First Texas 200MW wind-powered facility
Company: Applied Digital - Project: Garden City
What the later record shows
Delivered late · happened November 30, 2023
The facility was promised operational in H2 2022, but the 10-Q for the quarter ended November 30, 2023 says the company only then began energizing it. A 2026 presentation confirms the 200 MW Garden City data center was launched.
“During the quarter ended November 30, 2023, the Company entered into a long term 15 Table of Contents Retail Electric Service Agreement with TerraForm Power”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗
“to provide energy to the Company’s 200 MW Garden City, Texas facility and the Company began energizing the facility.”
2024-01-15 · Applied Digital 10-Q filed 2024-01-16 View cached copy (2026-08-31)Live source ↗
“Launched 200 MW Blockchain Data Center, in Garden City, TX”
2026-04-22 · applied-digital 8-K exhibit (apld_invxinvestorpresent.htm) View cached copy (2026-09-09)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The company signed an LOI on November 24, 2021 for a 200MW wind-powered facility in Texas. Construction began in April 2022, and the facility is expected to be operational in the latter half of calendar 2022.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗
Quote: “Construction of the facility began in April 2022 and is expected to be operational in the latter half of the calendar year.”
How we checked this
Checked on October 12, 2026. The cited source supports every part of this claim.
The release states the LOI date, the 200MW wind power, the April 2022 construction start, and the expected operation in the latter half of the calendar year, which is 2022 given the May 2022 release date.
Confirmed in the source:
- On November 24, 2021 the company entered a letter of intent to develop a Texas facility with 200MW of wind power
- Construction of the facility began in April 2022
- The facility was expected to be operational in the latter half of calendar 2022
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/10/applied-blockchain-reports-fiscal-third-quarter-2022-ended/) in full (19,893 characters, retrieved September 29, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “Construction of the facility began in April 2022 and is expected to be operational in the latter half of the calendar year.”
confirms Earnings Release
Quote: “entered into a letter of intent to develop a facility in Texas with 200MW of wind power. Construction of the facility began in April 2022 and is expected to be operational in the latter half of the calendar year.”
confirms Applied Digital 10-Q filed 2024-01-16
Quote: “During the quarter ended November 30, 2023, the Company entered into a long term 15 Table of Contents Retail Electric Service Agreement with TerraForm Power”
confirms applied-digital 8-K exhibit (apld_invxinvestorpresent.htm)
Quote: “Launched 200 MW Blockchain Data Center, in Garden City, TX”