Delta Forge 2
Project of Applied Digital
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | -- | ||
| Contracted a customer is on the hook | 210 MW IT load | 2026-09-01 | High Investment Grade Hyperscaler Delta Forge 2 lease |
| Under construction | 210 MW IT load | 2026-09-01 | Delta Forge 2 210 MW under construction |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 210 MW | 2026-07-28 | Delta Forge 2 expected delivery |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2026-09-01
Undisclosed counterparty (one or more) - tenant · 210 MW · 15-year term source
Claims about this project
2026-06-08 - stated
2026-06-30 - stated
15-year 210 MW hyperscaler lease 5200000000.0 USD.
2026-07-28 - stated
2026-07-28 - stated
2026-07-28 - stated
Delta Forge 2 contracted capacity and revenue 5.2 billion USD.
2026-07-28 - stated
Delta Forge 2 contracted capacity and revenue 5.2 billion USD.
2026-07-28 - stated
2026-08-18 - stated
Delta Forge 2 initial operations start. Promised by 2028-03-31.
2026-08-18 - stated
Delta Forge 2 lease base-term revenue 5.2 Billion USD.
2026-08-18 - stated
Delta Forge 2 total value with renewal options 12.7 Billion USD.
2026-08-20 - stated
2026-08-22 - stated
2026-08-22 - stated
2026-08-22 - stated
2026-08-22 - stated
2026-09-01 - stated
Delta Forge 2 210 MW under construction 210.0 MW.
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
2026-09-01 - stated
Delta Forge 2 – 210 MW hyperscaler lease 5200000000.0 USD.
2026-09-01 - stated