Garden City, Texas 200 MW facility energization
Company: Applied Digital - Project: Garden City
What the later record shows
Delivered on time · happened November 30, 2023
Energization began in the quarter ended November 30, 2023, after the October 9 statement and within calendar Q4 2023. Later company timelines list the 200 MW Garden City data center as launched in 2023.
“provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗
“Launched 200 MW Blockchain Data Center, in Garden City, TX”
2026-10-03 · Investor Presentation View cached copy (2026-10-03)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
200 MW facility in Garden City, Texas expected to energize in Q4 2023
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “The Company's 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar year 2023.”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The release says the 200 MW Garden City, Texas facility is expected to energize in the fourth quarter of calendar 2023.
Confirmed in the source:
- Applied Digital's Garden City, Texas facility is 200 MW
- The Garden City facility was expected to energize during the fourth quarter of calendar year 2023
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/72/applied-digital-reports-fiscal-first-quarter-2024-financial/) in full (23,308 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “The Company's 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar year 2023.”
confirms Earnings Release
Quote: “The Company's 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar year 2023.”
confirms Earnings Release
Quote: “The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar year 2023.”
confirms Earnings Release
Quote: “The Company's 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar year 2023.”
confirms Earnings Release
Quote: “The Company's 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar year 2023.”
confirms Earnings Release
Quote: “The Company’s 200 MW facility in Garden City, Texas is expected to energize during the fourth quarter of calendar year 2023.”
confirms Applied Digital 10-Q filed 2024-01-16
Quote: “provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility”
confirms Investor Presentation
Quote: “Launched 200 MW Blockchain Data Center, in Garden City, TX”